About this file
This document is a solicitation for a design-build construction project at Marine Corps Base Camp Lejeune, North Carolina. The project involves designing and constructing a Parachute Maintenance Facility with a Paraloft and a Supply Warehouse for the 2nd Radio Battalion, with an estimated budget of $18,030,800. The facilities will be low-rise steel frame structures with reinforced concrete masonry walls, brick veneer, and standing seam metal roof, featuring Georgian or Colonial revival architectural style.
The solicitation is issued by Naval Facilities Engineering Systems Command Mid-Atlantic and is limited to five pre-qualified Multiple Award Construction Contract (MACC) holders: Ameresco, Sauer Incorporated, Archer Western Federal JV, The Whiting-Turner Contracting Company, and RQ Construction, LLC. Proposals are due on 24 April 2025 at 2:00 PM EST and must be submitted electronically through the PIEE Solicitation Module. The project has a 780-calendar-day completion timeline, including 15 days for bond and insurance submission, with liquidated damages of $1,779.96 per calendar day of delay.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design-Build P1458 2nd Radio Battalion Complex, Phase 2, Solicitation N4008525R2523
Parachute and Supply Facilities Work Order 1397586
Marine Corps Base, Camp Lejeune, North Carolina
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, MID-ATLANTIC
9324 VIRGINIA AVE, BLDG Z-140
NAVAL STATION NORFOLK, NORFOLK, VA 23511
POC: MARY ANN POOL
MARY.A.POOL3.CIV@US.NAVY.MIL; (757) 341-1650
DESIGN-BUILD (DB)/DESIGN-BID-BUILD (DBB), INDEFINITE DELIVERY/INDEFINITE
QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR
LARGE GENERAL CONSTRUCTION PROJECTS IN MARINE CORPS FACILITIES,
PRIMARILY CAMP LEJEUNE AND CHERRY POINT, NORTH CAROLINA, NAVFAC MID-
ATLANTIC
PROPOSED TASK ORDER: N40085-25-R-2523
DESIGN-BUILD (DB), P-1458 2ND RADIO BATTALION COMPLEX, PHASE 2, PARACHUTE
AND SUPPLY FACILITIES, MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA
DATE OF SOLICITATION: 25 March 2025
MACC CONTRACT HOLDERS:
N4008520D0032
AMERESCO
5550 Seventy-Seven Center Drive
Suite 380
Charlotte, NC 28217
Email: nbulgarino@ameresco.com
N4008520D0035
Sauer Incorporated
11223 Phillips Parkway Drive East
Jacksonville, FL 32256
Email: Sauerjaxestimating@sauer-inc.com
N4008520D0033
Archer Western Federal JV
929 West Adams Street
Chicago, IL 60607
Email: dmarchiori@walshgroup.com adecarlo@walshgroup.com
N4008520D0036
The Whiting-Turner Contracting Company
6305 Ivy Lane, Suite 800
Greenbelt, Maryland 20770
Email: sam.abutaleb@whiting-turner.com
N4008520D0034
RQ Construction, LLC
1620 Faraday Ave.
Carlsbad, CA 92008
Email: grogers@rqconstruction.com tnichols@rqconstruction.com mailto:mary.a.pool3.civ@us.navy.mil mailto:nbulgarino@ameresco.com mailto:Sauerjaxestimating@sauer-inc.com mailto:dmarchiori@walshgroup.com mailto:adecarlo@walshgroup.com mailto:sam.abutale@whiting-turner.com mailto:grogers@rqconstruction.com mailto:tnichols@rqconstruction.com
General Requirements
All terms and conditions of N4008520D0032/0033/0034/0035/0036 Indefinite Delivery Quantity
Contract apply to this solicitation. Please review your MACC award document for guidance on contract clauses and requirements that may pertain to this order. All contract clauses in the Basic Contract by reference or full text remain in effect unless superseded by this task order. You are responsible for adhering to all applicable clauses, even if they are not stated in this RFP package or the Task Order award document. For clarification on any clause or other contractual issues, please contact Mary Ann Pool at mary.a.pool3.civ@us.navy.mil.
Amendments will be posted directly to www.SAM.gov.
