25R2523 Amendment 0004.pdf

PDF 381 KB Posted

Attached to
P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities
Solicitation number
N4008525R2523
Issued by

About this file

This document is Amendment 0004 to Solicitation N4008525R2523 for a Design-Build project at Marine Corps Base Camp Lejeune, North Carolina. The amendment provides responses to 178 Pre-Proposal Inquiries (PPIs) addressing various technical, architectural, and construction details for two primary facilities: a Parachute Maintenance Facility with Paraloft and a Supply Warehouse for the 2nd Radio Battalion.

Key clarifications include specifications for building materials, mechanical systems, electrical requirements, interior finishes, equipment installations, and design compliance with the Base Exterior Architectural Plan (BEAP). Notable items include confirming ground face concrete masonry unit (CMU) wall treatments, clarifying mechanical equipment placement, addressing floor coating systems, verifying parachute drying tower construction requirements, and resolving conflicts between room requirements and technical specifications. Some technical details remain pending resolution, indicating ongoing design refinement. The amendment extends the solicitation due date to 07 May 2025.

View the file

Other files

File Type Posted
N4008525R2523 Amendment 0018.pdf PDF
N4008525R2523 Amendment 0017.pdf PDF
N4008525R2523 Amendment 0016.pdf PDF
Attachment D - Price Schedule - Rev 2.pdf PDF
N4008525R2523 Amendment 0015.pdf PDF
N4008525R2523 Amendment 0014.pdf PDF
N4008525R2523 Amendment 0013.pdf PDF
N4008525R2523 Amendment 0012.pdf PDF
N4008525R2523 Amendment 0011.pdf PDF
N4008525R2523 Amendment 0010.pdf PDF
1397586_P1458_CPP1 SAT-TO-Drawings_PDF.pdf PDF
N4008525R2523 Amendment 0009.pdf PDF
N4008525R2523 Amendment 0008.pdf PDF
N4008525R2523 Amendment 0007.pdf PDF
N4008525R2523 Amendment 006.pdf PDF
Attachment D - Price Schedule - Rev 1.pdf PDF
N4008525R2523 Amendment 0005.pdf PDF
N4008525R2523 AMENDMENT 003.pdf PDF
P1458 Site Visit Log.pdf PDF
N4008525R2523 AMENDMENT 0002.pdf PDF
Attachment G - Site Visit Location.pdf PDF
N4008525R2523 AMENDMENT 0001.pdf PDF
Attachment F Site Visit Log.xlsx XLSX spreadsheet
Attachment C-Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
N4008525R2523 General Requirements.pdf PDF
Attachment E - PIEE Vendor Access Instructions.pdf PDF
Attachment D - Price Schedule.pdf PDF
Attachment A Work Order No. 1397586.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

N40085

N40085-25-R-2523 - DESIGN-BUILD, P-1458 2ND RADIO BTTALION COMPLEX, PHASE 2, PARACHUTE AND SUPPLY

FACILITIES, MARINE CORPS BASE CAMP LEJEUNE, NORTH CAROLINA

The purpose of this amendment is to provide responses to Pre-Proposal Inquiries (PPIs).

See SF30 Block 14 continuation page(s).

NAVFAC MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511-3095

NAVFACSYSCOM MID-ATLANTIC

ROICC CAMP LEJEUNE

1107A BIRCH STREET

CAMP LEJEUNE NC 28547-2521

N40085-25-R-2523

1 42

04/25/2025

03/25/2025

N40085-25-R-2523

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

The purpose of this amendment is to provide the following:

1. Responses to Pre-Proposal Inquiries (PPIs):

Question # Reference

Question Government Response Page Section Paragraph

Part 3, Chapter

3.0 Site

Analysis

This indicates the contractor is responsible for verifying adequate capacity of the stormwater control measures (SCMs) that are being constructed by RQ. If the SCMs are not adequate to meet state requirements, this section indicates the contractor is responsible for making changes to the SCMs. It ia not clear if the current stormwater permit has accounted for the Parachute and

Warehouse buildings. Please confirm the existing stormwater permit includes the Parachute and

Warehouse buildings in which case the requirement to verify the capacity of the current infrastructure would not be required?

