Attachment D - Draft CLIN Structure.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Request for Information: USCG POLAR STAR Service Life Extension Project (SLEP) Federal contract opportunity
- Solicitation number
- RFI-USCG-PSTAR-2019-3
About this file
This document contains a draft contract line item number (CLIN) structure for the Polar Star Service Life Extension Project (SLEP). The CLIN structure outlines work items, associated numbers, unit types, delivery dates and periods of performance for maintenance, modernization and installation efforts to extend the service life of the Polar Star from fiscal years 2021 through 2025. Key work items include hull maintenance and inspection, propulsion system overhaul, crane and davit inspections, pump and purifier overhauls, preservation activities, and installation of new systems such as sewage lift stations and piping replacements. The CLIN structure is intended to form the basis for task orders to be awarded under an existing indefinite delivery/indefinite quantity contract, with work to occur during annual availabilities and be completed within 140 days of starting each availability period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment J - DRAFT High Level PPD Scope USCGC POLAR STAR 2021.pdf | ||
| POLAR_STAR_SLEP RFI-USCG-PSTAR-2019-3.pdf | ||
| Attachment G - Draft Work Breakdown Structure Example.pdf | ||
| Attachment H - POLAR STAR DRAFT Pricing Estimate Template.xlsx | XLSX spreadsheet | |
| Attachment A - POLAR STAR SLEP Draft Solicitation.pdf | ||
| Attachment B - DRAFT POLAR_STAR _SLEP_ Specification.pdf | ||
| Attachment C - SFLC-Std-Spec-0000.pdf | ||
| Attachment E - Draft POLAR STAR SLEP CDRL.pdf | ||
| Attachment I - DRAFT High Level CGMCS Scope for POLAR STAR.pdf | ||
| Attachment F - Draft Mandated_Work_Item_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Draft CLIN Structure
| POLAR STAR SLEP - Draft CLIN Structure | |||||||||
| WBS Number | Contract Line Item Numbers (CLINs) | FY 2021 | FY 2022 | FY 2023 | FY 2024 | FY 2025 | Unit Type | Delivery by Date | POP |
| 2.4.2 | WI #1 Hull Plating (U/W Body) Inspect | 00001 | 10001 | 20001 | 30001 | 40001 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.3 | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 00002 | 10002 | 20002 | 30002 | 40002 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.4 | WI #3 Propulsion Shafting, Strain Guage and Air Gap Readings (All) | 00003 | 10003 | 20003 | 30003 | 40003 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.5 | WI #4 Centerline Propulsion Hub Remove and Reinstall | 00004 | 10004 | 20004 | 30004 | 40004 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.6 | WI #5 Port Propulsion Hub Remove and Reinstall | 00005 | 10005 | 20005 | 30005 | 40005 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.7 | WI #6 STBD Propulsion Hub Remove and Reinstall | 00006 | 10006 | 20006 | 30006 | 40006 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.8 | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 00007 | 10007 | 20007 | 30007 | 40007 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.9 | Wi #8 Port Propulsion Shafting Remove and Reinstall | 00008 | 10008 | 20008 | 30008 | 40008 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.10 | WI #9 STBD Propulsion Shafting Remove and Reinstall | 00009 | 10009 | 20009 | 30009 | 40009 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.11 | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 00010 | 10010 | 20010 | 30010 | 40010 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.12 | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 00011 | 10011 | 20011 | 30011 | 40011 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.13 | WI #12 Boiler, Biennial Maintenance and Inspect | 00012 | 10012 | 20012 | 30012 | 40012 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.14 | WI #13 Rudder and Rudder Stock, Remove and Inspect | 00013 | 10013 | 20013 | 30013 | 40013 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.15 | WI #14 Cathodic Protection /Zinc Anodes, Renew | 00014 | 10014 | 20014 | 30014 | 40014 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.16 | WI #15 Temporary Fuel Oil Offload and Storage, Drydock | 00015 | 10015 | 20015 | 30015 | 40015 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.17 | WI #16 Drydock | 00016 | 10016 | 20016 | 30016 | 40016 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.18 | WI #17 Dock and Sea Trial Performance, Support, Provide | 00017 | 10017 | 20017 | 30017 | 40017 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.19 | WI #18 Miranda Davit, Annual Inspect | 00018 | 10018 | 20018 | 30018 | 40018 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.20 | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 00019 | 10019 | 20019 | 30019 | 40019 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.21 | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 00020 | 10020 | 20020 | 30020 | 40020 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.22 | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 00021 | 10021 | 20021 | 30021 | 40021 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.23 | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 00022 | 10022 | 20022 | 30022 | 40022 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.24 | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 00023 | 10023 | 20023 | 30023 | 40023 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.25 | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 00024 | 10024 | 20024 | 30024 | 40024 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.26 | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 00025 | 10025 | 20025 | 30025 | 40025 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.27 | WI #26 Shaft Handling Equipment, Maintenance and Storage | 00026 | 10026 | 20026 | 30026 | 40026 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.28 | WI #27 Elevators, Annual Maintenance and Certification | 00027 | 10027 | 20027 | 30027 | 40027 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.29 | WI #28 Dumbwaiter, Annual Maintenance and Certification | 00028 | 10028 | 20028 | 30028 | 40028 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.30 | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 00029 | 10029 | 20029 | 30029 | 40029 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.31 | WI #30 Anchor Windlass, Service & Inspect | 00030 | 10030 | 20030 | 30030 | 40030 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.32 | WI #31 Voids (Non-Assessible), Internal Surfaces, Preserve | 00031 | 10031 | 20031 | 30031 | 40031 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.33 | WI #32 U/W Body, Preserve 100% | 00032 | 10032 | 20032 | 30032 | 40032 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.34 | WI #33 U/W Body, Preserve (Partial) | 00033 | 10033 | 20033 | 30033 | 40033 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.35 | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 00034 | 10034 | 20034 | 30034 | 40034 | Quantity | Availability end date in year of award | 140 days after availability start |