Incorporation of Technical Proposal: The Contractor’s technical proposal, including revisions and amendments, made prior to contract award and a copy of which is in the possession of both parties, will be incorporated into this contract upon award by reference with the same force and effect as if set forth in full text. All contractor personnel shall meet or exceed the qualification standards, experience levels and trade background set forth in the technical proposal. In the event of an inconsistency between the provisions of this contract and the technical proposal, the inconsistency shall be resolved by giving precedence in the following order: (i) Task Order, (ii) the contract (excluding the technical proposal), and then (iii) the technical proposal.
NAVFAC Solicitation No.: N4008525R2523
NAVFAC Specification/Drawings: Work Order No. 1397586 (Attachment A)
Title: P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities
Location of the Work: Marine Corps Base, Camp Lejeune, North Carolina
Description of the Work: This project will design and construct a Parachute Maintenance Facility with a
Paraloft, and a Supply Warehouse for the 2nd Radio Battalion at Camp Lejeune, North Carolina.
Construction includes low-rise steel frames facilities with reinforced concrete masonry unit with reinforced masonry walls, brick veneer, reinforced concrete floors and standing seam metal roof. The
Supply Warehouse includes administrative and support space, storage bays, secured storage, and shipping/receiving area. The Parachute Maintenance Facility includes a parachute washing area with drying tower, administrative and support space, training area, sewing and fabrication room, and parachute packing and storage areas. Building Architecture should be Georgian or Colonial revival in classification as defined by the BEAP (Base Exterior Architecture Plan) for Hadnot Point commensurate with facility importance. Special construction features include premium for compliance with Base Exterior
Architectural Plan. This project will provide Anti-Terrorism/Force Protection (ATFP) features and comply with ATFP regulations, physical security mitigation in accordance with DOD Minimum Anti-
Terrorism Standards for Buildings. Information systems will include basic telephone, computer network, fiber optic, security and fire alarm systems and infrastructure. Mechanical systems include heating, ventilation and air conditioning, water lines, plumbing and plumbing fixtures, fire protection systems and supply lines, sanitary sewer system, oil/water separators, and storm drainage piping & culverts. Built-in equipment includes storage racks, parachute-rigging system, parachute drying system, antenna support mast at roof, and fire pumps.
Estimated Budget Amount for Design and Construction: Approximately $18,030,800 (CLIN 0001).
http://www.sam.gov/
Marine Corps Base, Camp Lejeune, North Carolina
Time for Completion: In accordance with FAR 52.211-10 Commencement, Prosecution, and
Completion of Work, the duration of this task order shall be 780 calendar days from date of award
(includes 15 calendar days for submission and approval of bonds and insurance).
Wage Determination: Department of Labor (DoL) General Decision Number NC20250010 01/03/2025 applies to this work (Attachment B). The wage determination version in effect at the time of award shall apply to the work performed under this contract.
Liquidated Damages: In accordance with FAR 52.211-12 Liquidated Damages, if the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,779.96 for each calendar day of delay until the work is completed or accepted.
Utilities: In accordance with FAR 52.236-14 Availability and Use of Utility Services - The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.
Record Shop Drawings: In accordance with FAR 52.236-21 Specifications and Drawings for
Construction, record shop drawings are required. Reproducible copies of these record drawings are required.
Government Furnished Property: Not Included.
Options: In accordance with 52.217-5 Evaluation of Options, except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement.
Evaluation of options will not obligate the Government to exercise the option(s).
Bond Requirements: In accordance with FAR 52.228-1, Bid Guarantees, each Offeror shall submit with its offer a guarantee bond (Standard Form 24) in a penal sum equal to at least 20 percent of the offer price or $3,000,000, whichever is less.
The Offeror shall submit an electronic copy with the price proposal form and a hard copy of your bid bond must be submitted to the address listed in the title above, within three (3) days after the due date and time for receipt of proposals. Failure to submit a bid bond by the deadline will result in your proposal being removed from consideration.
Performance and Payment Bonds are required from the contract task order awardee ten (10) calendar days after date of award.
Proposal Acceptance Period: Proposal acceptance period shall be 120 days from receipt of offers.