The SCMs constructed as part of P1458 Phase I account for the Parachute and Warehouse

Buildings. The KTR/ DOR is responsible for submitting a stormwater redevelopment permit to document the impervious area for P1458

Phase II.

2 Site Survey

The current construction project develops the majority of the site infrastrucure. Will the design-build team, awarded this project, have access to current survey information and or as-built surveys in order to design the facilities under this contract?

The KTR is responsible for field verifying all utilities prior to design/ construction. The use of existing survey data, design data, and/or as-built data (if provided) does not relieve the

KTR/ DOR from verifying existing conditions prior to design/ construction and providing a current topographic survey.

3 Part 6 Chapter B

Drawings

The RFP includes site plans in part 6 by RQ design, please confirm these plans detail a separate project. Please also confirm references in these plans to a "future project" are refering to scope under this solicitation.

The site plans detail a separate project. The items denoted as

"future project" refers to the scope under this solicitation, but shall not be construed as the only requirement of this RFP.

4 Part 6 Chapter B

Drawings

The current construction project develops the majority of the site infrastrucure. Should bidders assume the work will be completed as shown in the provided part 6 civil plans prior to award of this solicitation?

Yes, assume the work will be completed prior to award of this solicitation.

General

Require ments

General

Requireme nts

On page 3 of the General

Requirements, it states that

Offerors are to submit their bid bond via "an electronic copy with the price proposal form and a hard copy of your bid bond must be submitted to the address listed in the title above, within three (3) days after the due date and time for receipt of proposals."

However, page 7 does not mention the mailed bid bond under Bid Guarantee. Please confirm that Offerors are expected to mail a hard copy of the bid bond.

Offeror only required to submit electronic copy of bid bond.

1 Part 3 2.0 Project

Objectives

In Part 3, 2.0 Project Objectives, Page 1, it states, “Requirements stated in this RFP are minimums.

Innovative, creative, and effective solutions which meet or exceed these requirements, are encouraged.” Including this reference and all other “or exceed” instances in the RFP, please confirm that the technical evaluation criteria does not include “exceeding RFP requirements” as betterments, strengths or additional considerations to offers who provide design features that are in excess of the RFP as a basis of award.

Confirmed

01 14 00 1.2.1.2.1 &

1.3.1.1

Specification section 01 14 00

1.2.1.2.1 & 1.3.1.1 states that the workforce must be performed by

US citizens. This is not a typical requirement for Camp Lejeune and would greatly limit subcontractors' workforce, likely resulting in substantially higher costs to the Government. Please clarify that the workforce is not limited to US citizens only.

PENDING

01 45 00 1.6.1.4 Specification section 01 45 00 states to provide a separate full-time QC manager at the Parachute

Maintenance with Paraloft

Facility and the Supply

Warehouse. Due to the close proximity of these buildings, typically only one (1) QC

Manager would be needed to cover both buildings. Please confirm that a dedicated QC

Manager is required at each building for a total of two (2) QC

Managers for this project.

Yes, one full time QC Manager is acceptable.

01 45 00 1.6.5 Specification section 01 45 00

1.6.5 states to provide a full-time assistant to the QC Manager.

Please clarify if the assistant to the QC Manager may perform other roles or must be dedicated to assisting the QC Manager.

01 45 00 1.6.8 Specification section 01 45 00

1.6.8 provides a table of QC

Specialists for Civil, Mechanical, Electrical, Telecommunications, Structural, Architectural, Submittals and Concrete, Pavement and Soils. However, the Frequency requirement for each of these specialists is blank.

(A) Please confirm all of these

QC Specialists are required as outlined in the table.

(B) If required, please provide the

Frequency requirement for each

QC Specialist.

(A). QC Specialists are required as outlined in the table. (B).

Frequency of QC surveillance and inspection will be once a week during installation and full-time during testing during installation and including final inspection.

