Attachment H - POLAR STAR DRAFT Pricing Estimate Template.xlsx
XLSX spreadsheet 44 KB Posted
- Attached to
- Request for Information: USCG POLAR STAR Service Life Extension Project (SLEP) Federal contract opportunity
- Solicitation number
- RFI-USCG-PSTAR-2019-3
About this file
This document contains a pricing template for the POLAR STAR Service Life Extension Project solicitation. The template requires offerors to provide pricing for 171 mandatory and planned work items across five dry dock availabilities from 2021 to 2025. Pricing must be provided per work item using the unit prices included in the template, which will automatically calculate total evaluated price. The template also includes instructions noting that offerors cannot modify mandated work item quantities or the pricing worksheet formulas, and must fill out highlighted cells for work item quantities and unit prices. This pricing template is intended to standardize offeror responses for the POLAR STAR SLEP effort to extend the service life of the vessel through overhauling of major ship systems.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment J - DRAFT High Level PPD Scope USCGC POLAR STAR 2021.pdf | ||
| Attachment D - Draft CLIN Structure.xlsx | XLSX spreadsheet | |
| POLAR_STAR_SLEP RFI-USCG-PSTAR-2019-3.pdf | ||
| Attachment G - Draft Work Breakdown Structure Example.pdf | ||
| Attachment A - POLAR STAR SLEP Draft Solicitation.pdf | ||
| Attachment B - DRAFT POLAR_STAR _SLEP_ Specification.pdf | ||
| Attachment C - SFLC-Std-Spec-0000.pdf | ||
| Attachment E - Draft POLAR STAR SLEP CDRL.pdf | ||
| Attachment I - DRAFT High Level CGMCS Scope for POLAR STAR.pdf | ||
| Attachment F - Draft Mandated_Work_Item_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing Worksheet Instruction
| The Offeror shall submit proposed pricing by filling out all highlighted price cells in the Pricing Worksheets. Enter pricing data to the cent (two decimal places). The pricing worksheet shall be used to calculate a total evaluated price based on the formulas already entered into the spreadsheet. |
| The Offeror shall submit proposed quantities of Work items per Dry Dock availability by filling out the highlighted cells in the "Contractor Planned WIs" columns. Mandated quantities of supplies and services per ordering year have been included and reflect the Mandated Work Item Schedule provided. Numbers from both Mandated WIs and Contractor Planned WIs will be used for the calculation of the total evaluated price. |
| The Offeror shall complete the tab for Pricing. |
The Offeror shall not modify the pricing worksheets other than to insert data in cells highlighted for data entry; formulas on the pricing worksheets are locked.
The Offeror shall not modify Mandated WI quantities.
The Offeror totals will automatically populate into the appropriate cell in the Total Price tab.
NOTE:
Total Price
| DRAFT | |||||
| Total OE | $0.00 | Total PC&I | $0.00 | ||
| Total Cost | $0.00 |
| Dry Dock 2021 Cost | ||||
| OE | PC&I | |||
| Mandatory WI | Contractor Planned WI | Mandatory WI | Contractor Planned WI | |
| Number | 34 | 0 | 7 | 0 |
| Cost | $0.00 | $0.00 | $0.00 | $0.00 |
| Total OE Items | 34 | Total PC&I Items | 7 | |
| Total OE Cost | $0.00 | Total PC&I Cost | $0.00 |
Total Dry Dock 2021 Cost $0.00
| Dry Dock 2022 Cost | ||||
| OE | PC&I | |||
| Mandatory WI | Contractor Planned WI | Mandatory WI | Contractor Planned WI | |
| Number | 37 | 0 | 2 | 0 |
| Cost | $0.00 | $0.00 | $0.00 | $0.00 |
| Total OE Items | 37 | Total PC&I Items | 2 | |
| Total OE Cost | $0.00 | Total PC&I Cost | $0.00 |
Total Dry Dock 2022 Cost $0.00
| Dry Dock 2023 Cost | ||||
| OE | PC&I | |||
| Mandatory WI | Contractor Planned WI | Mandatory WI | Contractor Planned WI | |
| Number | 39 | 0 | 2 | 0 |
| Cost | $0.00 | $0.00 | $0.00 | $0.00 |
| Total OE Items | 39 | Total PC&I Items | 2 | |
| Total OE Cost | $0.00 | Total PC&I Cost | $0.00 |
Total Dry Dock 2023 Cost $0.00
| Dry Dock 2024 Cost | |||||
| OE | PC&I | ||||
| Mandatory WI | Contractor Planned WI | Mandatory WI | Contractor Planned WI | ||
| Number | 29 | 0 | 1 | 0 | 352 |
| Cost | $0.00 | $0.00 | $0.00 | $0.00 | 463 |
| Total OE Items | 29 | Total PC&I Items | 1 | ||
| Total OE Cost | $0.00 | Total PC&I Cost | $0.00 |
Total Dry Dock 2024 Cost $0.00
| Dry Dock 2025 Cost | ||||
| OE | PC&I | |||
| Mandatory WI | Contractor Planned WI | Mandatory WI | Contractor Planned WI | |
| Number | 32 | 0 | 1 | 0 |
| Cost | $0.00 | $0.00 | $0.00 | $0.00 |
| Total OE Items | 32 | Total PC&I Items | 1 | |
| Total OE Cost | $0.00 | Total PC&I Cost | $0.00 |
Total Dry Dock 2025 Cost $0.00
Pricing
| DRAFT | |||||||
| Dry Dock 2021 Work Item Pricelist | |||||||
| WBS Number | Funding | Work Item | CLIN | Price | Mandated WIs | Contractor Planned WIs | |
| 2.4.2 | OE | WI #1 Hull Plating (U/W Body) Inspect | 00001 | 1 | |||
| 2.4.3 | OE | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 00002 | 1 | |||
| 2.4.4 | OE | WI #3 Propulsion Shafting, Strain Gauge and Air Gap Readings (All) | 00003 | 1 | |||
| 2.4.5 | OE | WI #4 Centerline Propulsion Hub Remove and Reinstall | 00004 | 1 | |||
| 2.4.6 | OE | WI #5 Port Propulsion Hub Remove and Reinstall | 00005 | 1 | |||
| 2.4.7 | OE | WI #6 STBD Propulsion Hub Remove and Reinstall | 00006 | 1 | |||
| 2.4.8 | OE | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 00007 | ||||
| 2.4.9 | OE | Wi #8 Port Propulsion Shafting Remove and Reinstall | 00008 | ||||
| 2.4.10 | OE | WI #9 STBD Propulsion Shafting Remove and Reinstall | 00009 | ||||
| 2.4.11 | OE | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 00010 | 1 | |||
| 2.4.12 | OE | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 00011 | 1 | |||
| 2.4.13 | OE | WI #12 Boiler, Biennial Maintenance and Inspect | 00012 | 1 | |||
| 2.4.14 | OE | WI #13 Rudder and Rudder Stock, Remove and Inspect | 00013 | ||||
| 2.4.15 | OE | WI #14 Cathodic Protection /Zinc Anodes, Renew | 00014 | 1 | |||
| 2.4.16 | OE | WI #15 Temporary Fuel Oil Offload and Storage, Dry-Dock | 00015 | 1 | |||
| 2.4.17 | OE | WI #16 Dry-Dock | 00016 | 1 | |||
| 2.4.18 | OE | WI #17 Dock and Sea Trial Performance, Support, Provide | 00017 | 1 | |||
