This document is Amendment No. 0002 to a federal solicitation for repair work on Building G702/G703 at MCB Camp Lejeune, North Carolina. The amendment, effective July 15, 2026, answers a Request for Information, updates G702 documents, and includes a site visit sign-in requirement. The proposal deadline remains August 5, 2026, at 2:00 PM EST, and offerors must acknowledge receipt of this amendment to avoid rejection.
The amendment adds Specification Section 23 11 20 – Facility Gas Piping to the project requirements. This section establishes standards for natural gas piping installation within the building, including both above-ground steel piping and corrugated stainless steel tubing (CSST). Key requirements include compliance with NFPA 54 and AGA standards for materials, equipment, and installation procedures. Contractors must provide shop drawings, product data, test reports, and operation/maintenance documentation. The gas piping system must include proper joints, fittings, valves, regulators, hangers, supports, and seismic provisions. Installation requirements address protection and cleaning of materials, workmanship standards, underground and above-ground piping installation, insulating joints, pipe sleeves, fire seals, electrical bonding and grounding, shutoff valves, testing procedures (pressure tests and gas tests), and purging protocols. All work must conform to referenced standards including ASME, ASTM, ANSI, API, and CSA specifications, with materials meeting NSF and UL listings where applicable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0013.pdf | ||
| Amend 0012.pdf | ||
| Amend 0011.pdf | ||
| Amend 0010.pdf | ||
| Amend 0009.pdf | ||
| Amend 0008.pdf | ||
| Amend 0007.pdf | ||
| Amend 0006.pdf | ||
| Amend 0005.pdf | ||
| Amend 0004.pdf | ||
| Amend 0003.pdf | ||
| Amend 0001.pdf | ||
| RFP 250010.pdf | ||
| 25-0051 SID.pdf | ||
| 25-0051 BOD.pdf | ||
| 25-0010 BOD.pdf | ||
| 25-0010 APPD.pdf | ||
| N4008525B0051 DWG_Signed.pdf | ||
| N4008525B0051 Specs.pdf | ||
| N4008525B0010 Specs.pdf | ||
| 25-0010 GEO.pdf | ||
| 25-0051 Asbestos and Lead Report.pdf | ||
| 25-0051 APPD.pdf | ||
| N4008525B0010 DWG_Signed.pdf | ||
| 25-0010 Lead and Asbestos Report.pdf | ||
| 25-0051 DM.pdf | ||
| 25-0010 SID.pdf | ||
| 25-0051 GEO.pdf | ||
| 25-0010 DM for Repair BEQ 702.pdf |
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1
1. CONTRACT ID CODE
I
PAG
OF PAGES
I 100
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REO. NO.
5. PROJECT NO. (If applicble)
AMENDMENT NO. 0002 07/15/26 25-0010
6. ISSUED BY CODE N40085 7. ADMINISTERED BY (If other than Item 6) CODE I
NAVFAC Mid-Atlantic See Item 6 Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICIATION NO.
,c N40085-26-R-9050
9B. DA TED (SEE ITEM 11)
07/06/26
10A. MODIFICATION OF CONTRACT/ORDER NO.
1 OB. DA TED (SEE ITEM 11)
CODE I FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[RI The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended, [RI is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 1 OA.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43. 103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor D is not, D is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
25-0010, Repair BEQ G702/G703 Amendment 0002, Answer Request for Information, Update G702 Documents, Site Visit Sign-in
The time and date for receipt of proposals remains 5 August 2026 at 2PM EST.
This amendment should be acknowledged when your proposal is submitted.
the amendment may constitute grounds for rejection of a proposal.
Failure to acknowledge
See Continuation Page(s)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 1 OA, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
1 5B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
NSN 7540-01-152-8070
Previous edition unusable
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of Contracting Officer)
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
N40085-26-R-9050 Amendment 000 Page 2 of
CONTINUATION SHEET
1. QUESTION: Can this RFP be sent via email like all the other bids on this MACC.
RFP states electronic copy, hard copy and CD copy.
ANSWER: Proposals may be submitt via email.
E-Mail Address for Proposals: jessica.r.huebner.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil.
Replace the G702 project specification PROJECT TABLE OF CONTENTS with the revised table of contents including specification section 23 11 20 Facility Gas Piping (see pages 3-6).
Replace the G702 PROJECT SUBMITTAL REGISTER with revised project submittal register including specification section 23 11 20 (see pages 7-8 ).
Add G702 Specification Section 23 11 20 Facility Gas Piping footnoted to the project specifications. Specification added to clarify facility gas piping requirements (see pages 8 -9 ).
All other terms and conditions remain unchanged.