Part 3 Chapter 5

Room

Requireme nts (Male

& Female

Heads)

The Room Requirements for the

Male and Female Heads in the

Parachute and Supply Buildings call for a Prefabricated 14 Gauge

Stainless Steel Shower Unit.

However, also within the same

Room Requirements, it states to provide a solid surface shower enclosure per C301090. Please confirm that all showers require the solid surface shower enclosure.

Showers require solid surface shower enclosure.

Part 3 Chapter 6

C3010

Section C3010 Wall Finishes states to provide ½” solid surface wall panels at shower walls. The typical industry standard for solid surface it to use ¼” thick wall panels at shower/wet wall

Comply with ESR C3010 -

Wall Finishes.

enclosures. At shower locations, using ¼” thick material will save a substantial amount of cost both in raw material price and labor to install the product. Would the

Government permit the use of ¼” thick solid surface wall panels to be used at shower locations?

Part 3 Chapter 5

Room

Requireme nts (Supply

Warehouse

- Shipping

Receiving

& HQ CO

Warehouse

In the Supply Warehouse Room

Requirements for the Shipping

Receiving and HQ CO

Warehouse, it states to provide

Translucent Clearstory Windows per B202090. However, in

Chapter 6 B202090 Other

Exterior Windows, it states "Not

Used." Please clarify if the

Translucent Clearstory Windows are required in the Supply

Warehouse.

Provide Translucent Clearstory

Windows

Part 3 3.1.3.1

New Site

Work

Chapter 3.1.3.1 New Site Work mentions that a cast-in-place concrete fork-lift ramp is to be provided on the Supply

Warehouse site. There is no other mention of this fork-lift ramp in the RFP. Please confirm the fork-lift ramp is required on the

Supply Warehouse site.

Confirmed.

Part 3 Chapter 6

C3040

C3040 Interior Coatings and

Special Finishes states to provide epoxy coating for vertical concrete/masonry surfaces and that all finish coatings must be as indicated in Part 3 Chapter 5

Room Requirements. The Room

Requirements do not specify epoxy coated paint on the concrete/masonry walls. Please clarify if epoxy coated paint is required for interior concrete/masonry walls.

CMU walls must receive block filler as modified, latex primer and two coats of Water Based

Catalyzed Epoxy in a satin finish.

Part 3 Chapter 6

C3040

C3040 Interior Coatings and

Special Finishes states to provide high performance, architectural coatings on walls in all areas without another specific wall finish. Please clarify that gypsum board furred walls and open to structure ceiling areas are required to receive high performance architectural paint coating.

Confirmed.

Part 3 Chapter 6

D102002

D102002 Overhead Cranes states the Construction Contractor must hire a 3rd party to perform Crane certification and that OSHA recognized the Navy Crane

Center as a third party certifier. Is the Government able to provide the cost for the Navy Crane

Center to perform the third party certification?

No. There are contractors in the area who can certify and load test per NAVFAC P-307

1 Part 3, Chapter

6 / ESR

F10

F101001 F101001 Metal Building Systems

(Pre-Engineered) - If Pre-

Engineered Metal Building

Systems are allowed, does this include the use of alternative exterior finishes such as metal panel and/or a combination of metal panel/CMU/Brick?

Refer to Part 3 Chapter 2, para.2.4 and Part 6,Chapter A, Camp Lejeune Base Exerior

Architectural Plan (BEAP)

Parachut e

Maintena nce with

Paraloft

Part 3, 4.0

Space

Tabulatio n

Grossing

Factor

The 4.0 Space Tabulation for the

Parachute Maintenance with

Paraloft includes a Grossing

Factor of 1.31, or approximately

1,596 SF. This Grossing Factor

SF must accommodate the following SF to meet functional, code, UFC, and Camp Lejeune requirements:

- Hot Mechanical Room, approx.

400 SF

- Cold Mechanical Room, approx.

