This is a technical specification document (Section 07 27 10) for building air barrier system construction and quality control at Portsmouth Naval Shipyard, Kittery, Maine, as part of SIOP 1740579 Production Facility Repairs project. The specification was updated by Amendment 009 on March 16, 2026.
The air barrier system must be continuous and contiguous across all enclosed surfaces, meeting strict leakage requirements tested at 75 Pa differential pressure. Specific requirements include: Air Barrier Annex Exterior Walls (5,500 square feet surface area with maximum allowable leakage rate of 0.25 CFM/sq.ft. and 1,375 total CFM maximum leakage); Air Barrier Annex Roof (3,400 square feet with 0.25 CFM/sq.ft. allowable rate and 850 total CFM maximum leakage); and Air Barrier Annex Doors (68 square feet with 0.25 CFM/sq.ft. allowable rate and 17 total CFM maximum leakage). Materials must conform to referenced ASTM standards including E2178 (air leakage of materials), E2357 (air barrier assemblies), D4541 (adhesion testing), and NFPA 285 (fire testing). The contractor must employ a qualified Air Barrier Inspector certified by the Air Barrier Association of America or demonstrating equivalent experience, provide a Design Review Report within 14 days of inspector approval, and conduct comprehensive quality control testing and inspection throughout installation including substrate preparation verification, adhesion testing, thickness measurements, and daily documentation. Testing and thermography reports must demonstrate system acceptance in accordance with Section 01 91 19 Building Enclosure Commissioning.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B60: PRODUCTION FACILITY REPAIRS - SIOP 1740579
PORTSMOUTH NAVAL SHIPYARD, KITTERY, MAINE
SECTION 07 27 10
BUILDING AIR BARRIER SYSTEM
08/23
PART 1 GENERAL
1.1 SUMMARY
This Section specifies the construction and quality control of the installation of an air barrier system. Construct the air barrier system indicated, taking responsibility for the means, methods, and workmanship of the installation of the air barrier system. The air barrier must be contiguous and connected across all surfaces of the enclosed air barrier envelope indicated. The maximum leakage requirements of individual air barrier components and materials are specified in the other specification sections covering these items.
This section also defines the maximum allowable leakage of the final air barrier system. The workmanship must be adequate to meet the maximum allowable leakage requirements of this specification. Test the assembled air barrier system to demonstrate that the building envelope is properly sealed and insulated. Passing the air barrier system leakage test and thermography test will result in system acceptance. Conform air barrier system leakage and thermography testing and reporting to the requirements of Section 01 91 19 BUILDING ENCLOSURE COMMISSIONING.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D4541 (2022) Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM E96/E96M (2024a) Standard Test Methods for Gravimetric Determination of Water Vapor Transmission Rate of Materials
ASTM E2178 (2021a) Standard Test Method for Determining Air Leakage Rate and Calculation of Air Permeance of Building Materials
ASTM E2357 (2018) Standard Test Method for Determining Air Leakage Rate of Air Barrier Assemblies
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 285 (2023) Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Wall Assemblies Containing Combustible
SECTION 07 27 10 Page 1 jriley Typewritten Text
AMENDMENT 009, 03-16-2026
Components
1.3 DEFINITIONS
The following terms as they apply to this section:
1.3.1 Air Barrier Accessory
Products designated to maintain air tightness between air barrier materials, air barrier assemblies and air barrier components, to fasten them to the structure of the building, or both (e.g., sealants, tapes, backer rods, transition membranes, fasteners, strapping, primers).
1.3.2 Air Barrier Assembly
The combination of air barrier materials and air barrier accessories that are designated and designed within the environmental separator to act as a continuous barrier to the movement of air through the environmental separator.
1.3.3 Air Barrier Component
Pre-manufactured elements such as windows, doors, dampers and service elements that are installed in the environmental separator.
1.3.4 Air Barrier Envelope
The combination of air barrier assemblies and air barrier components, connected by air barrier accessories that are designed to provide a continuous barrier to the movement of air through an environmental separator. There may be more than one air barrier envelope in a single building. Also known as Air Barrier System.
1.3.5 Air Barrier Material
A building material that is designed, tested or produced to provide the primary resistance to airflow through an air barrier assembly of a building enclosure.
1.3.6 Air Barrier System
Same as AIR BARRIER ENVELOPE.