| 2.4.36 | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 00035 | 10035 | 20035 | 30035 | 40035 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.37 | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 00036 | 10036 | 20036 | 30036 | 40036 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.38 | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 00037 | 10037 | 20037 | 30037 | 40037 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.39 | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 00038 | 10038 | 20038 | 30038 | 40038 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.40 | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 00039 | 10039 | 20039 | 30039 | 40039 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.41 | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 00040 | 10040 | 20040 | 30040 | 40040 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.42 | WI #41 Evaporators (General), Overhaul | 00041 | 10041 | 20041 | 30041 | 40041 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.43 | WI #42 Voids (Accessible), Clean and Inspect | 00042 | 10042 | 20042 | 30042 | 40042 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.44 | WI #43 Flight Deck Nets, Overhaul 5 year | 00043 | 10043 | 20043 | 30043 | 40043 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.45 | WI #44 Sewage Holding Tank(s) Clean/Inspect | 00044 | 10044 | 20044 | 30044 | 40044 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.46 | WI #45 Tanks (Potable Water), Clean/Inspect | 00045 | 10045 | 20045 | 30045 | 40045 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.47 | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 00046 | 10046 | 20046 | 30046 | 40046 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.48 | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 00047 | 10047 | 20047 | 30047 | 40047 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.49 | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 00048 | 10048 | 20048 | 30048 | 40048 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.50 | WI #49 Voids (Non-Accessible), Leak Test | 00049 | 10049 | 20049 | 30049 | 40049 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.51 | WI #50 Appendages (U/W), Leak Test | 00050 | 10050 | 20050 | 30050 | 40050 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.52 | WI #51 Fire Prevention and Protection, Provide | 00051 | 10051 | 20051 | 30051 | 40051 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.53 | WI #52 Flex Hose Assemblies, Renew (2021) | 00052 | 10052 | 20052 | 30052 | 40052 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.54 | WI #53 Flex Hose Assemblies, Renew (2022) | 00053 | 10053 | 20053 | 30053 | 40053 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.55 | WI #54 Flex Hose Assemblies, Renew (2023) | 00054 | 10054 | 20054 | 30054 | 40054 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.56 | WI #55 Flex Hose Assemblies, Renew (2024) | 00055 | 10055 | 20055 | 30055 | 40055 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.57 | WI #56 Flex Hose Assemblies, Renew (2025) | 00056 | 10056 | 20056 | 30056 | 40056 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.58 | WI #57 Distilling Plant Pumps and Motors, Overhaul | 00057 | 10057 | 20057 | 30057 | 40057 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.59 | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 00058 | 10058 | 20058 | 30058 | 40058 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.60 | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 00059 | 10059 | 20059 | 30059 | 40059 | Quantity | Availability end date in year of award | 140 days after availability start |
| 2.4.61 | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 00060 | 10060 | 20060 | 30060 | 40060 | Quantity | Availability end date in year of award | 140 days after availability start |
| 2.4.62 | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 00061 | 10061 | 20061 | 30061 | 40061 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.63 | WI #62 Boiler, Strength and Integrity Inspection | 00062 | 10062 | 20062 | 30062 | 40062 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.64 | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 00063 | 10063 | 20063 | 30063 | 40063 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.65 | WI #64 Warping Capstan, Inspect and Repair | 00064 | 10064 | 20064 | 30064 | 40064 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.66 | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 00065 | 10065 | 20065 | 30065 | 40065 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.67 | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 00066 | 10066 | 20066 | 30066 | 40066 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.68 | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 00067 | 10067 | 20067 | 30067 | 40067 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.69 | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 00068 | 10068 | 20068 | 30068 | 40068 | Dollars | Availability end date in year of award | 140 days after availability start |
| 1.2.1 | WI #69 Non-Recuring Engineering | 00069 | Dollars | 18 months after award | 18 months | ||||
| 1.2.2 | WI #70 Project Management and Planning, Perform | 00070 | Dollars | End of contract | Duration of the IDIQ Contract | ||||