| 2.4.19 | OE | WI #18 Miranda Davit, Annual Inspect | 00018 | 1 | |||
| 2.4.20 | OE | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 00019 | 1 | |||
| 2.4.21 | OE | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 00020 | 1 | |||
| 2.4.22 | OE | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 00021 | 1 | |||
| 2.4.23 | OE | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 00022 | ||||
| 2.4.24 | OE | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 00023 | 1 | |||
| 2.4.25 | OE | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 00024 | ||||
| 2.4.26 | OE | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 00025 | 1 | |||
| 2.4.27 | OE | WI #26 Shaft Handling Equipment, Maintenance and Storage | 00026 | 1 | |||
| 2.4.28 | OE | WI #27 Elevators, Annual Maintenance and Certification | 00027 | 1 | |||
| 2.4.29 | OE | WI #28 Dumbwaiter, Annual Maintenance and Certification | 00028 | ||||
| 2.4.30 | OE | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 00029 | 1 | |||
| 2.4.31 | OE | WI #30 Anchor Windlass, Service & Inspect | 00030 | 1 | |||
| 2.4.32 | OE | WI #31 Voids (Non-Assessable), Internal Surfaces, Preserve | 00031 | ||||
| 2.4.33 | OE | WI #32 U/W Body, Preserve 100% | 00032 | ||||
| 2.4.34 | OE | WI #33 U/W Body, Preserve (Partial) | 00033 | ||||
| 2.4.35 | OE | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 00034 | ||||
| 2.4.36 | OE | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 00035 | 1 | |||
| 2.4.37 | OE | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 00036 | ||||
| 2.4.38 | OE | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 00037 | 1 | |||
| 2.4.39 | OE | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 00038 | 1 | |||
| 2.4.40 | OE | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 00039 | ||||
| 2.4.41 | OE | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 00040 | ||||
| 2.4.42 | OE | WI #41 Evaporators (General), Overhaul | 00041 | ||||
| 2.4.43 | OE | WI #42 Voids (Accessible), Clean and Inspect | 00042 | ||||
| 2.4.44 | OE | WI #43 Flight Deck Nets, Overhaul 5 year | 00043 | ||||
| 2.4.45 | OE | WI #44 Sewage Holding Tank(s) Clean/Inspect | 00044 | ||||
| 2.4.46 | OE | WI #45 Tanks (Potable Water), Clean/Inspect | 00045 | ||||
| 2.4.47 | OE | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 00046 | ||||
| 2.4.48 | OE | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 00047 | ||||
| 2.4.49 | OE | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 00048 | ||||
| 2.4.50 | OE | WI #49 Voids (Non-Accessible), Leak Test | 00049 | ||||
| 2.4.51 | OE | WI #50 Appendages (U/W), Leak Test | 00050 | ||||
| 2.4.52 | OE | WI #51 Fire Prevention and Protection, Provide | 00051 | 1 | |||
| 2.4.53 | OE | WI #52 Flex Hose Assemblies, Renew (2021) | 00052 | 1 | |||
| 2.4.54 | OE | WI #53 Flex Hose Assemblies, Renew (2022) | 00053 | ||||
| 2.4.55 | OE | WI #54 Flex Hose Assemblies, Renew (2023) | 00054 | ||||
| 2.4.56 | OE | WI #55 Flex Hose Assemblies, Renew (2024) | 00055 | ||||
| 2.4.57 | OE | WI #56 Flex Hose Assemblies, Renew (2025) | 00056 | ||||
| 2.4.58 | OE | WI #57 Distilling Plant Pumps and Motors, Overhaul | 00057 | ||||
| 2.4.59 | OE | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 00058 | ||||
| 2.4.60 | OE | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 00059 | ||||
| 2.4.61 | OE | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 00060 | ||||
| 2.4.62 | OE | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 00061 | ||||
| 2.4.63 | OE | WI #62 Boiler, Strength and Integrity Inspection | 00062 | ||||
| 2.4.64 | OE | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 00063 | ||||
| 2.4.65 | OE | WI #64 Warping Capstan, Inspect and Repair | 00064 | 1 | |||
| 2.4.66 | OE | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 00065 | 1 | |||
| 2.4.67 | OE | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 00066 | 1 | |||
| 2.4.68 | OE | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 00067 | 1 | |||
| 2.4.69 | OE | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 00068 | 1 | |||
| 1.2.1 | PC&I | WI #69 Non-Recurring Engineering | 00069 | 1 | |||
| 1.2.2 | PC&I | WI #70 Project Management and Planning, Perform | 00070 | 1 | |||
| 1.2.3 | PC&I | WI #71 Weight and Moment, Management | 00071 | 1 | |||
| 1.2.4 | PC&I | WI #72 NSWCPD CGMCS Installation, Coordinate | 00072 | 1 | |||
| 1.2.5 | PC&I | WI #73 NSWCPD PPD Installation, Coordinate | 00073 | 1 | |||
| 1.2.6 | PC&I | WI #74 Sewage System Grey Water Lift Stations, Install | 00074 | ||||
| 1.2.7 | PC&I | WI #75 Sewage Retention Tank, Add | 00075 | ||||
| 1.2.8 | PC&I | WI #76 Piping, Renewal | 00076 | ||||
| 1.2.9 | PC&I | WI #77 Gyro Repeaters, Recapitalize | 00077 | ||||
| 1.2.10 | PC&I | WI #78 Boiler, Recapitalize Ancillaries | 00078 | ||||
| 1.2.11 | PC&I | WI #79 1MC, Renewal | 00079 | 1 | |||
| 1.2.12 | PC&I | WI #80 6MC, Refurbish | 00080 | ||||
| 1.2.13 | PC&I | WI #81 Ship Service Air Compressors, Recapitalize | 00081 | ||||
| 1.2.14 | PC&I | WI #82 Start Air System, Modify | 00082 | ||||
| 1.2.15 | PC&I | WI #83 Oily Water Separator, Recapitalize | 00083 | ||||
| 1.2.16 | PC&I | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 00084 | ||||
| 1.2.17 | PC&I | WI #85 Dumbwaiter, Recapitalize | 00085 | ||||
| 1.2.18 | PC&I | WI #86 Elevators, Upgrade | 00086 | ||||
| 1.2.19 | PC&I | WI #87 Small Boat Davit Control Equipment, Relocation | 00087 | ||||
| 1.2.20 | PC&I | WI #88 Commissary Equipment, Recapitalize | 00088 | ||||
| 1.2.21 | PC&I | WI #89 Fire Detection System, Recapitalize | 00089 | ||||
| 1.2.22 | PC&I | WI #90 400 Hz System, Modify | 00090 | ||||
| 1.2.23 | PC&I | WI #91 False Overhead, Remove | 00091 | 1 | |||
| 1.2.24 | PC&I | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 00092 | ||||
| 1.2.25 | PC&I | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 00093 | ||||
| 1.2.26 | PC&I | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 00094 | ||||
| 1.2.27 | PC&I | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 00095 | ||||
| 1.2.28 | PC&I | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 00096 | ||||