1.3.7 Air Leakage Rate
The rate of airflow (CFM) driven through a unit surface area (sq.ft.) of an assembly or system by a unit static pressure difference (Pa) across the assembly. (example: 0.25 CFM/sq.ft. @ 75 Pa)
1.3.8 Air Leakage
The total airflow (CFM) driven through the air barrier system by a unit static pressure difference (Pa) across the air barrier envelope. (example:
6500 CFM @ 75 Pa)
1.3.9 Air Permeance
The tested rate of airflow (CFM) through a unit area (sq.ft.) of a material driven by unit static pressure difference (Pa) across the
SECTION 07 27 10 Page 2 material (example: 0.004 CFM/sq.ft. @ 75 Pa) as established by ASTM E2178.
1.3.10 Environmental Separator
The parts of a building that separate the controlled interior environment from the uncontrolled exterior environment, or that separate spaces within a building that have dissimilar environments. Also known as the Control Layer.
1.3.11 Vapor Permeance
Vapor permeance is separated into three classes based on the water vapor permeance of a material as tested via ASTM E96/E96M
Class I Vapor Barrier/Retarder 0.1 perm or less
Class II Vapor Barrier/Retarder 0.1 perm to 1.0 perm
Class III Vapor Barrier/Retarder 1.0 perm to 10 perm
1.4 PREPARATORY PHASE OR PRECONSTRUCTION CONFERENCE
Organize pre-construction conferences between the air barrier inspector and the sub-contractors involved in the construction of, or penetration of, the air barrier system to discuss where the work of each sub-contractor begins and ends, the sequence of installation, and each sub-contractor's responsibility to ensure airtight joints, junctures, penetrations and transitions between materials. Discuss the products, and assemblies of products specified in the different sections to be installed by the different sub-contractors.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 22 SUBMITTAL PROCEDURES (PWD ME):
SD-02 Shop Drawings
Air Barrier System Shop Drawings ; G
SD-03 Product Data
Air Barrier System Product Data ; G
SD-04 Samples
Material Samples For Air Barrier System ; G
SD-05 Design Data
Design Data And Calculations For The Air Barrier System ; G
SD-06 Test Reports
Design Review Report ; G
Testing and Inspection ; G
SECTION 07 27 10 Page 3
SD-07 Certificates
Air Barrier Inspector ; G
1.6 AIR BARRIER ENVELOPE SURFACE AREA AND LEAKAGE REQUIREMENTS
The building air barrier systems must meet the following leakage requirements. The allowable leakage rate and the maximum leakage are at a differential test pressure of 75 Pa.
Air Barrier Annex Exterior Walls
Surface Area 5,500 square feet
Architectural Only Test:
Allowable leakage rate 0.25 CFM/sq.ft
Maximum leakage 1,375 total CFM
Air Barrier Annex Roof
Surface Area 3,400 square feet
Architectural Only Test:
Allowable leakage rate 0.25 CFM/sq.ft
Maximum leakage 850 total CFM
Air Barrier Annex Doors
Surface Area 68 square feet
Architectural Only Test:
Allowable leakage rate 0.25 CFM/sq.ft
Maximum leakage 17 total CFM
1.7 AIR BARRIER INSPECTOR
Employ a designated Air Barrier Inspector on this project. The Air Barrier Inspector performs a Design Review, oversees quality control testing specified in these specifications, performs quality control air barrier inspection as specified, interfaces with the designer and product manufacturer's representatives to assure installation requirements are met, and verifies that the constructed work is in accordance with both the manufacturer's recommendations for products used, the content of this specification and other Contract drawings or documents. Qualifications
SECTION 07 27 10 Page 4 for the Air Barrier Inspector are as follows:
a. Training and certification as an Air Barrier Auditor from the Air Barrier Association of America (ABAA) or other third-party air barrier association.
b. Or, provide documentation in resume format that demonstrates that the individual proposed has the experience, knowledge, skills and abilities to fulfill the above stated duties as the air barrier inspector.
c. It is acceptable that this individual be employed by the firm performing the building pressurization test or another independent third-party entity, provided they meet the above requirements but must not be a member of the installing Contractor or firm.
Provide copies of Air Barrier Inspector qualifications 30 days after Notice to Proceed.