| 1.2.3 | WI #71 Weight and Moment, Management | 00071 | 10071 | 20071 | 30071 | 40071 | Dollars | Availability-Period end date in year of award | 140 days after availability start |
| 1.2.4 | WI #72 NSWCPD CGMCS Installation, Coordinate | 00072 | 10072 | 20072 | 30072 | 40072 | Dollars | 12 months after award | 12 months |
| 1.2.5 | WI #73 NSWCPD PPD Installation, Coordinate | 00073 | 10073 | 20073 | 30073 | 40073 | Dollars | 12 months after award | 12 months |
| 1.2.6 | WI #74 Sewage System Grey Water Lift Stations, Install | 00074 | 10074 | 20074 | 30074 | 40074 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.7 | WI #75 Sewage Retention Tank, Add | 00075 | 10075 | 20075 | 30075 | 40075 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.8 | WI #76 Piping, Renewal | 00076 | 10076 | 20076 | 30076 | 40076 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.9 | WI #77 Gyro Repeaters, Recapitalize | 00077 | 10077 | 20077 | 30077 | 40077 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.10 | WI #78 Boiler, Recapitalize Ancillaries | 00078 | 10078 | 20078 | 30078 | 40078 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.11 | WI #79 1MC, Renewal | 00079 | 10079 | 20079 | 30079 | 40079 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.12 | WI #80 6MC, Refurbish | 00080 | 10080 | 20080 | 30080 | 40080 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.13 | WI #81 Ship Service Air Compressors, Recapitalize | 00081 | 10081 | 20081 | 30081 | 40081 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.14 | WI #82 Start Air System, Modify | 00082 | 10082 | 20082 | 30082 | 40082 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.15 | WI #83 Oily Water Separator, Recapitalize | 00083 | 10083 | 20083 | 30083 | 40083 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.16 | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 00084 | 10084 | 20084 | 30084 | 40084 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.17 | WI #85 Dumbwaiter, Recapitalize | 00085 | 10085 | 20085 | 30085 | 40085 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.18 | WI #86 Elevators, Upgrade | 00086 | 10086 | 20086 | 30086 | 40086 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.19 | WI #87 Small Boat Davit Control Equipment, Relocation | 00087 | 10087 | 20087 | 30087 | 40087 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.20 | WI #88 Commissary Equipment, Recapitalize | 00088 | 10088 | 20088 | 30088 | 40088 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.21 | WI #89 Fire Detection System, Recapitalize | 00089 | 10089 | 20089 | 30089 | 40089 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.22 | WI #90 400 Hz System, Modify | 00090 | 10090 | 20090 | 30090 | 40090 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.23 | WI #91 False Overhead, Remove | 00091 | 10091 | 20091 | 30091 | 40091 | Dollars | Availability-Period end date in year of award | Completed during Availability-Period in year of Task Order award. |
| 1.2.24 | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 00092 | 10092 | 20092 | 30092 | 40092 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.25 | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 00093 | 10093 | 20093 | 30093 | 40093 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.26 | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 00094 | 10094 | 20094 | 30094 | 40094 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.27 | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 00095 | 10095 | 20095 | 30095 | 40095 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.28 | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 00096 | 10096 | 20096 | 30096 | 40096 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.29 | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 00097 | 10097 | 20097 | 30097 | 40097 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.30 | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 00098 | 10098 | 20098 | 30098 | 40098 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.31 | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 00099 | 10099 | 20099 | 30099 | 40099 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.32 | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 00100 | 10100 | 20100 | 30100 | 40100 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.33 | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 00101 | 10101 | 20101 | 30101 | 40101 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.34 | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 00102 | 10102 | 20102 | 30102 | 40102 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.35 | WI #103 False Overhead, Recapitalize | 00103 | 10103 | 20103 | 30103 | 40103 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.36 | WI #104 Evaporator Salinity Monitoring, Recapitalize | 00104 | 10104 | 20104 | 30104 | 40104 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.37 | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 00105 | 10105 | 20105 | 30105 | 40105 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.38 | WI #106 Flooding Alarms, Recapitalize | 00106 | 10106 | 20106 | 30106 | 40106 | Dollars | Finals no later than 90-days after completion of installation and testing. | Install during Availability-Period in year of Task Order award, with all logstics deliverables 90 days after installation and testing. |
| 1.2.39 | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 00107 | 10107 | 20107 | 30107 | 40107 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.40 | WI #108 Centerline Disconnect Coupling, Recapitalize | 00108 | 10108 | 20108 | 30108 | 40108 | Dollars | Availability-Period end date in year of award | Install during Availability-Period in year of Task Order award. |
| 1.2.41 | WI #109 Temporary Services, Contractor Facility, Provide | 00109 | 10109 | 20109 | 30109 | 40109 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.70 | WI #110 Anticipated Growth | 00110 | 10110 | 20110 | 30110 | 40110 | Dollars | Availability end date in year of award | 140 days after availability start |
| 2.4.71 | WI #111 Voyage Repairs | 00111 | 10111 | 20111 | 30111 | 40111 | Dollars | Availability end date in year of award | 140 days after availability start |
| Early Delivery Incentive | 00200 | 10200 | 20200 | 30200 | 40200 | Dollars |