N6247023R0004 Amend 0006.pdf
PDF 148 KB Posted
- Solicitation number
- N6247023R0004
View the file
Other files
Show 40 more
Latest 50 of 85 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
MILCON PROJECT P-91332 FAMILY HOUSING PHASE 4 AT VILLAGGIO AT VICENZA, ITALY
Please see Block 14 Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Jun-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247023R0004
X 9B. DATED (SEE ITEM 11)
28-Mar-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Jun-2023
CODE
COMNAVFACSYSCOM ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247023R0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0006
The purpose of this amendment is to:
1. Extend the Proposal Due Date
2. Respond to Pre-Proposal Inquiries (PPIs)
3. Specification Revisions
4. Drawing Revisions
5. Solicitation Revision
6. Provide Attachments
1. The proposal due date is extended from Tuesday, 20 June 2023 at 2:00 PM Norfolk, VA local time to Tuesday, 27 June 2023 at 2:00 PM Norfolk, VA local time.
2. Responses to PPIs
17. Inquiry: (Reference: Project Drawings) Please confirm the medium voltage (MV) loop will remain in continuous service for the duration of Phase 4, and that the Contractor may utilize this power source for construction power
Response: Please review Section 01 14 00 Work Restrictions for Utility Cutovers and Power Outage requests and coordination and review section 01 50 00 Temporary Construction Facilities and Controls for availability of existing utilities. Propose in accordance with the solicitation.
18. Inquiry: (Reference: Project Drawings) Given the changes in the drawings provided in Amendment 004, we would Kindly request you to extend the proposal due date by 3 weeks to accordingly update the suppliers and subcontractors quotes and allow for accurate pricing of the project and provide the Government with a competitive offer.
Response: Please see amendment detail below.
3. Specification Revisions
Section 01 33 00 SUBMITTAL PROCEDURES is deleted in its entirety and is replaced with Section 01 33 00 SUBMITTAL PROCEDURES dated 26 May 2023 and accompanies this amendment.
Section 11 24 23 FALL PROTECTION SYSTEM is deleted in its entirety and is replaced with Section 11 24 23 FALL PROTECTION SYSTEM dated 26 May 2023 and accompanies this amendment.
4. Drawing Revisions
The following drawings are revised as of 26 May 2023 and accompany this Amendment.
NAVFAC DWG NO. Title
14125983 (CS101) SITE LAYOUT PLAN / PLANIMETRIA DEL SITO
14125985 (CS103) SITE LAYOUT PLAN /PLANIMETRIA DEL SITO
14125990 (CS602) SITE LAYOUT PLAN COORDINATE TABLES / PLANIMETRIA DEL SITO
TABELLE DELLE COORDINATE
14126064 (CG103) GRADING AND DRAINAGE PLAN / PLANIMETRIA SISTEMAZIONE DEL
TERRENO E DRENAGGIO
14126092 (CP701) SIGNAGE AND PAVEMENT MARKING PLAN / PLANIMETRIA SEGNALETICA E
MARCATURA SU PAVIMENTAZIONE
14126093 (CP702) SIGNAGE AND PAVEMENT MARKING PLAN / PLANIMETRIA SEGNALETICA E
MARCATURA SU PAVIMENTAZIONE
14126094 (CP703) SIGNAGE AND PAVEMENT MARKING PLAN / PLANIMETRIA SEGNALETICA E
MARCATURA SU PAVIMENTAZIONE
14126117 (LS103) LANDSCAPE SITE PLAN / PIANTA PAESAGGIO DEL SITO
14126181 (LS604) LANDSCAPE SITE SCHEDULE / TABELLA PAESAGGIO DEL SITO
14126186 (LL103) LANDSCAPE LAYOUT PLAN / PIANTA LAYOUT PAESAGGIO
14126210 (LP103) LANDSCAPE PLANTING PLAN / PIANTA DI PIANTUMAZIONEPAESAGGIO
14126221 (LP601) LANDSCAPE PLANTING SCHEDULE / TABELLE PIANTUMAZIONE PAESAGGIO
14127153 (EP430) OH BUILDING 20160 GROUND FLOOR POWER PLAN / PIANTA
ALIMENTAZIONE OH BUILDING 20160 PIANO TERRA
14127187 (EP652) OH BUILDING 20160 ELECTRICAL PANELBOARD SCHEDULE / ELENCHI
QUADRO ELETTRICO TERMINALE OH BUILDING 20160
5. Revise the Solicitation:
CURRENT:
ALL SUBMITTALS MUST BE RECEIVED AT THE LOCATION SPECIFIED ABOVE PRIOR TO
2:00 PM Norfolk, VA local time, Tuesday 20 June 2023. LATE SUBMITTALS WILL NOT BE
CONSIDERED.
REVISED TO:
ALL SUBMITTALS MUST BE RECEIVED AT THE LOCATION SPECIFIED ABOVE PRIOR TO
2:00 PM Norfolk, VA local time, Tuesday 27 June 2023. LATE SUBMITTALS WILL NOT BE
CONSIDERED.
6. Provide Attachments
• Attachment AE_Amend0006_Spec
• Attachment AF_Amend0006_DWG_ELEC
• Attachment AG_Amend0006_DWG_CIVIL
• Attachment AH_Amend0006_DWG_LARCH
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 20-Jun-2023 02:00 PM to 27-Jun-2023 02:00 PM.
(End of Summary of Changes)