1,100 SF

- Fire Pump Room, approx. 240

SF

- Telecom Room, approx. 80 SF

- Electrical Room, approx. 120 SF

- Circulation per Affinity

Diagram, approx. 120 SF

- TOTAL approx. 2,060 SF

Additionally, all interior and exterior walls and partitions must be accounted for in this Grossing

Factor. These required areas cannot be accounted for by the assigned Grossing Factor. In order to provide a functional, compliant facility, will the overall building gross square footage be increased or will the required square footage overage be taken from other programmed spaces?

The overall building gross square footage will not be increased.

Supply

Warehou se

Part 3, 4.0

Space

Tabulatio n;

PPI #11

Response

PPI #14

Response

Grossing

Factor

The 4.0 Space Tabulation for the

Supply Warehouse includes a grossing factor of 1.11, or approximately 1,178 SF. The

Grossing Factor SF must accommodate the following SF to meet functional, code, UFC, and

Camp Lejeune requirements:

- Hot Mechanical Room, approx.

400 SF

- Cold Mechanical Room, approx.

1,100 SF

- Fire Pump Room, approx. 240

SF

- Telecom Room (2), approx. 160

SF total

- Electrical Room, approx. 120 SF

- TOTAL approx. 2,020 SF

Additionally, all interior and exterior walls and partitions must be accounted for in this Grossing

Factor. These required areas cannot be accounted for by the assigned Grossing Factor. In order to provide a functional, compliant facility, will the overall building gross square footage be increased or will the required square footage overage be taken from other programmed spaces?

See response to PPI 19.

Page 1 Part 3, Chapter

6 / ESR

B20

B201001 Please confirm if an insulated metal panel system with an interior liner panel would be an acceptable Exterior Closure at the

Parachute Drying Tower in lieu of brick veneer and acrylic coated/filled CMU 70' tall walls.

See response to PPI 18.

Page 3 Part 3, Chapter

6 / ESR

B20

B201011 B201001 Sun Control Devices

(Exterior) states, "Provide fixed horizontal type. Detail sun control devices to integrate with the architectural character of wall system." However per 3.2 Site

Photos, Elevation of Adjacent

Facilities, there are no Sun

Control Devices on the adjacent buildings. Additionally, horizontal Sun Control Devices do not match the historic character seen in Georgian and

Colonial Revival Architecture.

Please confirm the requirement for Sun Control Devices.

Sun Control Devices, if provided, must be compatible with Georgian and Colonial

Revival historic character seen.

Page 6 Part 3, Chapter

6 / ESR

G20

G2030 G2030 Pedestrian Paving states, "Provide, as indicated in BEAP

3.2.8 PLAZAS AND

COURTYARDS - EXTERIOR

USE AREAS, entrance plazas and pedestrian spaces to create outdoor meeting spaces and reinforce the arrival sequence from parking lot to building entrance(s)." With the extensive surrounding heavy-duty concrete pavement supporting the building functions at the Supply

Warehouse and Paraloft Building for purposes of bidding, please confirm and identify the requirements for entrance plazas at these buildings.

For the arrival sequence leading to the paraloft building entrance adjacent to the admin space refer to BEAP 3.2.8 PLAZAS

AND COURTYARDS -

EXTERIOR USE AREAS.

-- Part 6, Chapter

A, Executiv e Order

14057 -

Catalyzin g Clean

Energy

Industrie s and

Jobs

Through

Federal

Sustaina bility

-- Please clarify the intent of including Part 6 Chapter A

"Executive Order 14057 -

Catalyzing Clean Energy

Industries and Jobs Through

Federal Sustainability". This

Document appears to be applicable to buildings more than

25,000 SF. The NAVFAC HIGH

PERFORMANCE AND

SUSTAINABLE BUILDING

CHECKLIST provided in the

RFP indicates Renewable Energy is not LCCE.

Executive Order 14057, which aimed to catalyze clean energy industries and jobs through federal sustainability, was revoked by Section 2 of

EO 14148 signed by President

Trump on January 20, 2025.

Entry

Corridor

Part 3, 5.0

Room

Require ments, Combine d

Electroni cs/

Comm/

Vehicle

Maintena nce &

Boat Ops

Facility

-- Entry Corridor, D304007 HVAC indicates "Air conditioned space."