Pre-Proposal Inquiries (PPIs): Offerors who determine that the technical and or contractual requirements of this RFP require clarification(s) in order to permit submittal of a responsive proposal shall submit all questions in writing. All inquiries shall be submitted via email to Mary Ann Pool at mary.a.pool3.civ@us.navy.mil no later than, fourteen (14) calendar days prior to proposal due date.
PPIs received after this timeframe may not receive a response. Additionally, all inquiries shall be submitted using the Pre-Proposal Inquiry (PPI) form (Attachment C). Do not submit the same inquiry https://www.acquisition.gov/far/17.206#FAR_17_206
Marine Corps Base, Camp Lejeune, North Carolina more than once. Please verify that inquiries submitted by you on behalf of your subcontractors are not duplicates. A response will be published via an amendment by email to MACC holders.
Site Visit: Information to be provided via amendment.
Proposal Due Date: Thursday, 24 April 2025 at 02:00PM EST. LATE PROPOSALS WILL NOT BE
ACCEPTED.
PROPOSAL SUBMISSION INSTRUCTIONS: OFFERORS SHALL SUBMIT ELECTRONIC
PROPOSALS (.PDF FORMAT) IN RESPONSE TO THIS SOLICITATION. Only the PIEE
Solicitation Module is authorized for the submission of electronic proposals in response to this solicitation. Electronic proposal submissions should be no larger than 1.9 GB per file.
Offerors shall ensure that the Government has received the electronic proposal prior to the date and time specified. PIEE Solicitation Vendor Access Instructions are provided via Attachment E. EMAILED
SUBMISSIONS WILL NOT BE ACCEPTED.
Offerors shall allow adequate time to upload files which may be slower for non-DoD users and to avoid other technical difficulties that may be encountered. Offerors are also responsible for submitting files in the format specified and consistent with requirements stated elsewhere in this solicitation. Files that cannot be opened or are otherwise missing the required content are the responsibility of the Offeror.
PIEE system will record the date and time of package submittal. The date and time of package submittal recorded in PIEE shall govern the timeliness of any proposal submission. PROPOSALS NOT
RECEIVED BY THE DATE AND TIME SPECIFIC IN THE RFP SHALL BE TREATED IN
ACCORDANCE WITH FAR 52.215-1 “INSTRUCTIONS TO OFFERORS – COMPETITIVE
ACQUISITIONS” AND MAY BE REJECTED.
In response to this request for proposal, the complete proposal shall include the Price Proposal and the
Non-Cost/Price Factors Proposal, submitted in accordance with the Basis of Evaluation and Submittal
Requirements for Each Factor.
Basis for Award:
The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value-the proposal most advantageous to the Government, price and other factors considered.
The Government intends to evaluate proposals and award a contract without discussions with offerors
(except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the
Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
Marine Corps Base, Camp Lejeune, North Carolina
The single technical factor is of equal importance to the performance confidence assessment (past performance) rating; and all non-price factors, when combined, are approximately equal in importance to price.
Any proposal found to have a Deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the Deficiency is corrected through discussions
(if held). An Unacceptable rating for the non-cost/price factor will result in an overall rating of
“Unacceptable” for the non-cost/price factors, unless corrected through discussions (if held). Proposals may be found to have either a Significant Weakness or multiple Weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified Weakness(s) and the associated risk to successful contract performance resulting from the Weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
Evaluation Factors for Award
The Proposed Task Order will be awarded to the responsible offeror offering the best value to the
Government. To make a determination of Best Value, the Government shall evaluate each offeror on the following criteria:
Factor 1 – Technical Solution
Factor 2 – Past Performance
The relative order of importance of the non-cost/price evaluation factors is the technical factor (Factor 1 –
Technical Solution) is of equal importance to the performance confidence assessment (Factor 2 – Past
Performance). The non-cost/price factors, when combined, are approximately equal to price.
The importance of price will increase if the Offerors’ non-price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
Non-Cost/Price Evaluation Factors
All submissions shall include the following:
The Offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below. The Price and Non-price proposals shall be submitted in separate files and submitted in
Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered; likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR
15.208.