| 1.2.29 | PC&I | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 00097 | ||||
| 1.2.30 | PC&I | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 00098 | ||||
| 1.2.31 | PC&I | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 00099 | ||||
| 1.2.32 | PC&I | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 00100 | ||||
| 1.2.33 | PC&I | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 00101 | ||||
| 1.2.34 | PC&I | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 00102 | ||||
| 1.2.35 | PC&I | WI #103 False Overhead, Recapitalize | 00103 | ||||
| 1.2.36 | PC&I | WI #104 Evaporator Salinity Monitoring, Recapitalize | 00104 | ||||
| 1.2.37 | PC&I | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 00105 | ||||
| 1.2.38 | PC&I | WI #106 Flooding Alarms, Recapitalize | 00106 | ||||
| 1.2.39 | PC&I | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 00107 | ||||
| 1.2.40 | PC&I | WI #108 Centerline Disconnect Coupling, Recapitalize | 00108 | ||||
| 1.2.41 | OE | WI #109 Temporary Services, Contractor Facility, Provide | 00109 | 1 | |||
| 2.4.70 | OE | WI #110 Anticipated Growth | 00110 | ||||
| 2.4.71 | OE | WI #111 Voyage Repairs | 00111 | ||||
| PC&I | Early Delivery Incentive | 00200 | |||||
| Planned Total | $0.00 | $0.00 | $0.00 |
| Dry Dock 2022 Work Item Pricelist | ||||||
| WBS Number | Funding | Work Item | CLIN | Price | Mandated WIs | Contractor Planned WIs |
| 2.4.2 | OE | WI #1 Hull Plating (U/W Body) Inspect | 10001 | 1 | ||
| 2.4.3 | OE | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 10002 | 1 | ||
| 2.4.4 | OE | WI #3 Propulsion Shafting, Strain Gauge and Air Gap Readings (All) | 10003 | 1 | ||
| 2.4.5 | OE | WI #4 Centerline Propulsion Hub Remove and Reinstall | 10004 | 1 | ||
| 2.4.6 | OE | WI #5 Port Propulsion Hub Remove and Reinstall | 10005 | 1 | ||
| 2.4.7 | OE | WI #6 STBD Propulsion Hub Remove and Reinstall | 10006 | 1 | ||
| 2.4.8 | OE | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 10007 | 1 | ||
| 2.4.9 | OE | Wi #8 Port Propulsion Shafting Remove and Reinstall | 10008 | |||
| 2.4.10 | OE | WI #9 STBD Propulsion Shafting Remove and Reinstall | 10009 | |||
| 2.4.11 | OE | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 10010 | 1 | ||
| 2.4.12 | OE | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 10011 | |||
| 2.4.13 | OE | WI #12 Boiler, Biennial Maintenance and Inspect | 10012 | |||
| 2.4.14 | OE | WI #13 Rudder and Rudder Stock, Remove and Inspect | 10013 | 1 | ||
| 2.4.15 | OE | WI #14 Cathodic Protection /Zinc Anodes, Renew | 10014 | 1 | ||
| 2.4.16 | OE | WI #15 Temporary Fuel Oil Offload and Storage, Dry-Dock | 10015 | 1 | ||
| 2.4.17 | OE | WI #16 Dry-Dock | 10016 | 1 | ||
| 2.4.18 | OE | WI #17 Dock and Sea Trial Performance, Support, Provide | 10017 | 1 | ||
| 2.4.19 | OE | WI #18 Miranda Davit, Annual Inspect | 10018 | 1 | ||
| 2.4.20 | OE | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 10019 | 1 | ||
| 2.4.21 | OE | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 10020 | 1 | ||
| 2.4.22 | OE | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 10021 | 1 | ||
| 2.4.23 | OE | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 10022 | 1 | ||
| 2.4.24 | OE | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 10023 | |||
| 2.4.25 | OE | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 10024 | |||
| 2.4.26 | OE | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 10025 | 1 | ||
| 2.4.27 | OE | WI #26 Shaft Handling Equipment, Maintenance and Storage | 10026 | 1 | ||
| 2.4.28 | OE | WI #27 Elevators, Annual Maintenance and Certification | 10027 | 1 | ||
| 2.4.29 | OE | WI #28 Dumbwaiter, Annual Maintenance and Certification | 10028 | |||
| 2.4.30 | OE | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 10029 | 1 | ||
| 2.4.31 | OE | WI #30 Anchor Windlass, Service & Inspect | 10030 | |||
| 2.4.32 | OE | WI #31 Voids (Non-Assessable), Internal Surfaces, Preserve | 10031 | |||
| 2.4.33 | OE | WI #32 U/W Body, Preserve 100% | 10032 | |||
| 2.4.34 | OE | WI #33 U/W Body, Preserve (Partial) | 10033 | |||
| 2.4.35 | OE | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 10034 | |||
| 2.4.36 | OE | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 10035 | |||
| 2.4.37 | OE | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 10036 | 1 | ||
| 2.4.38 | OE | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 10037 | |||
| 2.4.39 | OE | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 10038 | |||
| 2.4.40 | OE | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 10039 | 1 | ||
| 2.4.41 | OE | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 10040 | 1 | ||
| 2.4.42 | OE | WI #41 Evaporators (General), Overhaul | 10041 | |||
| 2.4.43 | OE | WI #42 Voids (Accessible), Clean and Inspect | 10042 | 1 | ||
| 2.4.44 | OE | WI #43 Flight Deck Nets, Overhaul 5 year | 10043 | |||
| 2.4.45 | OE | WI #44 Sewage Holding Tank(s) Clean/Inspect | 10044 | 1 | ||
| 2.4.46 | OE | WI #45 Tanks (Potable Water), Clean/Inspect | 10045 | 1 | ||
| 2.4.47 | OE | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 10046 | 1 | ||
| 2.4.48 | OE | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 10047 | 1 | ||
| 2.4.49 | OE | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 10048 | |||
| 2.4.50 | OE | WI #49 Voids (Non-Accessible), Leak Test | 10049 | |||
| 2.4.51 | OE | WI #50 Appendages (U/W), Leak Test | 10050 | 1 | ||
| 2.4.52 | OE | WI #51 Fire Prevention and Protection, Provide | 10051 | 1 | ||
| 2.4.53 | OE | WI #52 Flex Hose Assemblies, Renew (2021) | 10052 | |||
| 2.4.54 | OE | WI #53 Flex Hose Assemblies, Renew (2022) | 10053 | 1 | ||
| 2.4.55 | OE | WI #54 Flex Hose Assemblies, Renew (2023) | 10054 | |||
| 2.4.56 | OE | WI #55 Flex Hose Assemblies, Renew (2024) | 10055 | |||
| 2.4.57 | OE | WI #56 Flex Hose Assemblies, Renew (2025) | 10056 | |||
| 2.4.58 | OE | WI #57 Distilling Plant Pumps and Motors, Overhaul | 10057 | |||
| 2.4.59 | OE | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 10058 | 1 | ||
| 2.4.60 | OE | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 10059 | 1 | ||
| 2.4.61 | OE | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 10060 | 2 | ||
