This amendment modifies a solicitation for cooling water equipment and systems preventative maintenance, repair, and cooling water analysis and chemical treatment services. The Naval Surface Warfare Center Philadelphia Division seeks these services through an IDIQ contract awarded to a small business. A site visit will be held on February 20, 2024 at 9:30am EST, and all requests to attend must be submitted by February 16 to the identified Navy contacts. The services are required at various NSWCPD government buildings located at the Philadelphia Navy Yard.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See description of Amendment 0002 on page tw o.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Mar-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6449824R4028

X 9B. DATED (SEE ITEM 11)

09-Feb-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Mar-2024

CODE

NAVAL SURFACE WARFARE CENTER PHILA

CODE 0242, TYNISE CAIN

TYNISE.S.CAIN.CIV@US.NAVY.MIL

5001 SOUTH BROAD STREET

PHILADELPHIA PA 19112

N64498 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6449824R4028

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

Amendment 0002 is hereby issued to provided Government response to submitted questions. No further questions will be received at this time. The solicitation response date remains unchanged, 5 March 2024 2:00pm EST.

Reminder to potential offerors of submission of offer via DoD SAFE. Please reference Section L - Instructions, Conditions and Notices to Bidders

L2.2 PROPOSAL ELECTRONIC FORMAT AND SUBMISSION REQUIREMENTS

All other terms and conditions remain unchanged.

Questions/Answers:

Q1. Will the cooling towers be cleaned in-house by your engineers, or are you looking for someone to perform the cooling tower cleanings?

A1. No, not part of this requirement.

Q2. 77 Bldg cooling tower treatment is isolated and the controller is not feeding chemicals. Will your engineers be energizing the lines and repairing any leaks or dealing with any clogged lines?

A2. The system is not in use in the wintertime when we typically do not flow water to the tower. The chemical injection system uses a flow switch in the injection loop to detect operation of the cooling water system and that flow switch is only satisfied when the return water flows through the tower. Flowing through the tower creates more back pressure on the header to force enough flow into the injection loop to satisfy the switch. In the winter time, the normal operation has the return water bypassing the tower which lowers the pressure in the return header which does not activate the chemical injection system.

The system will be activated when the 77H cooling tower is put back in use. When this occurs the Contractor will be notified if there are any issues or they may discover some problems while performing their PMs. Based on Government review of the service reports provided by the current contractor all the numbers were within range when the system is operational.

Q3. If 77 Bldg controller is not working, or the lines are clogged and need repair will you upgrade the controller?

A3. The controller is Government equipment (see additional response information to question 2). If there is an issue or need for repair, it will be addressed via Preventative Maintenance or Corrective Maintenance portion of the contract.

Q4. Is there a list of System and Tonnage/volume I may be able to review?

A4. Please refer to Section C PWS Section 3.3.1 of the solicitation.

N6449824R4028

Q5. I just wanted to touch base with a few insights about the water treatment program for the large cooling tower system at building 77 that we just surveyed. This is an extremely large system that is obviously not being treated properly or sufficiently. Looking over the system specifications, the cooling tower is rated for 8333 tons (current operating load around 16%), with a Total System Volume of 800,000 gallons. With that volume of water, the daily biocide dosage should be 25 gallons. As we saw, there was only one 55 gallon container of biocide, which would run empty in two days.

A proper treatment program would have to utilize larger, 275- gallon totes for chemical applications, which would require fork-lift and in-house personnel assistance. This program would also require larger capacity feed pumps for both the biocides and inhibitor. It appears that this system has been operating like this for some time and that there is now renewed focus on getting things operating properly

Is that something that you were aware of, or expecting? I would not know how to set-up or price a treatment program any other way, so your input would be a great assistance.

A5. Historical reports indicate that the system functions properly. Offerors shall propose based on the existing equipment.

(End of Summary of Changes)