This document is a draft scope of work for the US Coast Guard's POLAR STAR Service Life Extension Project. The scope involves removing and replacing various electrical enclosures and panels aboard the vessel, installing new computer and input/output equipment, and modifying bridge consoles. Specific tasks include replacing enclosures in six areas of the ship and connecting new cabling; replacing subpanels in two locations; installing new input/output racks in the engine control center for vital alarms; replacing existing computers in the engine control center with new models; and removing existing input/output racks from bridge consoles and installing new racks mounted on plates. Foundation work and cable runs between areas of the pilothouse are also included. The Coast Guard seeks industry feedback on this draft scope through a request for information as part of planning the solicitation for the service life extension project aimed at extending the service life of the POLAR STAR and recapitalizing major systems.

View the file

Other files for this federal contract opportunity

Other files attached to Request for Information: USCG POLAR STAR Service Life Extension Project (SLEP), newest first.
File Type Posted
Attachment J - DRAFT High Level PPD Scope USCGC POLAR STAR 2021.pdf PDF
Attachment D - Draft CLIN Structure.xlsx XLSX spreadsheet
POLAR_STAR_SLEP RFI-USCG-PSTAR-2019-3.pdf PDF
Attachment G - Draft Work Breakdown Structure Example.pdf PDF
Attachment H - POLAR STAR DRAFT Pricing Estimate Template.xlsx XLSX spreadsheet
Attachment A - POLAR STAR SLEP Draft Solicitation.pdf PDF
Attachment B - DRAFT POLAR_STAR _SLEP_ Specification.pdf PDF
Attachment C - SFLC-Std-Spec-0000.pdf PDF
Attachment E - Draft POLAR STAR SLEP CDRL.pdf PDF
Attachment F - Draft Mandated_Work_Item_Schedule.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT – High Level CGMCS Scope for USCGC POLAR STAR

High Level SOW FY21

2021 (6 electricians rotated for 60 days, 2 technicians to support testing post installation 40 days, then 2 days dock trials 5 days Sea Trials. 4 Mechanics onsite approximately 30 days to support foundation work and other modifications)

Remove existing enclosures and replace with new enclosures RIB1A/B, RIB2A/B, RIB3A/B, RIB4A, RIB5.

Reinstall field cabling and connect new CAT5e and power cabling. Foundation work required

Replace subpanels in RDU4 and RDU6 and install new subpanels. Reinstall field cabling and connect new

CAT5e and power cabling. Modify enclosures panels.

Install new I/O racks in the ECCC for Vital alarms.

Replace existing computers in ECCC with new computers.

Remove existing Opto22 IO racks in bridge consoles and install new Rockwell racks mounted on plates (4)

Run signal cables from Pilothouse center console to PBW, SBW and Aloft Conn (<14 conductor cable )

Remove existing Opto 22 IO racks in ECCC and install new Rockwell racks mounted on plates (4).

Remove existing UPS and foundations in ECC.

Remove existing switches including 19 inch Rack in ECCC and Install new Rack, Switches (2) and Rack mounted computer.

Install new UPS units in ECC (2 bulkhead mounted units)

Remove existing Computers/Monitors at Bridge (4) including brackets, install new computers, monitors and brackets (4)

Install power cabling from UPS to all new devices, Ethernet cabling from ECC to all new devices.

Insert new pushbuttons and lights in bridge consoles for transfer of control. Connect wiring to existing

Opto22 units in bridge consoles.

Install terminals and replace power supplies in ECCC for power distribution.

Install ETAP in LMAS units to connect to existing Opto22 Rack (5)

Install MVI and ETAP in Main GT LOCOPs (3)

Install CAT5e cable from OOD Station Computers to Bridge switch (3)

Support signal testing for field signals (Fluke simulator or similar)

Support operational testing for plant including dock and Sea Trials

2022 (2 electricians for 20 days)

Install quarterdeck monitoring (3 locations). Power and CAT-5 communication to be run from ECCC to the quarterdeck locations.

Install signal cable from RDU4 to the Vibration monitoring system

Support testing for Quarterdeck and Vibration monitoring systems

2023 (2 electricians for 15 days)

Remove existing Opto22 IO racks in the LMAS enclosures replacing with two Rockwell 1794 devices.

Replace power supplies with one 24VDC power supply. (5 LMAS units total)

Support testing for LMAS signals.