| 2.4.62 | OE | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 10061 | |||
| 2.4.63 | OE | WI #62 Boiler, Strength and Integrity Inspection | 10062 | |||
| 2.4.64 | OE | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 10063 | 1 | ||
| 2.4.65 | OE | WI #64 Warping Capstan, Inspect and Repair | 10064 | |||
| 2.4.66 | OE | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 10065 | |||
| 2.4.67 | OE | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 10066 | |||
| 2.4.68 | OE | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 10067 | |||
| 2.4.69 | OE | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 10068 | |||
| 1.2.1 | PC&I | WI #69 Non-Recurring Engineering | ||||
| 1.2.2 | PC&I | WI #70 Project Management and Planning, Perform | ||||
| 1.2.3 | PC&I | WI #71 Weight and Moment, Management | 10071 | 1 | ||
| 1.2.4 | PC&I | WI #72 NSWCPD CGMCS Installation, Coordinate | 10072 | |||
| 1.2.5 | PC&I | WI #73 NSWCPD PPD Installation, Coordinate | 10073 | |||
| 1.2.6 | PC&I | WI #74 Sewage System Grey Water Lift Stations, Install | 10074 | |||
| 1.2.7 | PC&I | WI #75 Sewage Retention Tank, Add | 10075 | |||
| 1.2.8 | PC&I | WI #76 Piping, Renewal | 10076 | |||
| 1.2.9 | PC&I | WI #77 Gyro Repeaters, Recapitalize | 10077 | |||
| 1.2.10 | PC&I | WI #78 Boiler, Recapitalize Ancillaries | 10078 | |||
| 1.2.11 | PC&I | WI #79 1MC, Renewal | 10079 | |||
| 1.2.12 | PC&I | WI #80 6MC, Refurbish | 10080 | |||
| 1.2.13 | PC&I | WI #81 Ship Service Air Compressors, Recapitalize | 10081 | |||
| 1.2.14 | PC&I | WI #82 Start Air System, Modify | 10082 | |||
| 1.2.15 | PC&I | WI #83 Oily Water Separator, Recapitalize | 10083 | |||
| 1.2.16 | PC&I | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 10084 | |||
| 1.2.17 | PC&I | WI #85 Dumbwaiter, Recapitalize | 10085 | |||
| 1.2.18 | PC&I | WI #86 Elevators, Upgrade | 10086 | |||
| 1.2.19 | PC&I | WI #87 Small Boat Davit Control Equipment, Relocation | 10087 | |||
| 1.2.20 | PC&I | WI #88 Commissary Equipment, Recapitalize | 10088 | |||
| 1.2.21 | PC&I | WI #89 Fire Detection System, Recapitalize | 10089 | |||
| 1.2.22 | PC&I | WI #90 400 Hz System, Modify | 10090 | |||
| 1.2.23 | PC&I | WI #91 False Overhead, Remove | 10091 | |||
| 1.2.24 | PC&I | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 10092 | |||
| 1.2.25 | PC&I | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 10093 | |||
| 1.2.26 | PC&I | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 10094 | |||
| 1.2.27 | PC&I | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 10095 | |||
| 1.2.28 | PC&I | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 10096 | |||
| 1.2.29 | PC&I | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 10097 | |||
| 1.2.30 | PC&I | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 10098 | |||
| 1.2.31 | PC&I | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 10099 | |||
| 1.2.32 | PC&I | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 10100 | |||
| 1.2.33 | PC&I | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 10101 | |||
| 1.2.34 | PC&I | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 10102 | |||
| 1.2.35 | PC&I | WI #103 False Overhead, Recapitalize | 10103 | |||
| 1.2.36 | PC&I | WI #104 Evaporator Salinity Monitoring, Recapitalize | 10104 | |||
| 1.2.37 | PC&I | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 10105 | |||
| 1.2.38 | PC&I | WI #106 Flooding Alarms, Recapitalize | 10106 | |||
| 1.2.39 | PC&I | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 10107 | 1 | ||
| 1.2.40 | PC&I | WI #108 Centerline Disconnect Coupling, Recapitalize | 10108 | |||
| 1.2.41 | OE | WI #109 Temporary Services, Contractor Facility, Provide | 10109 | 1 | ||
| 2.4.70 | OE | WI #110 Anticipated Growth | 10110 | |||
| 2.4.71 | OE | WI #111 Voyage Repairs | 10111 | |||
| PC&I | Early Delivery Incentive | 10200 | ||||
| Planned Total | $0.00 | $0.00 | $0.00 |
| Dry Dock 2023 Work Item Pricelist | ||||||
| WBS Number | Funding | Work Item | CLIN | Price | Mandated WIs | Contractor Planned WIs |
| 2.4.2 | OE | WI #1 Hull Plating (U/W Body) Inspect | 20001 | 1 | ||
| 2.4.3 | OE | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 20002 | 1 | ||
| 2.4.4 | OE | WI #3 Propulsion Shafting, Strain Guage and Air Gap Readings (All) | 20003 | 1 | ||
| 2.4.5 | OE | WI #4 Centerline Propulsion Hub Remove and Reinstall | 20004 | 1 | ||
| 2.4.6 | OE | WI #5 Port Propulsion Hub Remove and Reinstall | 20005 | 1 | ||
| 2.4.7 | OE | WI #6 STBD Propulsion Hub Remove and Reinstall | 20006 | 1 | ||
| 2.4.8 | OE | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 20007 | |||
| 2.4.9 | OE | Wi #8 Port Propulsion Shafting Remove and Reinstall | 20008 | 1 | ||
| 2.4.10 | OE | WI #9 STBD Propulsion Shafting Remove and Reinstall | 20009 | 1 | ||
| 2.4.11 | OE | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 20010 | 1 | ||
| 2.4.12 | OE | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 20011 | 1 | ||
| 2.4.13 | OE | WI #12 Boiler, Biennial Maintenance and Inspect | 20012 | |||
| 2.4.14 | OE | WI #13 Rudder and Rudder Stock, Remove and Inspect | 20013 | |||
| 2.4.15 | OE | WI #14 Cathodic Protection /Zinc Anodes, Renew | 20014 | 1 | ||
| 2.4.16 | OE | WI #15 Temporary Fuel Oil Offload and Storage, Dry-Dock | 20015 | 1 | ||
| 2.4.17 | OE | WI #16 Dry-Dock | 20016 | 1 | ||
| 2.4.18 | OE | WI #17 Dock and Sea Trial Performance, Support, Provide | 20017 | 1 | ||
| 2.4.19 | OE | WI #18 Miranda Davit, Annual Inspect | 20018 | 1 | ||
| 2.4.20 | OE | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 20019 | 1 | ||
| 2.4.21 | OE | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 20020 | 1 | ||
| 2.4.22 | OE | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 20021 | 1 | ||
| 2.4.23 | OE | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 20022 | |||
| 2.4.24 | OE | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 20023 | |||
| 2.4.25 | OE | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 20024 | 1 | ||
| 2.4.26 | OE | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 20025 | 1 | ||
| 2.4.27 | OE | WI #26 Shaft Handling Equipment, Maintenance and Storage | 20026 | 1 | ||
