240016 Pricing Sheet Awarding All Options.pdf
PDF 82 KB Posted
- Attached to
- Repair BEQ BB250
- Solicitation number
- N408525R9008
About this file
This document is a Pricing Sheet for the Repair BEQ BB250 project at MCB Camp Lejeune, North Carolina, solicitation number N40085-25-R-9008. The pricing sheet details seven Exhibit Line Item Numbers (ELINs) for specific renovation and remediation work, including interior renovations, lightning protection installation, parking lot milling and striping, soil replacement, and handling of unforeseen asbestos-containing materials and lead removal. Each ELIN requires contractors to provide unit pricing for specific quantities, with a total of 200 CY (cubic yards) for soil replacement, 200 LF (linear feet) for asbestos materials, and 1,000 SF (square feet) for additional asbestos-containing materials.
Key notes specify that offers must be submitted on all line items, with failure to do so potentially resulting in a non-responsive bid. The pricing includes all markups for overhead, labor burden, and profit. The government will evaluate offers by adding the prices for all ELINs (0001-0007), with the evaluation not obligating the government to exercise all options. The solicitation is specifically for General MACC Contractors within the ROICC Camp Lejeune area of responsibility, issued by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair BEQ BB250 Solicitation No. N40085-25-R-9008 MCB Camp Lejeune, North Carolina Project No. 24-0016
RFP 6/30/25
PRICING SHEET
Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:
ELIN 0001
Price includes completing all work associated with the interior renovations in accordance with the provided drawings and specifications, but excluding work described in ELIN 0002-0007. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0002
Price includes completing all work associated with installation of lightning protection in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001, and 0003-0007. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0003
Price includes completing all work associated with milling, overlaying, and striping of the parking lot at BEQ BB250 but excluding work described in ELIN 0001, 0002, and 0004-0007.
The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0004
Price includes completing all work associated with removal, disposal, and replacement of unsuitable soil but excluding work described in ELIN 0001-0003, 0005-0007. The price for this line item should include all applicable costs, overhead and profit for this work.
Quantity Unit Price Total
200 CY $_________ $___________________________________
ELIN 0005
Price includes completing all work associated with unforeseen asbestos containing material (ACM) (piping, pipe insulation, HVAC insulation, etc.). This includes identification, removal, wetting/handling, proper packaging, and disposal of ACM in accordance with all state/federal asbestos handling laws. This excludes work described in ELIN 0001-0004, 0006, and 0007. The price for this line item should include all applicable costs, overhead and profit for this work.
Repair BEQ BB250 Solicitation No. N40085-25-R-9008 MCB Camp Lejeune, North Carolina Project No. 24-0016
RFP 6/30/25
200 LF $_________ $___________________________________
ELIN 0006
Price includes completing all work associated with unforeseen asbestos containing material (ACM) (Adhesives, vinyl floor tiles, wall and ceiling insulation, roofing, etc.). This includes identification, removal, wetting/handling, proper packaging, and disposal of ACM in accordance with all state/federal asbestos handling laws. This excludes work described in ELIN 0001-0005 and 0007. The price for this line item should include all applicable costs, overhead and profit for this work.
1,000 SF $_________ $___________________________________
ELIN 0007
Price includes completing all work associated with unforeseen lead removal. This includes identification, scraping/removal, encapsulation, handling, proper packaging, and disposal of lead based material per local requirements of North Carolina. This excludes work described in ELIN 0001-0006. The price for this line item should include all applicable costs, overhead and profit for this work.
Quantity Unit Price Total
200 CY $_________ $___________________________________
TOTAL ELIN 0001 - 0007: $______________________________________
Notes A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.
B. ELINs shall include all markups (overhead, labor burden, and profit).
C. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0001 through 0007. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).
File details come from the government source that posted it. Updated .