All submissions shall include the following characteristics:
• One complete electronic copy of the non-price/technical proposal factors as a single .pdf searchable file with bookmarks
• Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, Unique Entity Identifier (UEI), Cage Code, Point of
Contact (POC), Title, Phone Number for the POC, and Email Address for the POC;
Marine Corps Base, Camp Lejeune, North Carolina
• Text pages must be 8 ½” x 11” format; Drawings pages may be 11”x17” format;
• 10-point font, Times New Roman;
• Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated. Information submitted beyond any of the page limits below will not be considered.
Factor 1 – Technical Solution
(i) Solicitation Submittal Requirements:
Provide a narrative describing the technical approach to the project that meets the requirements of the
RFP. The narrative shall include, but is not limited to:
- Interior circulation/space adjacencies and square footage. Describe how pedestrian access to, and vehicular traffic through, the various areas of the facilities are coordinated. Highlight items that illustrate an understanding of the workflow through the various facilities, as well as individual segments of each facility supporting different functional requirements.
- Exterior façade describing how the proposed construction integrates with the surrounding area and existing base facilities design or architectural theme.
- Site layout including a description of the building orientations, roadways, parking (include ingress and egress), walkways, emergency vehicle access, ATFP standoff distances, and drainage
/low impact development (LID). Describe vehicular circulation around the facilities, in particular equipment / trailers that must navigate the exterior, as well as enter and exit from the facility.
Narrative shall not exceed four (4) pages. A minimum of three conceptual drawings are required:
Conceptual drawings of site plan, building floor plans and building evaluation. However, up to six (6) conceptual drawings may be provided to supplement the narrative (i.e., each facility floor plan per level, all exterior elevations for each facility, and site plan(s)).
(ii) Basis of Evaluation:
The Government will evaluate the narrative and conceptual drawings considering the extent to which the
Offeror demonstrates a clear understanding of the architectural and engineering requirements of the project. The Government will evaluate the effectiveness of the design-build team's technical solution to determine the likelihood that the work will be performed in accordance with the technical requirements of the RFP.
Factor 2 – Past Performance:
Offerors do not need to provide any information under this factor as the Government will base the evaluation on known past performance on task orders awarded under this Multiple Award Contract
(MAC). However, Offerors may provide any information on problems encountered and the corrective actions taken on task orders under this MAC. Offerors may also address any adverse past performance issues under this MAC. Explanations shall not exceed or four (4) pages in total.
(ii) Basis of Evaluation:
This evaluation focuses on how well the Offeror performed on projects under this Multiple Award
Contract. More emphasis will be placed on task orders that are more similar to this RFP. The
Government reserves the right to obtain information for use in the evaluation of past performance other than projects performed under this Multiple Award Contract from any and all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Rating System (CPARS), inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the
Offeror.
The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the
Offeror’s past performance will be used as a means of evaluating the Offeror’s ability to successfully meet the requirements of the RFP.
Offerors lacking past performance information on other task orders under this Multiple Award Contract will not be evaluated favorably or unfavorably in past performance and will receive a Neutral Confidence rating.
Price
The offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below. The Price and Non-price proposals shall be submitted in separate files and submitted in
Portable Document Format (PDF). In addition, non-price/technical information included in the price proposal will not be considered; likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR
All submissions shall include the following:
• Cover page with solicitation number, solicitation title, offeror name, address, phone number, fax number, UEI in SAM, CAGE code, POC Name, POC phone number, and POC email address;
• All amendments acknowledged;
• Completed Price Proposal Form;
• Federal Awardee Performance and Integrity Information System (FAPIIS) Certification as required by FAR 52.209-7, Information Regarding Responsibility Matters;
• Copy of Representation and Certifications and proof of registration in System for Award
Management (SAM);
• Confirmation of filing of Veterans’ Employment and Training (VETS) VETS-4212 for the
2023/2024 filing cycle;
• Bid Guarantee in accordance with FAR Clause 52.228-1, Bid Guarantee. Amount shall be at least
20 percent of the proposed price, but shall not exceed $3 million; and
The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). All required proposal documents shall be submitted in accordance with FAR
Marine Corps Base, Camp Lejeune, North Carolina
The price proposal shall be submitted separately, but at the same time as the technical proposal.