Per ASHRAE 90.1, Section

5.4.3.4 Vestibules: "Building

entrances that separate condition space from the exterior shall be protected with an enclosed vestibule..."

a) Please confirm the floor area footprint needed to comply with the aforementioned ASHRAE

90.1 code criteria for vestibules at

Corridors D1 and D2 can be taken from the corridors.

b) Please provide room requirements for the vestibules.

Square footage for code required enclosed vestibules is to be subtracted from ciruclation space (Corridors).

Room requirements for vestibules shall match those of the corridors with C102002 glazed interior doors and

C102007 interior door hardware

Part 3 Chapter

(Parachute

Maintenanc e with

Paraloft

Facility)

Room

Requireme nts

Parachute Inspection and Packing

Area, Secure Parachute Storage

Room, Parachute Drying Tower, Parachute Repair Room, Paraloft

Pack-out Staging Area, Janitorial

Room, Helicopter Rope

Suspension Techniques (HRST), Mechanical Room, Telecom

Room, Electrical Room, Fire

Pump Room; All these room identify C101001 Fixed Partitions ground faced masonry or concrete walls.

C101001 FIXED PARTITIONS

has no reference to ground faced masonry.

B201001 EXTERIOR CLOSURE

allows for "Provide precast concrete, ground face or standard concrete masonry units as the back-up construction for the

Exterior Closure."

(a) Please confirm Standard

Concrete Masonry Block is intended to be utilized.

(b) Please confirm, per C3010, the interior face will be painted accordingly.

Provide precast concrete, ground face or standard concrete masonry units as the back-up construction. Paint all exposed surfaces in accordance with Master Painter Institute

(MPI) standards for the interior architectural surface being finished. CMU walls must receive block filler as modified, latex primer and two coats of

Water Based Catalyzed Epoxy in a satin finish.

Part 3 Chapter

Supply

Warehouse

Room

Requireme nts

HQ CO Warehouse, Receiving

Cage, PN Effects Cage, Security

Cage Mechanical Room, Electrical Room, Telecom Room , Mechanical Room, Telecom

Room, Electrical Room, Fire

Pump Room - All of these room identify C101001 Fixed Partitions

Ground faced masonry or concrete walls.

C101001 FIXED PARTITIONS

has no reference to ground faced masonry.

B201001 EXTERIOR CLOSURE

allows for "Provide precast concrete, ground face or standard concrete masonry units as the back-up construction for the

Exterior Closure."

(a) Please confirm Standard

Refer to PPI response 26.

Concrete Masonry Block is intended to be utilized.

(b) Please confirm, per C3010, the interior face will be painted accordingly

6 Part 3, Chapter

6 / ESR

E10

E1040 E1040 Government Furnished

Equipment - Please identify any

Government furnished equipment to be accommodated.

Government furnished equipment is identified in ESR

E10.

1 B201001

EXTERIO

R

CLOSURE

"Provide precast concrete veneer water table WC505 - precast concrete keystone, precast concrete sill, split-face water table to match existing adjacent structures. On a case-by-case basis, ARB accepts freeze band using pre-cast or

GFRC/FRP material." Per the

Camp Lejeune BEAP "Wallace

Creek indicates the Base

Foundation to be'"white split face, white mortar.' Please confirm that the water table is to be white split face concrete block per the

BEAP.

Refer to Part 3, 3.2 Site Photos.

Water table is to match water table of adjacent facility.

1920 Part 6

Attachm ents, Chapter

E Camp

Lejeune

Mechani cal

Design

Guidance

General The Camp Lejeune Mechanical

Design Guidance, dated 10 Aug

2022, General item #4 includes a reference to providing separate hot and cold mechanical rooms to separate fuel fired equipment from AHU and similar cool surface equipment. RFP Part 3, Chapter 4.0 Space Tabulation for both Parachute Maintenance with

Paraloft and Supply Warehouse facilities do not include reference to providing multiple mechanical spaces. Space required for mechanical to be located in two separate rooms will require 1,200

SF more per building.

