Attachment J - DRAFT High Level PPD Scope USCGC POLAR STAR 2021.pdf

PDF 391 KB Posted

Attached to
Request for Information: USCG POLAR STAR Service Life Extension Project (SLEP) Federal contract opportunity
Solicitation number
RFI-USCG-PSTAR-2019-3
Issued by
Department of Homeland Security US Coast Guard

About this file

This document contains a draft scope of work for electrical system upgrades aboard the USCGC POLAR STAR from fiscal years 2021 through 2023. The scope of work includes replacing voltage regulator enclosures, upgrading engine actuators, installing new controller enclosures, replacing switchboard devices, installing battery units and reverse acting governors. Electrical and mechanical personnel from the shipyard and Naval Surface Warfare Center Carderock Division engineers will perform the work in engine control centers, auxiliary machinery spaces, diesel engine rooms and other areas over a three year period. The United States Coast Guard issued a request for information to solicit industry feedback on the draft solicitation for the POLAR STAR Service Life Extension Project, which will extend the cutter's service life by recapitalizing major systems similar to previous drydock maintenance availabilities.

View the file

Other files for this federal contract opportunity

Other files attached to Request for Information: USCG POLAR STAR Service Life Extension Project (SLEP), newest first.
File Type Posted
Attachment H - POLAR STAR DRAFT Pricing Estimate Template.xlsx XLSX spreadsheet
Attachment A - POLAR STAR SLEP Draft Solicitation.pdf PDF
Attachment B - DRAFT POLAR_STAR _SLEP_ Specification.pdf PDF
Attachment C - SFLC-Std-Spec-0000.pdf PDF
Attachment E - Draft POLAR STAR SLEP CDRL.pdf PDF
Attachment I - DRAFT High Level CGMCS Scope for POLAR STAR.pdf PDF
Attachment F - Draft Mandated_Work_Item_Schedule.pdf PDF
Attachment D - Draft CLIN Structure.xlsx XLSX spreadsheet
POLAR_STAR_SLEP RFI-USCG-PSTAR-2019-3.pdf PDF
Attachment G - Draft Work Breakdown Structure Example.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

High Level PPD SOW FY21-FY23

2021 (Complete changeover/ installation of PPD system including but not limited to: Replace Replacement all

Voltage Regulator enclosures, upgrade engine actuators, install Atlas II enclosures, terminate cabling from

2020 installation, Integration with CGMCS shipboard. 8 electricians for 60-90 days, 6 mechanics for 60-90 days, 2

Electricians to support testing post installation 40 days, 2 electricians 2 days of dock trials, 2 Electricians 5 days of

Sea Trials, 8-10 NSWCPD Engineers at any time.)

Disconnect existing power & control cables inside existing Generator and Motor Voltage

Regulator cabinets and remove cabinets within ECC o STBD Generator Voltage Regulator Cabinet o CTR Generator Voltage Regulator Cabinet o PORT Generator Voltage Regulator Cabinet o Motor Voltage Regulator Cabinet

Install Controller Enclosures

Disconnect existing power & control cables inside existing Generator and Motor Voltage

Regulator cabinets and remove cabinets within ECC

Remove existing and install new foundations for the Voltage Regulator cabinets. Install new

Voltage Regulator cabinets.

Westinghouse Switchboards o Disconnect existing wiring and remove devices/ equipment to be removed from backplanes o Mount new devices/ equipment inside Switchboard and terminate existing wiring

Install new battery units for UPS units on new foundation in ECC (3 units)

Install new reverse acting governors/ actuators (one per engine, totaling 6)

Work Spaces: ECCC, Aux 1/2/3, Diesel 1 & 2, Motor Gear Compartment, Pilothouse, Aloft Con

2022 (2 electricians rotated for 30 days, 2 mechanics onsite for 30 days, 2-4 NSWCPD Engineers at any time.)

Groom existing system, confirm right and tight

Support testing/ trouble shooting

Software Updates

Coordination with CGMCS

Download data logger

Work Spaces: •ECC, Aux 1, 2, Deisel 1 &

2023 (2 electricians for 30 days, 2 mechanics onsite for 10 days, 2-3 NSWCPD Engineers at any time.)

Groom existing system, confirm right and tight

Support testing/ trouble shooting

Software Updates

Coordination with CGMCS

Download data logger

Work Spaces: ECC, Aux 1, 2, Diesel 1 & 2