N4008525R2523 Amendment 0012.pdf

PDF 543 KB Posted

Attached to
P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities
Solicitation number
N4008525R2523
Issued by

About this file

This document is an Amendment (0012) to Solicitation N4008525R2523 for the P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities project at Marine Corps Base Camp Lejeune, North Carolina. The amendment provides responses to Pre-Proposal Inquiries (PPIs) addressing multiple technical and procedural questions, including clarifications on geotechnical engineering restrictions, drawing interpretations, quality control specialist requirements, and environmental compliance standards. Key clarifications include: confirmation that contractors are prohibited from hiring the geotechnical engineer who previously provided project data, specification that drawings are for informational purposes only, requirements for separate QC Manager, SSHO, and Superintendent roles, mandatory SSPC QP9 and QP1 certifications for contractors performing surface preparation and applicable work, and confirmation that PFAS contaminated soil is considered hazardous and cannot be disposed of as surplus soil.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE

PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

N40085

N40085-25-R-2523 - DESIGN-BUILD, P-1458 2ND RADIO BTTALION COMPLEX, PHASE 2, PARACHUTE AND SUPPLY

FACILITIES, MARINE CORPS BASE CAMP LEJEUNE, NORTH CAROLINA

See SF30 Block 14 continuation page(s).

NAVFAC MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511-3095

NAVFACSYSCOM MID-ATLANTIC

ROICC CAMP LEJEUNE

1107A BIRCH STREET

CAMP LEJEUNE NC 28547-2521

N40085-25-R-2523

1 5

05/22/2025

03/25/2025

N40085-25-R-2523

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

The purpose of this amendment is to provide the following:

1. Responses to Pre-Proposal Inquiries (PPIs):

Question # Reference

Question Government Response Page Section Paragraph

Part 6 - Chapter

K - Subsurfa ce Soil

Informati on

The Chapter K - Subsurface Soil Information was provided by ECS to the government through RQ construction, the current contractor on the site and MACC holder over this Task Order. Part 3 - Chapter 3, 3.1.2 states, " In accordance with FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, the Contractor is prohibited from hiring the Geotechnical Engineer who provided data, reports and any other services on behalf of the Government for this project.

Please confirm ECS an other firms who have prepared documents used in this RFP are not allowed to be used on this Task Order.

Confirmed, in accordance with Part 3 - Chapter 3, 3.1.2, the contractor is prohibited from hiring the Geotechnical Engineer who provided data, reports, and any other services on behalf of the Government for this project.

Part 6 -

B - Drawing s

Please confirm the Part 6 - Chapter B - Drawings are as-built conditions and can be utilized as such for existing conditions?

Note it appears current conditions do not match those on the drawings at the work in in progress and there are stockpiles, office trailers, etc within the LOD for the new project.

Drawings provided are not as-built drawings but are provided for informational purposes only and cannot be used for design.

Part 3 -

Part 3 - Chapter 3, 3.0 notes, "An on-going project will provide stormwater ponds. The KTR/ DoR is responsible for verifying adequate capacity with the work of this project. The KTR/ DoR shall modify stormwater permits.

If changes to the existing SCMs

1. Bid accord to scope and information provided in RFP.

Refer to PPI resposnes 1. 2.

Prime Contractor for on-going project is responsible for compliance with contract agreement between itself and the Government.

are required, the KTR/ DoR shall make the necessary improvements and secure applicable permits/ permit modifications prior to construction." 1 - Please provide all calculations for the existing stormwater design to confirm changes are not required. 2 - During the site visit it appeared the Wet Pods will need future maintenance as erosiion is already an issue with what is installed such as the Stormwater BMP installed to the south of the Supply Warehouse site. Please confirm these structure's will be restored to new conditions and in compliance with the Part 6 - Chapter B - Drawings prior to this contract's start.

01 45 00 1.6.1.1

01 45 00 - 1.6.1.1 notes the contractor must have a QC manger to manage the QC program and to serve as the SSHO. 01 35 26 - 1.7.1.1.1 notes the SSHO may not serve as the QC Manager nor the Superintendent. Please confirm the offeror shall employee full-time onsite a Superintendent, SSHO, and QC Manager dedicated to only this project.

QC Manager, SSHO, and Superintendent are separate roles. Prime Contractor is responsible for employing separate individuals as QC Manager, SSHO, and Superintendent.

Part 3 -

6 - C30

C30 -

SSPC QP 9

Certificatio n

Part 3 - Chapter 6 - C30 requires all contractors and subcontractors that perform surface preparation to be SSPC QP 9 certified prior to contract award. This is not a common certification to have as there are only four (4) contractors in the United States that hold this certification. Please consider removing this requirement.

SSPC QP9 Certification required for all contractors and subcontractors performing applicable work.

Part 4 - Section

C30 C30 1.2.1.1

Paragraph C30 1.2.1.1 requires all contractors and subcontractors to be SSPC QP 1 certified. Being that this is not included in Part 3 of the RFP, please confirm this certification is not required.

SSPC QP1 Certification required for all contractors and subcontractors performing applicable work.

01 57 19 Pg 6 -

1.2.15.6

Section 01 57 19 - 1.2.15.6 Surplus Soil says that contaminated soil that is hazardous material or hazardous waste is not included. Please confirm that PFAS contaminated

PFAS contaminated soil is considered hazardous and cannot be disposed as surplus soil. Comply with RFP requirements, Part 6, Chapter A, Environmental Standard soil is considered hazardous material and is not included.

Operating Procedure (ESOP) 5090.21, Contaminated Soil.

Part 6

B

CU Series of

Drawings

The civil utility drawings are marked up with electrical and telecom duct banks. The duct banks don't match up with what is shown on the TS and ES drawings. Which drawings take precedence?

Drawings provided are for informational purposes only.

Proceed in accordance with information provided in Civil Utility drawing mark-ups.

1.6.8 Quality Control (QC)

Specialists Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who may perform production related duties but must be allowed sufficient time to perform their assigned quality control duties. These individuals or specialized technical companies are directly employed by the Prime Contractor and cannot be employed by a supplier or subcontractor on this project. QC Specialists must be physically present at the work site with frequency as indicated in the Experience Matrix below, to participate in the QC Meetings, perform the three phases of control, including participation in Preparatory and Initial Phase meetings, and to perform and document Follow-up inspections as an extension of the QC Manager for each definable feature of work in their area of responsibility. QC Specialist must assist and be present for training events, and Critical System Acceptance inspections by the Government.

Qualification, experience, Area of Responsibility, and frequency of QC surveillance are provided in Matrix listed herein.

Question – Please consider that the QC Specialists could be employed by the specialty

Bid per RFP requirements. QC Specialists are individuals or specialized technical companies directly employed by the Prime Contractor and cannot be employed by a supplier or subcontractor on this project.

subcontractor performing that work. Also, the QC Matrix does not provide the frequency of the time for inspection during installation and testing on site, please update the matrix to include this information.

0012 CP