These documents are architectural and civil engineering design drawings for the 10th Marine and Combat Engineers Battalion Armories project located in Jacksonville, North Carolina. The comprehensive set of technical drawings covers multiple aspects of the facility construction, including:
Foundation and structural plans detail a building with dimensions of approximately 61.365 meters long, featuring concrete footings, roof plans, and transverse/longitudinal sections. The project includes specific design elements such as 229mm concrete slabs, treated timber rafters, moment connections, and various wall and column specifications. Technical drawings provide extensive details on structural components, including reinforcement requirements, joint configurations, masonry lintel designs, and foundation footing details. The plans also incorporate specifications for utilities, drainage systems, security features like fencing, and site grading, with careful attention to elevation markers, construction joint layouts, and compliance with engineering standards.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hadnot Point - 500-01A - Hadnot Point Map - Map Grid #: 104
Building Number: HP500Tank Type: AST
Capacity (gallons): 2000
Contents: No. 2 Fuel Oil
Use: Emergency Generator
Facility: HP-500 Weapons Storage
Date Installed: 10/31/2002
Status: In Use
Compliance Status: Not Compliant
Notes: Pipe sump with liquid sensor inop.
General
POC Info:
Tank Alias: n/a Latitude: 34.654773
Longitude: 77.341906
Date Closed:
Tank Construction: Double Wall Steel/HDPE Liner/Concrete Tank ID Label: Yes
Corrosion Protection: Paint Adequate Contents Label: No
Fabrication: Shop Fabricated Capacity Label: No
Tank Manufacturer: Convault No Smoking Label: Yes
UL Listed: Yes NFPA Diamond: Yes
STI Category: 1
Grounded: NoCRDM: Yes
Compat w/Contents: YesDirect Ground Contact: No
Integrity Inspection: Visual
Notes: Concrete shell cracked. Integrity Inspection Schedule: STI Periodic
Tank Design
Tank Ladder: Adequate
Tank Name Plate: No
Pipe Construction: SW Steel AG, DW FRP UG
Pipe Design
Exposure: Aboveground/Underground
Corrosion Protection: Paint Failed on AG, FRP for UG
Delivery System Supply: Suction
Delivery System Return: Pressure
Line Leak Detector: No
Secondary Containment: Yes
Release Detection Method: Visual for AG, None for UG
Notes: Pipe sump liquid sensor inoperable.
Pipe Support Design: Adequate
Spill Catchment: Spill Bucket
Drop Tube Flow Limiter: No
Spill & Overfill Prevention
Spill Bucket Capacity (gallons): 3
Whistle Vent: NoRemote Fill: N/A
Comm Link b/w Gauge & Pumper: VisualOverfill Protection: Liquid Level Gauge
Liquid Level Gauge: Clock Valves to Surface Security: N/A
Liquid Level Sensing Device Test: No Pump Starter Control Security: At the Generator or Boiler
High Level Alarms: None
Collision Barrier: No
Tank Leak Detection: None
ATG Annual Calibration: N/A
Notes: Neither alarm is functional.
Area Lighting: Adequate
Use of Low Melting Pt Materials: No
Electrical Wiring Exposed: No
NFPA
Normal Vent on Primary: Yes
Tank Separation From Building: Adequate
Emergency Vent on Primary: Yes
Tank to Tank Separation: N/A
Emergency Vent on Interstice: N/A
Primary Normal Vent Ht (ft above ground): 20
Remote Fillport Sep. from Tank: N/A
Tank Vented Outside: Yes
Notes: Normal vent pipe corroded.