Furthermore, technical information contained in the price proposal will not be considered. Likewise, price information contained in the technical proposal will not be considered.
(ii) Basis of Evaluation: The Government will evaluate price based on the total lump sum price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
a. Comparison of proposed prices received in response to the RFP.
b. Comparison of proposed prices with the Independent Government Cost Estimate (IGCE).
c. Comparison of proposed prices with available historical information.
d. Comparison of market survey results.
Evaluation
1. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value-the proposal most advantageous to the Government, price and other factors considered.
2. The Government intends to evaluate proposals and award a contract without discussions with offerors
(except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the
Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
3. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
4. The single technical factor is of equal importance to the performance confidence assessment (past performance) rating; and all non-price factors, when combined, are approximately equal in importance to price.
5. Any proposal found to have a Deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the Deficiency is corrected through discussions (if held). An Unacceptable rating for the non-cost/price factor will result in an overall rating of “Unacceptable” for the non-cost/price factors, unless corrected through discussions (if held). Proposals may be found to have either a Significant Weakness or multiple Weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified Weakness(s) and the associated risk to successful contract performance resulting from the Weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
Attachments:
ATTACHMENT A: Work Order No. 1397586
ATTACHMENT B: Wage Determination NC20250010
ATTACHMENT C: Pre-Proposal Inquiry (PPI) form
ATTACHMENT D: Price Proposal Form
ATTACHMENT E: PIEE Solicitation Vendor Access Instructions
RECAP OF IMPORTANT DATES:
SOLICITATION DATE: 25 MARCH 2025
SITE VISIT DATE: TBD
PPI CUT OFF DATE: 14 DAYS BEFORE PROPOSAL DUE DATE
PROPOSAL DUE DATE: 24 APRIL 2025 at 1400 EST
ATTACHMENT B
"General Decision Number: NC20250010 01/03/2025
Superseded General Decision Number: NC20240010
State: North Carolina
Construction Type: Building
County: Onslow County in North Carolina.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the |
|2022, or the contract is | contract. |
|renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at |
|after January 30, 2022: | least $17.75 per hour (or |
| | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2025. |
|If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the |
|January 29, 2022, and the | contract. |
|contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least |
|30, 2022: | $13.30 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
| | hours performing on that |
| | contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the
Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/03/2025
IRON0848-003 07/01/2024
Rates Fringes
IRONWORKER.......................$ 28.75 17.50
PLUM0421-006 07/01/2023
PIPEFITTER.......................$ 33.96 13.48
SUNC2018-010 08/08/2023
BRICKLAYER.......................$ 19.13 0.00
CARPENTER, Excludes Form Work....$ 18.11 2.63
CEMENT MASON/CONCRETE FINISHER...$ 16.72 ** 0.00
ELECTRICIAN......................$ 22.15 5.93
FORM WORKER......................$ 14.51 ** 1.88
LABORER: Common or General......$ 11.98 ** 0.81
LABORER: Mason Tender - Brick...$ 13.17 ** 0.00
LABORER: Mason Tender -
Cement/Concrete..................$ 15.26 ** 0.00
LABORER: Pipelayer..............$ 16.33 ** 3.11
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 21.00 2.89
OPERATOR: Bulldozer.............$ 17.54 ** 2.63
OPERATOR: Forklift..............$ 16.75 ** 0.00
OPERATOR: Grader/Blade..........$ 22.68 3.27
OPERATOR: Roller................$ 15.31 ** 1.46
PAINTER..........................$ 15.55 ** 1.05
PLUMBER..........................$ 23.11 0.00
ROOFER...........................$ 18.26 4.38
SHEET METAL WORKER...............$ 19.67 13.27
TRUCK DRIVER: Dump Truck........$ 15.98 ** 2.93
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658
($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey
Marine Corps Base, Camp Lejeune, North Carolina rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
Marine Corps Base, Camp Lejeune, North Carolina ?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
2) If an initial decision has been issued, then any interested
Marine Corps Base, Camp Lejeune, North Carolina party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
Washington, DC 20210.
END OF GENERAL DECISION"