| 2.4.28 | OE | WI #27 Elevators, Annual Maintenance and Certification | 20027 | 1 | ||
| 2.4.29 | OE | WI #28 Dumbwaiter, Annual Maintenance and Certification | 20028 | |||
| 2.4.30 | OE | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 20029 | 1 | ||
| 2.4.31 | OE | WI #30 Anchor Windlass, Service & Inspect | 20030 | 1 | ||
| 2.4.32 | OE | WI #31 Voids (Non-Assessable), Internal Surfaces, Preserve | 20031 | 1 | ||
| 2.4.33 | OE | WI #32 U/W Body, Preserve 100% | 20032 | 1 | ||
| 2.4.34 | OE | WI #33 U/W Body, Preserve (Partial) | 20033 | |||
| 2.4.35 | OE | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 20034 | |||
| 2.4.36 | OE | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 20035 | |||
| 2.4.37 | OE | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 20036 | |||
| 2.4.38 | OE | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 20037 | 1 | ||
| 2.4.39 | OE | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 20038 | |||
| 2.4.40 | OE | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 20039 | |||
| 2.4.41 | OE | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 20040 | |||
| 2.4.42 | OE | WI #41 Evaporators (General), Overhaul | 20041 | 1 | ||
| 2.4.43 | OE | WI #42 Voids (Accessible), Clean and Inspect | 20042 | |||
| 2.4.44 | OE | WI #43 Flight Deck Nets, Overhaul 5 year | 20043 | 1 | ||
| 2.4.45 | OE | WI #44 Sewage Holding Tank(s) Clean/Inspect | 20044 | |||
| 2.4.46 | OE | WI #45 Tanks (Potable Water), Clean/Inspect | 20045 | |||
| 2.4.47 | OE | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 20046 | |||
| 2.4.48 | OE | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 20047 | |||
| 2.4.49 | OE | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 20048 | 1 | ||
| 2.4.50 | OE | WI #49 Voids (Non-Accessible), Leak Test | 20049 | 1 | ||
| 2.4.51 | OE | WI #50 Appendages (U/W), Leak Test | 20050 | |||
| 2.4.52 | OE | WI #51 Fire Prevention and Protection, Provide | 20051 | 1 | ||
| 2.4.53 | OE | WI #52 Flex Hose Assemblies, Renew (2021) | 20052 | |||
| 2.4.54 | OE | WI #53 Flex Hose Assemblies, Renew (2022) | 20053 | |||
| 2.4.55 | OE | WI #54 Flex Hose Assemblies, Renew (2023) | 20054 | 1 | ||
| 2.4.56 | OE | WI #55 Flex Hose Assemblies, Renew (2024) | 20055 | |||
| 2.4.57 | OE | WI #56 Flex Hose Assemblies, Renew (2025) | 20056 | |||
| 2.4.58 | OE | WI #57 Distilling Plant Pumps and Motors, Overhaul | 20057 | 1 | ||
| 2.4.59 | OE | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 20058 | |||
| 2.4.60 | OE | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 20059 | 1 | ||
| 2.4.61 | OE | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 20060 | 2 | ||
| 2.4.62 | OE | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 20061 | |||
| 2.4.63 | OE | WI #62 Boiler, Strength and Integrity Inspection | 20062 | 1 | ||
| 2.4.64 | OE | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 20063 | |||
| 2.4.65 | OE | WI #64 Warping Capstan, Inspect and Repair | 20064 | 1 | ||
| 2.4.66 | OE | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 20065 | |||
| 2.4.67 | OE | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 20066 | |||
| 2.4.68 | OE | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 20067 | 1 | ||
| 2.4.69 | OE | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 20068 | |||
| 1.2.1 | PC&I | WI #69 Non-Recurring Engineering | ||||
| 1.2.2 | PC&I | WI #70 Project Management and Planning, Perform | ||||
| 1.2.3 | PC&I | WI #71 Weight and Moment, Management | 20071 | 1 | ||
| 1.2.4 | PC&I | WI #72 NSWCPD CGMCS Installation, Coordinate | 20072 | |||
| 1.2.5 | PC&I | WI #73 NSWCPD PPD Installation, Coordinate | 20073 | |||
| 1.2.6 | PC&I | WI #74 Sewage System Grey Water Lift Stations, Install | 20074 | |||
| 1.2.7 | PC&I | WI #75 Sewage Retention Tank, Add | 20075 | |||
| 1.2.8 | PC&I | WI #76 Piping, Renewal | 20076 | |||
| 1.2.9 | PC&I | WI #77 Gyro Repeaters, Recapitalize | 20077 | |||
| 1.2.10 | PC&I | WI #78 Boiler, Recapitalize Ancillaries | 20078 | |||
| 1.2.11 | PC&I | WI #79 1MC, Renewal | 20079 | |||
| 1.2.12 | PC&I | WI #80 6MC, Refurbish | 20080 | |||
| 1.2.13 | PC&I | WI #81 Ship Service Air Compressors, Recapitalize | 20081 | |||
| 1.2.14 | PC&I | WI #82 Start Air System, Modify | 20082 | |||
| 1.2.15 | PC&I | WI #83 Oily Water Separator, Recapitalize | 20083 | |||
| 1.2.16 | PC&I | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 20084 | |||
| 1.2.17 | PC&I | WI #85 Dumbwaiter, Recapitalize | 20085 | |||
| 1.2.18 | PC&I | WI #86 Elevators, Upgrade | 20086 | |||
| 1.2.19 | PC&I | WI #87 Small Boat Davit Control Equipment, Relocation | 20087 | |||
| 1.2.20 | PC&I | WI #88 Commissary Equipment, Recapitalize | 20088 | |||
| 1.2.21 | PC&I | WI #89 Fire Detection System, Recapitalize | 20089 | |||
| 1.2.22 | PC&I | WI #90 400 Hz System, Modify | 20090 | |||
| 1.2.23 | PC&I | WI #91 False Overhead, Remove | 20091 | |||
| 1.2.24 | PC&I | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 20092 | |||
| 1.2.25 | PC&I | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 20093 | |||
| 1.2.26 | PC&I | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 20094 | |||
| 1.2.27 | PC&I | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 20095 | |||
| 1.2.28 | PC&I | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 20096 | |||
| 1.2.29 | PC&I | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 20097 | |||
| 1.2.30 | PC&I | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 20098 | |||
| 1.2.31 | PC&I | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 20099 | |||
| 1.2.32 | PC&I | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 20100 | |||
| 1.2.33 | PC&I | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 20101 | |||
| 1.2.34 | PC&I | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 20102 | |||
| 1.2.35 | PC&I | WI #103 False Overhead, Recapitalize | 20103 | |||
| 1.2.36 | PC&I | WI #104 Evaporator Salinity Monitoring, Recapitalize | 20104 | |||
| 1.2.37 | PC&I | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 20105 | |||
| 1.2.38 | PC&I | WI #106 Flooding Alarms, Recapitalize | 20106 | |||
| 1.2.39 | PC&I | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 20107 | |||