Please confirm the following:

a) Separate hot and cold mechanical rooms are required for each facility to comply with the RFP included Camp Lejeune

Mechanical Design Guidance dated 10 Aug. 2022, including all associated design requirements.

b) Will additional floor area required to accommodate

Comply with Camp Lejeune

Mechanical Design Guidance, dated 10 Aug 2022.Room

Requirements are the same for both hot and cold mechanical rooms. Square footage for systems is included in the facility grossing factor.The overall building gross square footage will not be increased.

providing separate hot and cold mechanical rooms be added to increase to the overall building gross square footage, or will it be taken out of another program space?

1897 Part 6, Chapter

C

Affinity

Diagrams

The Affinity Diagram for the

Supply Warehouse indicates an exterior Building Mechanical

Yard placed directly adjacent to what is interpreted as the main building entry (Admin area).

Please confirm if this design strategy is intentional, or should the interior room layouts be configured to locate the building entry on a facade away from the

Mechanical Yard?

Affinity diagrams are notional ment to convey relationships between programmed space.

The final layout and design is the responsibility of AE2.

633 Part 3, Chapter

ESR B20 B201001 Exterior Enclosure states, "Provide Exterior Closure system to match the exterior of surrounding buildings in the

Complex. The architectural style is described in the Base Exterior

Architectural Plan (BEAP). The

Installation Wide Design

Guidelines establishes the massing, character, and material for the Common District at

Wallace Creek. These guidelines also require other building design consideration such as “Entrances must be formal, clearly identifiable and located toward the most common approach, preferably facing the public way or open space, security requirements, and anti-terrorism standards”. The Part 6, Ch C

Affinity Diagrams provided for

Supply Warehouse and the

Parachute Maintenance with

Paraloft facilities indicate, what are interpreted to be, primary building entrances location far from center on the building facade, which does not meet the formal symmetry typical of the prescribed BEAP Georgian and

Colonial Revival styles.

Please confirm:

a) This design deviation is intentional or;

Refer to PPI response no. 31.

b) The building layout requires adjustment to better centralize the main building entries in compliance with design guidelines outlined in the BEAP.

636 Part 3, Chapter

B2020

EXTERIO

R

WINDOW

S

B2020 EXTERIOR WINDOWS

states "Exterior windows must be provided in areas such as stairwells & mechanical / electrical rooms for architectural symmetry. Spandrel glass is acceptable." Spandrel glass typically has to be concealed from interior view by framing, is the intent to have translucent glazing where light would still be let into the space?

No, the function of mechanical and electrical rooms is more important than introducing exterior light into these types of spaces.

553 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Admin Spaces has conflicting room requirements. C101005 states

"Fixed interior side lite to view

Entry Vestibule and

Packing/Staging Room." While

C102001 states "Standard interior door may include vision side lite or an 8” x 32” glazing in door." Please clarify if a 2'x7' sidelite or independent window is required at the interior entry door from the vestibule directly into the admin space.

Provide either but not both a side light or a lite in the door.

572 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Male Head calls for 3 lavatory sinks, in excess of the minimum plumbing fixtures calculated for this building footprint. Please confirm that 3 lavatory sinks is a user requirement in the Male Head at the Parachute Maintence and

Paraloft Facility or whether code minimum lavatory count is acceptable.

Three sinks is a user request.

566 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Parachute Repair

Room calls for an exterior window in B2020001. The affinity diagram while locating

Refer to PPI resposne 31.

Windows are not defined in the affinity diagrams, only adjacencies and door ways.

this space at an exterior wall does not indicate direct access from the exterior is required. Please confirm if this room is required to be located on an exterior wall with a window.

575 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Female Head states "Occupancy: 1 female."

C103001 states "Floor mounted overhead braced HDPE Toilet

Partitions screens if more than one fixture is provided."

The Space Tabulation allocated to this Female Head has insufficient square footage to provide sink, watercloset stall, and shower area as independent spaces. Please confirm if Female Head can instead be treated as a single occupancy restroom with no water closet stall.

Female Head is single occupat restroom without toilet partitions.

