This is a Questions and Answers document for a federal solicitation regarding turf treatment services at Culpeper National Cemetery. The document addresses a contractor's clarification request concerning fertilizer specifications, specifically regarding the NPK analysis discrepancy between the application schedule, which references 26-0-12 fertilizer, and the fertilization requirement paragraph, which references 24-0-12. The government's response confirms that either NPK analysis is acceptable provided the slow-release requirement is met, allowing contractors flexibility in their product selection while maintaining performance standards.

The underlying solicitation (QSE--36C78626Q50075) is a new grounds herbicide and fertilizer contract for Culpeper National Cemetery administered by the Department of Veterans Affairs National Cemetery Administration for Fiscal Year 26. The original quote submission deadline of February 26, 2026, by 12:00 PM EST was extended to February 27, 2026, by 12:00 PM EST. This Q&A response, issued as the second contractor question and answer document (36C78626Q50075 QandAr2), was released to provide clarity prior to final pricing and enable informed bid preparation.

View the file

Other files

File Type Posted
Attachment A Culpeper Fert SOW (FY-26).doc DOC document
Attachment B Price Schedule Culpeper Fert Weed Controlr.docx DOCX document
36C78626Q50075 QandAr.docx DOCX document
Attachment C Past performance questionnaire_ (002).docx DOCX document
Attachment D Wage Determination .docx DOCX document
6c Turfgrass3420_Handbook.pdf PDF
Culpeper combined synopisis_ 36C78626Q50075.docx DOCX document
NCA-operational-standards-and-measures-guidebook-dec2023.pdf PDF
Attachment B Price Schedule Culpeper Fert Weed Controlr.docx DOCX document
NCA-operational-standards-and-measures-guidebook-dec2023.pdf PDF
Attachment D Wage Determination .docx DOCX document
36C78626Q50075 QandAr2i.docx DOCX document
6c Turfgrass3420_Handbook.pdf PDF
Culpeper combined synopisis_ 36C78626Q50075.docx DOCX document
36C78626Q50075 QandAr.docx DOCX document
Attachment A Culpeper Fert SOW (FY-26).doc DOC document
Attachment C Past performance questionnaire_ (002).docx DOCX document
Culpeper combined synopisis_ 36C78626Q50075.docx DOCX document
Attachment B Price Schedule Culpeper Fert Weed Controlr.docx DOCX document
Attachment D Wage Determination .docx DOCX document
36C78626Q50075 QandAr.docx DOCX document
Attachment C Past performance questionnaire_ (002).docx DOCX document
Attachment A Culpeper Fert SOW (FY-26).doc DOC document
Attachment C Past performance questionnaire_ (002).docx DOCX document
Attachment D Wage Determination .docx DOCX document
Culpeper combined synopisis_ 36C78626Q50075.docx DOCX document
Attachment B Price Schedule Culpeper Fert Weed Controlr.docx DOCX document
Attachment A Culpeper Fert SOW (FY-26).doc DOC document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C78626Q50075 Contractor Question and Answer

For clarity prior to final pricing: the application schedule references 26-0-12 fertilizer in multiple rounds, while the fertilization requirement paragraph references 24-0-12. Please confirm which NPK analysis governs (or if either is acceptable provided the slow-release requirement is met).

Answer: Either is acceptable provided the slow-release requirement is met