| 1.2.40 | PC&I | WI #108 Centerline Disconnect Coupling, Recapitalize | 20108 | 1 | ||
| 1.2.41 | OE | WI #109 Temporary Services, Contractor Facility, Provide | 20109 | 1 | ||
| 2.4.70 | OE | WI #110 Anticipated Growth | 20110 | |||
| 2.4.71 | OE | WI #111 Voyage Repairs | 20111 | |||
| PC&I | Early Delivery Incentive | 20200 | ||||
| Planned Total | $0.00 | $0.00 | $0.00 |
| Dry Dock 2024 Work Item Pricelist | ||||||
| WBS Number | Funding | Work Item | CLIN | Price | Mandated WIs | Contractor Planned WIs |
| 2.4.2 | OE | WI #1 Hull Plating (U/W Body) Inspect | 30001 | 1 | ||
| 2.4.3 | OE | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 30002 | 1 | ||
| 2.4.4 | OE | WI #3 Propulsion Shafting, Strain Gauge and Air Gap Readings (All) | 30003 | 1 | ||
| 2.4.5 | OE | WI #4 Centerline Propulsion Hub Remove and Reinstall | 30004 | 1 | ||
| 2.4.6 | OE | WI #5 Port Propulsion Hub Remove and Reinstall | 30005 | 1 | ||
| 2.4.7 | OE | WI #6 STBD Propulsion Hub Remove and Reinstall | 30006 | 1 | ||
| 2.4.8 | OE | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 30007 | |||
| 2.4.9 | OE | Wi #8 Port Propulsion Shafting Remove and Reinstall | 30008 | |||
| 2.4.10 | OE | WI #9 STBD Propulsion Shafting Remove and Reinstall | 30009 | |||
| 2.4.11 | OE | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 30010 | 1 | ||
| 2.4.12 | OE | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 30011 | |||
| 2.4.13 | OE | WI #12 Boiler, Biennial Maintenance and Inspect | 30012 | |||
| 2.4.14 | OE | WI #13 Rudder and Rudder Stock, Remove and Inspect | 30013 | |||
| 2.4.15 | OE | WI #14 Cathodic Protection /Zinc Anodes, Renew | 30014 | 1 | ||
| 2.4.16 | OE | WI #15 Temporary Fuel Oil Offload and Storage, Dry-Dock | 30015 | 1 | ||
| 2.4.17 | OE | WI #16 Dry-Dock | 30016 | 1 | ||
| 2.4.18 | OE | WI #17 Dock and Sea Trial Performance, Support, Provide | 30017 | 1 | ||
| 2.4.19 | OE | WI #18 Miranda Davit, Annual Inspect | 30018 | 1 | ||
| 2.4.20 | OE | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 30019 | 1 | ||
| 2.4.21 | OE | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 30020 | 1 | ||
| 2.4.22 | OE | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 30021 | 1 | ||
| 2.4.23 | OE | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 30022 | 1 | ||
| 2.4.24 | OE | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 30023 | |||
| 2.4.25 | OE | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 30024 | |||
| 2.4.26 | OE | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 30025 | 1 | ||
| 2.4.27 | OE | WI #26 Shaft Handling Equipment, Maintenance and Storage | 30026 | 1 | ||
| 2.4.28 | OE | WI #27 Elevators, Annual Maintenance and Certification | 30027 | 1 | ||
| 2.4.29 | OE | WI #28 Dumbwaiter, Annual Maintenance and Certification | 30028 | 1 | ||
| 2.4.30 | OE | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 30029 | 1 | ||
| 2.4.31 | OE | WI #30 Anchor Windlass, Service & Inspect | 30030 | |||
| 2.4.32 | OE | WI #31 Voids (Non-Assessable), Internal Surfaces, Preserve | 30031 | |||
| 2.4.33 | OE | WI #32 U/W Body, Preserve 100% | 30032 | |||
| 2.4.34 | OE | WI #33 U/W Body, Preserve (Partial) | 30033 | |||
| 2.4.35 | OE | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 30034 | |||
| 2.4.36 | OE | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 30035 | 1 | ||
| 2.4.37 | OE | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 30036 | |||
| 2.4.38 | OE | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 30037 | |||
| 2.4.39 | OE | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 30038 | |||
| 2.4.40 | OE | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 30039 | 1 | ||
| 2.4.41 | OE | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 30040 | 1 | ||
| 2.4.42 | OE | WI #41 Evaporators (General), Overhaul | 30041 | |||
| 2.4.43 | OE | WI #42 Voids (Accessible), Clean and Inspect | 30042 | |||
| 2.4.44 | OE | WI #43 Flight Deck Nets, Overhaul 5 year | 30043 | |||
| 2.4.45 | OE | WI #44 Sewage Holding Tank(s) Clean/Inspect | 30044 | |||
| 2.4.46 | OE | WI #45 Tanks (Potable Water), Clean/Inspect | 30045 | |||
| 2.4.47 | OE | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 30046 | |||
| 2.4.48 | OE | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 30047 | 1 | ||
| 2.4.49 | OE | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 30048 | |||
| 2.4.50 | OE | WI #49 Voids (Non-Accessible), Leak Test | 30049 | |||
| 2.4.51 | OE | WI #50 Appendages (U/W), Leak Test | 30050 | |||
| 2.4.52 | OE | WI #51 Fire Prevention and Protection, Provide | 30051 | 1 | ||
| 2.4.53 | OE | WI #52 Flex Hose Assemblies, Renew (2021) | 30052 | |||
| 2.4.54 | OE | WI #53 Flex Hose Assemblies, Renew (2022) | 30053 | |||
| 2.4.55 | OE | WI #54 Flex Hose Assemblies, Renew (2023) | 30054 | |||
| 2.4.56 | OE | WI #55 Flex Hose Assemblies, Renew (2024) | 30055 | 1 | ||
| 2.4.57 | OE | WI #56 Flex Hose Assemblies, Renew (2025) | 30056 | |||
| 2.4.58 | OE | WI #57 Distilling Plant Pumps and Motors, Overhaul | 30057 | |||
| 2.4.59 | OE | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 30058 | |||
| 2.4.60 | OE | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 30059 | |||
| 2.4.61 | OE | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 30060 | |||
| 2.4.62 | OE | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 30061 | 1 | ||
| 2.4.63 | OE | WI #62 Boiler, Strength and Integrity Inspection | 30062 | |||
| 2.4.64 | OE | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 30063 | |||
| 2.4.65 | OE | WI #64 Warping Capstan, Inspect and Repair | 30064 | |||
| 2.4.66 | OE | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 30065 | |||
| 2.4.67 | OE | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 30066 | |||
| 2.4.68 | OE | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 30067 | |||
| 2.4.69 | OE | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 30068 | |||
| 1.2.1 | PC&I | WI #69 Non-Recurring Engineering | ||||
| 1.2.2 | PC&I | WI #70 Project Management and Planning, Perform | ||||
| 1.2.3 | PC&I | WI #71 Weight and Moment, Management | 30071 | 1 | ||