1.8 DESIGN REVIEW
Review the Contract Plans and Specifications and advise the Contracting Officer of any deficiencies that would prevent the construction of an effective air barrier system. Provide a Design Review Report individually listing each deficiency and the corresponding proposed corrective action necessary for a proper air barrier system. Provide copies of the Design Review Report not later than 14 days after approval of the Air Barrier Inspector Qualifications. Submit design data and calculations for the Air Barrier System for a manufacturer produced and warranted air barrier system.
PART 2 PRODUCTS
2.1 AIR BARRIER
Provide air barrier system of compatible parts from one or several manufacturers coordinated by the Contractor or provide a single warranted system provided by a primary manufacturer. The air barrier system as part of a tested exterior wall assembly must meet the conditions of acceptance as tested in accordance with NFPA 285 . Materials used for roof assembly air barrier must conform to the appropriate UL and FM wind and fire requirements for the specified roof assemblies.
If a complete air barrier system from a single manufacturer is utilized, whether warranted or not warranted, the air barrier system must conform to
ASTM E2357.
Materials in the following categories, as used in the air barrier system or assembly of the exterior wall system, are tested and are required to conform to ASTM E2178: Self-adhered sheet membranes, fluid applied membranes, factory bonded membranes/insulated metal panel assemblies to sheathing, and adhesive backed commercial building wrap and accessory products.
Other materials used as an air barrier such as concrete, glass, wood, metal or gypsum board may or may not conform to ASTM E2178 but are acceptable provided that when integrated into the air barrier system or assemblies they are not subject to material or environmental induced degradation in their final produced state once incorporated in the
SECTION 07 27 10 Page 5 permanent construction.
All materials used must be identifiable through manufacturer testing data or literature to be compatible with all the attached or adjoining materials or substrates used in the system.
Provide Air Barrier System Shop Drawings , Material Samples for Air Barrier System and Air Barrier System Product Data .
PART 3 EXECUTION
3.1 QUALITY CONTROL
3.1.1 Documentation and Reporting
Document the entire installation process on daily job site reports. These reports include information on the Installer, substrates, substrate preparation, products used, ambient and substrate temperature, the location of the air barrier installation, the results of the quality control procedures, and testing results.
3.1.2 Quality Control Testing And Inspection
Conduct the following tests and inspections as applicable in the presence of the Contracting Officer during installation of the air barrier system, and submit quality control reports as indicated below.
a. Provide a Daily Report of Observations with a copy to the Contracting Officer.
b. Inspect to assure continuity of the air barrier system throughout the building enclosure and that all gaps are covered, the covering is structurally sound, and all penetrations are sealed allowing for no infiltration or exfiltration through the air barrier system.
c. Inspect to assure structural support of the air barrier system to withstand design air pressures.
d. Inspect to assure masonry surfaces receiving air barrier materials are smooth, clean, and free of cavities, protrusions and mortar droppings, with mortar joints struck flush or as required by the manufacturer of the air barrier material.
e. Inspect and test to assure site conditions for application temperature, and dryness of substrates are within guidelines.
f. Inspect to assure substrate surfaces are properly primed, if applicable, and in accordance with manufacturer's instructions.
Priming must extend at least 2 inches beyond the air barrier material to make it obvious that the primer was applied to the substrate before the air barrier material.
g. Inspect to assure laps in materials are at least a 2-inch minimum, shingled in the correct direction or mastic applied in accordance with manufacturer's recommendations, and with no fishmouths.
h. Inspect to assure that a roller has been used to enhance adhesion.
Identify any defects such as fishmouths, wrinkles, areas of lost adhesion, and improper curing. Note the intended remedy for the
SECTION 07 27 10 Page 6 deficiencies.
i. Measure application thickness of liquid applied materials to assure that manufacturer's specifications for the specific substrate are met.
j. Inspect to assure that the correct materials are installed for compatibility.
k. Inspect to assure proper transitions for change in direction and structural support at gaps.
l. Inspect to assure proper connection between assemblies (membrane and sealants) for cleaning, preparation and priming of surfaces, structural support, integrity and continuity of seal.
m. Perform adhesion tests for fluid-applied and self-adhered air barrier membranes to assure that the manufacturer's specified adhesion strength properties are met. Determine the bond strength of coatings to substrate in accordance with ASTM D4541.
n. Provide written test reports of all tests performed.
3.2 REPAIR AND PROTECTION
Upon completion of inspection, testing, sample removal and similar services, repair damaged construction and restore substrates, coatings and finishes. Protect construction exposed by or for quality control service activities, and protect repaired construction.
-- End of Section --