Tank Fillport Outside: Yes
Primary Normal Vent Ht Adequate: Yes
Distance of Primary Vent from Air Intakes: Adequate
Tank Sec. Cont.: Double Wall
Secondary Containment
Tank Sec. Cont. Dim. (in.): N/A
Tank Sec. Cont. Dim. Adjusted for Freeboard (in.):
N/A
Tank Sec. Cont. Volume Status: 100%
Tank Sec. Cont. Drain Mechanism: N/A
Tank Sec. Cont. Drain Security: N/A
Truck Loading/Offloading Cont.: N/A
Truck Cont. Dim. (in.): N/A
Truck Cont. Volume Status: N/A
Truck Departure Warning System: N/A
Tanker Truck Inspection: N/A
Notes: Foundation has minor washout.
Material: N/A
Spill Prevention & Response
Spill Direction: All modes: S 100 feet to storm drain.
Ultimate Discharge: Outfall OHP-035.
Notes:
Typical Discharge Failure Mode:
Photo
1, 2, 5, 13, 14
| HP 500 9158 BE&RW-10th dwg fuel tank detail |
| HP 500 9158DBCivStruct-10th Dwg |
| Civil Title Sheet |
| T-1 TITLE SHEET, INDEX AND VICINITY MAPS |
| T-2 LEGEND, ABBREVIATIONS AND GENERAL NOTES |
| Demolition |
| D-1 10TH MARINE ARMORY DEMOLITION PLAN |
| D-2 COMBAT ENGINEERS BATTALION ARMORY DEMOLITION PLAN |
| Civil |
| C-1 10TH MARINE ARMORY LAYOUT AND UTILITIES PLAN |
| C-2 10TH MARINE ARMORY LAYOUT AND UTILITIES PLAN |
| C-3 10TH MARINE ARMORY GRADING AND DRAINAGE PLAN |
| C-4 COMBAT ENGINEERS BATTALION ARMORY LAYOUT AND UTILITIES PLAN |
| C-5 COMBAT ENGINEERS BATTALION ARMORY LAYOUT AND UTILITIES PLAN |
| C-6 COMBAT ENGINEERS BATTALION ARMORY GRADING AND DRAINAGE PLAN |
| C-7 10TH MARINE ARMORY TYP. SECTIONS |
| C-8 COMBAT ENGINEERS BATTALION ARMORY TYP. SECTIONS |
| C-9 TYP. DETENTION BASIN SECTIONS AND DETAILS |
| C-10 TYP. DETENTION BASIN SECTIONS AND DETAILS |
| C-11 SANITARY SEWER PROFILES |
| C-12 STORM DRAIN PROFILES |
| C-13 TYP. PAVEMENT AND WALK DETAILS |
| C-14 TYP. WATER SYSTEM DETAILS |
| C-15 TYP. SEWER DETAILS |
| C-16 TYP. DRAINAGE DTAILS |
| C-17 TYP. SECURITY FENCE DETAILS |
| C-18 CONCRETE PAVEMENT JOINT LAYOUT PLANS |
| C-19 SOIL BORING LOCATIONS, ABBREVIATIONS AND LEGEND |
| C-20 10TH MARINE - SOIL BORING LOGS |
| C-21 COMBAT ENGINEERS BN - SOIL BORING LOG |
| Structural Title Sheet |
| T-1 TITLE SHEET, INDEX AND VICINITY MAPS |
| Structural |
| S-1 STRUCTURAL GENERAL NOTES, ABBREVIATIONS AND LEGEND |
| S-2 10TH MARINE FOUNDATION PLAN |
| S-3 10TH MARINE ROOF PLAN |
| S-4 COMBAT ENGINEERS FOUNDATION AND ROOF PLAN |
| S-5 TYP. FOUNDATION, BEAM AND COLUMN DETAILS |
| S-6 TYP. SECTIONS THROUGH BUILDINGS |
| S-7 MISC. DETAILS |
| S-8 MISC. DETAILS |
| HP500 Bulk Storage Tank |
| RE_ P1556 MILCON - Renovate HP500 - Remove AST_UST on north side of facility |
| Scan from 2023-07-19 02_24_26 PM |
| Scan from 2023-07-19 02_24_52 PM |
| Scan from 2023-07-19 02_31_14 PM |
File details come from the government source that posted it. Updated .