| 1.2.4 | PC&I | WI #72 NSWCPD CGMCS Installation, Coordinate | 30072 | |||
| 1.2.5 | PC&I | WI #73 NSWCPD PPD Installation, Coordinate | 30073 | |||
| 1.2.6 | PC&I | WI #74 Sewage System Grey Water Lift Stations, Install | 30074 | |||
| 1.2.7 | PC&I | WI #75 Sewage Retention Tank, Add | 30075 | |||
| 1.2.8 | PC&I | WI #76 Piping, Renewal | 30076 | |||
| 1.2.9 | PC&I | WI #77 Gyro Repeaters, Recapitalize | 30077 | |||
| 1.2.10 | PC&I | WI #78 Boiler, Recapitalize Ancillaries | 30078 | |||
| 1.2.11 | PC&I | WI #79 1MC, Renewal | 30079 | |||
| 1.2.12 | PC&I | WI #80 6MC, Refurbish | 30080 | |||
| 1.2.13 | PC&I | WI #81 Ship Service Air Compressors, Recapitalize | 30081 | |||
| 1.2.14 | PC&I | WI #82 Start Air System, Modify | 30082 | |||
| 1.2.15 | PC&I | WI #83 Oily Water Separator, Recapitalize | 30083 | |||
| 1.2.16 | PC&I | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 30084 | |||
| 1.2.17 | PC&I | WI #85 Dumbwaiter, Recapitalize | 30085 | |||
| 1.2.18 | PC&I | WI #86 Elevators, Upgrade | 30086 | |||
| 1.2.19 | PC&I | WI #87 Small Boat Davit Control Equipment, Relocation | 30087 | |||
| 1.2.20 | PC&I | WI #88 Commissary Equipment, Recapitalize | 30088 | |||
| 1.2.21 | PC&I | WI #89 Fire Detection System, Recapitalize | 30089 | |||
| 1.2.22 | PC&I | WI #90 400 Hz System, Modify | 30090 | |||
| 1.2.23 | PC&I | WI #91 False Overhead, Remove | 30091 | |||
| 1.2.24 | PC&I | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 30092 | |||
| 1.2.25 | PC&I | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 30093 | |||
| 1.2.26 | PC&I | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 30094 | |||
| 1.2.27 | PC&I | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 30095 | |||
| 1.2.28 | PC&I | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 30096 | |||
| 1.2.29 | PC&I | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 30097 | |||
| 1.2.30 | PC&I | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 30098 | |||
| 1.2.31 | PC&I | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 30099 | |||
| 1.2.32 | PC&I | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 30100 | |||
| 1.2.33 | PC&I | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 30101 | |||
| 1.2.34 | PC&I | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 30102 | |||
| 1.2.35 | PC&I | WI #103 False Overhead, Recapitalize | 30103 | |||
| 1.2.36 | PC&I | WI #104 Evaporator Salinity Monitoring, Recapitalize | 30104 | |||
| 1.2.37 | PC&I | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 30105 | |||
| 1.2.38 | PC&I | WI #106 Flooding Alarms, Recapitalize | 30106 | |||
| 1.2.39 | PC&I | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 30107 | |||
| 1.2.40 | PC&I | WI #108 Centerline Disconnect Coupling, Recapitalize | 30108 | |||
| 1.2.41 | OE | WI #109 Temporary Services, Contractor Facility, Provide | 30109 | 1 | ||
| 2.4.70 | OE | WI #110 Anticipated Growth | 30110 | |||
| 2.4.71 | OE | WI #111 Voyage Repairs | 30111 | |||
| PC&I | Early Delivery Incentive | 30200 | ||||
| Planned Total | $0.00 | $0.00 | $0.00 |
| Dry Dock 2025 Work Item Pricelist | ||||||
| WBS Number | Funding | Work Item | CLIN | Price | Mandated WIs | Contractor Planned WIs |
| 2.4.2 | OE | WI #1 Hull Plating (U/W Body) Inspect | 40001 | 1 | ||
| 2.4.3 | OE | WI #2 Hull Plating (U/W Body) Ultrasonic Testing | 40002 | 1 | ||
| 2.4.4 | OE | WI #3 Propulsion Shafting, Strain Gauge and Air Gap Readings (All) | 40003 | 1 | ||
| 2.4.5 | OE | WI #4 Centerline Propulsion Hub Remove and Reinstall | 40004 | 1 | ||
| 2.4.6 | OE | WI #5 Port Propulsion Hub Remove and Reinstall | 40005 | 1 | ||
| 2.4.7 | OE | WI #6 STBD Propulsion Hub Remove and Reinstall | 40006 | 1 | ||
| 2.4.8 | OE | WI #7 Centerline Propulsion Shafting Remove and Reinstall | 40007 | |||
| 2.4.9 | OE | Wi #8 Port Propulsion Shafting Remove and Reinstall | 40008 | |||
| 2.4.10 | OE | WI #9 STBD Propulsion Shafting Remove and Reinstall | 40009 | |||
| 2.4.11 | OE | WI #10 Sea Strainers (Hayward) Open, Clean, Inspect | 40010 | 1 | ||
| 2.4.12 | OE | WI #11 Sea Valves and Waster Pieces, Overhaul or Renew | 40011 | 1 | ||
| 2.4.13 | OE | WI #12 Boiler, Biennial Maintenance and Inspect | 40012 | 1 | ||
| 2.4.14 | OE | WI #13 Rudder and Rudder Stock, Remove and Inspect | 40013 | |||
| 2.4.15 | OE | WI #14 Cathodic Protection /Zinc Anodes, Renew | 40014 | 1 | ||
| 2.4.16 | OE | WI #15 Temporary Fuel Oil Offload and Storage, Dry-Dock | 40015 | 1 | ||
| 2.4.17 | OE | WI #16 Dry-Dock | 40016 | 1 | ||
| 2.4.18 | OE | WI #17 Dock and Sea Trial Performance, Support, Provide | 40017 | 1 | ||
| 2.4.19 | OE | WI #18 Miranda Davit, Annual Inspect | 40018 | 1 | ||
| 2.4.20 | OE | WI #19 Allied K280-70 Crane, Starboard, Annual Inspect and Repair | 40019 | 1 | ||
| 2.4.21 | OE | WI #20 Allied K280-70 Crane, Port, Annual Inspect and Repair | 40020 | 1 | ||
| 2.4.22 | OE | WI #21 Allied T60-60 Crane, Annual Inspect and Repair | 40021 | 1 | ||
| 2.4.23 | OE | WI #22 Fuel Oil Purifier (FOP) Overhaul, 4000 Hour | 40022 | |||
| 2.4.24 | OE | WI #23 Lube Oil Purifier (LOP) Overhaul, 4000 Hour | 40023 | 1 | ||
| 2.4.25 | OE | WI #24 Hydraulic Oil Purifier (HOP) Overhaul, 4000 Hour | 40024 | |||
| 2.4.26 | OE | WI #25 Propulsion Shaft Seal, Clean, Inspect, and Overhaul | 40025 | 1 | ||
| 2.4.27 | OE | WI #26 Shaft Handling Equipment, Maintenance and Storage | 40026 | 1 | ||
| 2.4.28 | OE | WI #27 Elevators, Annual Maintenance and Certification | 40027 | 1 | ||
| 2.4.29 | OE | WI #28 Dumbwaiter, Annual Maintenance and Certification | 40028 | 1 | ||
| 2.4.30 | OE | WI #29 Fixed Fire Suppression Systems, Annual Inspect and Certification | 40029 | 1 | ||
| 2.4.31 | OE | WI #30 Anchor Windlass, Service & Inspect | 40030 | 1 | ||
| 2.4.32 | OE | WI #31 Voids (Non-Assessable), Internal Surfaces, Preserve | 40031 | |||
| 2.4.33 | OE | WI #32 U/W Body, Preserve 100% | 40032 | |||
| 2.4.34 | OE | WI #33 U/W Body, Preserve (Partial) | 40033 | |||
| 2.4.35 | OE | WI #34 Stern Tube Interior Surfaces, Preserve 100% | 40034 | |||
| 2.4.36 | OE | WI #35 Anchor Chain(s) and Ground Tackle, Inspect & Repair | 40035 | |||
| 2.4.37 | OE | WI #36 Lube Oil Purifier (LOP) Overhaul 8,000 Hour | 40036 | |||
