Repair Building Envelope and Interior Finishes, Building 298 WO # N40085-19-F-6882 Building 298, Cherry Point, North Carolina
PART 3 - CHAPTER 6 - Page 1 07/07/20
F20 SELECTIVE BUILDING DEMOLITION
GENERAL SYSTEMS REQUIREMENTS
Perform all off-site work necessary to meet the requirements of the project, local codes, reference standards, technical specifications and performance criteria.
Identify and obtain permits to comply with federal, state, and local regulatory requirements associated with this work. Complete the Permits Record of Decision (PROD) form with the first design submittal package.
Determine correct permit fees and pay said fees. Forward copies of permits, permit applications, and the completed PROD form to the Government's Civil Reviewer. Perform work in accordance with the approved permits.
Coordinate and obtain approval from the Contracting Officer for proposed haul route(s), work site access point(s), utility connections, employee parking location(s) and material laydown and storage area(s).
F2010 BUILDING ELEMENTS DEMOLITION
This project includes the demolition of interior partitions; ceiling systems; interior finishes; mechanical, electrical, plumbing, and fire alarm systems, for a complete building refurbishment. Exterior windows, portions of masonry veneer exterior wall, and exterior ramps and stairs will also be demolished and replaced.
F2010 1.3 DUST CONTROL
Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.
F2010 1.6 BURNING
Burning will not be permitted.
F201002
Exterior brick veneer will be replaced on entire building except Northeast Portion of Wing B where security must be maintained. This wing houses HR Offices on first floor and FRCE on second floor. Brick removal, window removal, and associated trim will not be required on the three sides of this wing. Work requires a complete removal of the brick, windows, doors, and trim from the footing to the roof on all other sides of the building.
F201003 ROOFING
Existing asphalt shingle roofing system will be demolished, removed to the deck for replacement.
F201004 INTERIOR CONSTRUCTION & FINISHES
The interior partition walls to be demolished are constructed of wood stud and gypsum board, plaster and lathe, and concrete masonry units. Interior partition walls will be demolished as required to achieve the Concept plan
PART 3 - CHAPTER 6 - Page 2 layout included in Part 6 Attachments. Interior floor finishes and subfloor materials will be removed to be replaced with new materials.
F201006 MECHANICAL SYSTEMS
Remove and dispose of all HVAC equipment, ductwork, and associated appurtenances.
Remove and dispose of all plumbing fixtures and piping. The underground main supply piping shall be removed and replaced.
All HVAC equipment and plumbing associated appurtenances associated with FRC-E and the library shall remain existing.
F201007 ELECTRICAL SYSTEMS
The existing electrical system shall be removed in its entirety, including panels, subpanels, junction boxes, wiring, switches, and receptacles, with the exception of the FRC-East and Library sections of the building. For the library section, only the existing light fixtures and their associated controls shall be removed. All other electrical devices within the library section of the building shall remain, unless otherwise directed by another section. All equipment located in the FRC-East section of the building shall remain existing.
F201008 EQUIPMENT & FURNISHINGS
Existing furnishings will be demolished and removed.
F2020 HAZARDOUS COMPONENT ABATEMENT
F2020 1.1 PRIVATE QUALIFIED PERSON (PQP)
The General Contractor is required to hire, as a first-tier subcontractor, a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification of the hazardous components work including: asbestos, and lead containing paint.
F2020 1.3 ASBESTOS
Abate Asbestos containing materials as identified in Asbestos Inspection Report included in Part 6.
F202004 INTERIOR CONSTRUCTION & FINISHES
Interior finishes include floor tile and mastic as described in Part 6 Attachments.
F202006 MECHANICAL SYSTEMS
Pipe insulation identified as Asbestos Containing Material (ACM).
F202007 ELECTRICAL SYSTEMS
No parts of the electrical system were discovered to contain asbestos.
PART 3 - CHAPTER 6 - Page 3
F2020 1.4 Lead Containing Paint
Lead containing paint has been identified in materials found in report included in Part 6 Attachments. Perform removal or encapsulation of lead containing paint in accordance with the specifications and plans provided in Part 6.
--End of Section--