| 2.4.38 | OE | WI #37 Fuel Oil Purifier (FOP) Overhaul 8,000 Hour | 40037 | 1 | ||
| 2.4.39 | OE | WI #38 Hydraulic Oil Purifier (HOP) Overhaul, 8000 Hour | 40038 | 1 | ||
| 2.4.40 | OE | WI #39 Vent Ducts (Galley & Scullery), Commercial Cleaning | 40039 | |||
| 2.4.41 | OE | WI #40 Vent Ducts (Laundry Exhaust), Commercial Cleaning | 40040 | |||
| 2.4.42 | OE | WI #41 Evaporators (General), Overhaul | 40041 | |||
| 2.4.43 | OE | WI #42 Voids (Accessible), Clean and Inspect | 40042 | |||
| 2.4.44 | OE | WI #43 Flight Deck Nets, Overhaul 5 year | 40043 | |||
| 2.4.45 | OE | WI #44 Sewage Holding Tank(s) Clean/Inspect | 40044 | |||
| 2.4.46 | OE | WI #45 Tanks (Potable Water), Clean/Inspect | 40045 | |||
| 2.4.47 | OE | WI #46 Potable Water Pneumatic Tank and Hot Water Storage Tank, Clean, Inspect, Hydrotest | 40046 | |||
| 2.4.48 | OE | WI #47 Tanks (Diesel Fuel Oil), Clean and Inspect (2022) | 40047 | |||
| 2.4.49 | OE | WI #48 Tanks (Aviation Fuel), Clean and Inspect | 40048 | |||
| 2.4.50 | OE | WI #49 Voids (Non-Accessible), Leak Test | 40049 | |||
| 2.4.51 | OE | WI #50 Appendages (U/W), Leak Test | 40050 | |||
| 2.4.52 | OE | WI #51 Fire Prevention and Protection, Provide | 40051 | 1 | ||
| 2.4.53 | OE | WI #52 Flex Hose Assemblies, Renew (2021) | 40052 | |||
| 2.4.54 | OE | WI #53 Flex Hose Assemblies, Renew (2022) | 40053 | |||
| 2.4.55 | OE | WI #54 Flex Hose Assemblies, Renew (2023) | 40054 | |||
| 2.4.56 | OE | WI #55 Flex Hose Assemblies, Renew (2024) | 40055 | |||
| 2.4.57 | OE | WI #56 Flex Hose Assemblies, Renew (2025) | 40056 | 1 | ||
| 2.4.58 | OE | WI #57 Distilling Plant Pumps and Motors, Overhaul | 40057 | |||
| 2.4.59 | OE | WI #58 Main Reduction Gear (MRG), Maintenance and Inspection | 40058 | |||
| 2.4.60 | OE | WI #59 Main Propulsion Motors (MRM), Clean and Inspect | 40059 | |||
| 2.4.61 | OE | WI #60 Main Propulsion Generators (MRG), Clean and Inspect | 40060 | |||
| 2.4.62 | OE | WI #61 Tanks (Diesel Fuel Oil), Clean and Inspect (2024) | 40061 | |||
| 2.4.63 | OE | WI #62 Boiler, Strength and Integrity Inspection | 40062 | |||
| 2.4.64 | OE | WI #63 Tanks (Boilers Feedwater), Preserve "100%" | 40063 | |||
| 2.4.65 | OE | WI #64 Warping Capstan, Inspect and Repair | 40064 | 1 | ||
| 2.4.66 | OE | WI #65 Ship Services Diesel Generator Exhaust Stack Uptakes, Commercial Clean | 40065 | |||
| 2.4.67 | OE | WI #66 Main Diesel Engine Exhaust Stack Uptakes, Commercial Clean | 40066 | |||
| 2.4.68 | OE | WI #67 Boiler Exhaust Stack Uptakes, Commercial Clean | 40067 | 1 | ||
| 2.4.69 | OE | WI #68 Compressed Air Receivers and System Valves (all), Clean, Inspect, Hydro and Lift | 40068 | 1 | ||
| 1.2.1 | PC&I | WI #69 Non-Recurring Engineering | ||||
| 1.2.2 | PC&I | WI #70 Project Management and Planning, Perform | ||||
| 1.2.3 | PC&I | WI #71 Weight and Moment, Management | 40071 | 1 | ||
| 1.2.4 | PC&I | WI #72 NSWCPD CGMCS Installation, Coordinate | 40072 | |||
| 1.2.5 | PC&I | WI #73 NSWCPD PPD Installation, Coordinate | 40073 | |||
| 1.2.6 | PC&I | WI #74 Sewage System Grey Water Lift Stations, Install | 40074 | |||
| 1.2.7 | PC&I | WI #75 Sewage Retention Tank, Add | 40075 | |||
| 1.2.8 | PC&I | WI #76 Piping, Renewal | 40076 | |||
| 1.2.9 | PC&I | WI #77 Gyro Repeaters, Recapitalize | 40077 | |||
| 1.2.10 | PC&I | WI #78 Boiler, Recapitalize Ancillaries | 40078 | |||
| 1.2.11 | PC&I | WI #79 1MC, Renewal | 40079 | |||
| 1.2.12 | PC&I | WI #80 6MC, Refurbish | 40080 | |||
| 1.2.13 | PC&I | WI #81 Ship Service Air Compressors, Recapitalize | 40081 | |||
| 1.2.14 | PC&I | WI #82 Start Air System, Modify | 40082 | |||
| 1.2.15 | PC&I | WI #83 Oily Water Separator, Recapitalize | 40083 | |||
| 1.2.16 | PC&I | WI #84 Fire Pump Manual Bus Transfer, Recapitalize | 40084 | |||
| 1.2.17 | PC&I | WI #85 Dumbwaiter, Recapitalize | 40085 | |||
| 1.2.18 | PC&I | WI #86 Elevators, Upgrade | 40086 | |||
| 1.2.19 | PC&I | WI #87 Small Boat Davit Control Equipment, Relocation | 40087 | |||
| 1.2.20 | PC&I | WI #88 Commissary Equipment, Recapitalize | 40088 | |||
| 1.2.21 | PC&I | WI #89 Fire Detection System, Recapitalize | 40089 | |||
| 1.2.22 | PC&I | WI #90 400 Hz System, Modify | 40090 | |||
| 1.2.23 | PC&I | WI #91 False Overhead, Remove | 40091 | |||
| 1.2.24 | PC&I | WI #92 Heating Ventilation and Air Conditioning System, Groom, (Zones 1) | 40092 | |||
| 1.2.25 | PC&I | WI #93 Heating Ventilation and Air Conditioning System, Groom, (Zones 2) | 40093 | |||
| 1.2.26 | PC&I | WI #94 Heating Ventilation and Air Conditioning System, Groom, (Zones 3) | 40094 | |||
| 1.2.27 | PC&I | WI #95 Heating Ventilation and Air Conditioning System, Groom, (Zones 4) | 40095 | |||
| 1.2.28 | PC&I | WI #96 Heating Ventilation and Air Conditioning System, Groom, (Zones 5) | 40096 | |||
| 1.2.29 | PC&I | WI #97 Heating Ventilation and Air Conditioning System, Groom, (Zones 6) | 40097 | |||
| 1.2.30 | PC&I | WI #98 Heating Ventilation and Air Conditioning System, Groom, (Zones 7) | 40098 | |||
| 1.2.31 | PC&I | WI #99 Heating Ventilation and Air Conditioning System, Groom, (Zones 8) | 40099 | |||
| 1.2.32 | PC&I | WI #100 Heating Ventilation and Air Conditioning System, Groom, (Zones 9) | 40100 | |||
| 1.2.33 | PC&I | WI #101 Heating Ventilation and Air Conditioning System, Groom, (Zones 10) | 40101 | |||
| 1.2.34 | PC&I | WI #102 Heating Ventilation and Air Conditioning System, Groom, (Zones 11) | 40102 | |||
| 1.2.35 | PC&I | WI #103 False Overhead, Recapitalize | 40103 | |||
| 1.2.36 | PC&I | WI #104 Evaporator Salinity Monitoring, Recapitalize | 40104 | |||
| 1.2.37 | PC&I | WI #105 Ancillary Pump and Motor Assemblies, Recapitalize | 40105 | |||
| 1.2.38 | PC&I | WI #106 Flooding Alarms, Recapitalize | 40106 | |||
| 1.2.39 | PC&I | WI #107 Wing Shaft Disconnect Coupling, Recapitalize | 40107 | |||
| 1.2.40 | PC&I | WI #108 Centerline Disconnect Coupling, Recapitalize | 40108 | |||
| 1.2.41 | OE | WI #109 Temporary Services, Contractor Facility, Provide | 40109 | 1 | ||
| 2.4.70 | OE | WI #110 Anticipated Growth | 40110 | |||
| 2.4.71 | OE | WI #111 Voyage Repairs | 40111 | |||
| PC&I | Early Delivery Incentive | 40200 | ||||
| Planned Total | $0.00 | $0.00 | $0.00 |