575 Part 3, Chapter

Room

Requireme nts

The Supply Warehouse Female

Head C103001 states "Floor mounted overhead braced HDPE

Toilet Partitions screens if more than one fixture is provided." The

Space Tabulation allocated to this

Female Head has insufficient square footage to provide sink, watercloset stall, and shower area as independent spaces. Please confirm if Female Head can instead be treated as a single occupancy restroom with no water closet stall.

See PPI response 38.

566 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Training Area

C101001 states "Interior fixed partitions include metal studs, sheetrock, masonry, and concrete walls. " C301003 states

"Assembly includes gypsum wallboard applied directly to an interior wall surface. Furring strips or channels are included in this assembly. Assembly includes taping, sanding, finishing, and sheetrock accessories. Provide impact resistant gypsum bd."

Please clarify whether finish face of wall is required to be gypsum board or if masonry partition is acceptable.

Finished face of wall is gypsum board.

563 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Parachute Drying

Tower has H1060 "OSHA approved ladder to access platform grate." H1060 is not located in the ESRs please confirm reference.

Refer to C201090

635 Part 3, Chapter

B201012

SCREEN

WALL

B201012 SCREEN WALL

"Provide screen walls to screen mechanical units, electrical substations, loading docks, and trash receptacles. Provide screen walls compatible with the exterior architecture of the building and in alignment with the BEAP Design rooftop mechanical screens to minimize roofing penetrations."

Please confirm that because the buildings are within a fenced perimeter, screening is not required for mechanical yards.

Confirmed, screen walls are required. Also refer to Part 3,

3.2 Photo, Dumpster enclosure

example.

6 Part 1

General

Require ments

Factor 1 –

Technical

Solution

States "Narrative shall not exceed four (4) pages. A minimum of three conceptual drawings are required: Conceptual drawings of site plan, building floor plans and building evaluation." Please confirm if this should be

"Narrative shall not exceed four

(4) pages. A minimum of three conceptual drawings are required:

Conceptual drawings of site plan, building floor plans and building elevation."

Yes, It should be "elevation" not "evaluation"

553 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility Admin and

Training area both have C103090

Other Interior Specialties. Part 3

Chapter 6 does not have any

C103090 Other Interior

Specialties description, please provide further clarification on these material requirements.

C103090 Wall-mounted cranial helmet rack. Other Interior

Specialties. Add Manuf. Zoro.

Model: G915195386 or equilivant.

563 Part 3, Chapter

Room

Requireme nts

The Parachute Maintenance and

Paraloft Facility E109090 horizontal lift bar with attachment hooks (4) power operated to raise/lower (11) parachutes per lift bar for drying. This quantity is roughly half the area of the

Parachute Drying Tower.

(a) Is the platform intended to cover the whole Parachute Drying

Tower wall to wall, or is the

(a) Coordinate platform size with OSHA ladder, lighting, mechanical ductwork and crane. (b) Structure and infrastructure should accommodate hanging 37 concurrent chutes. Expansion of lifts is not anticipated.

platform intended to be sized to match the quantity of lifts provided?

(b) Should structure and infrastructure accomodate any future drying lifts inside the space?

653 Part 3

Chapter

D102002

OVERHE

AD

CRANES

Crane is noted to facilitate loading and unloading materials and be within 4' of the wall.

Please confirm the monorail 1/2 ton crane shall be located beneath the parachute lifts around the perimeter of the Paraloft Drying

Room.

Monorail to be located above parachute lifts.

613 Part 3, Chapter

Room

Requireme nts

Supply Warehouse Receiving

Cage E101005 states "Pair of double 8’ wide swing gates centered and located for forklift access from inside of Warehouse.

Cylinder lock to be pre-set lock box into doors. Provide egress capability from inside of cage thru locked door." Please confirm that this egress capability is intended to go through the cage gate and not the secondary door providing direct egress from the cage.

AE2 to comply with IBC and

NFPA egress requirements.

615 Part 3, Chapter

Room

Requireme nts

Supply Warehouse Security Cage

E101005 "Pair of double 8’ wide swing gates centered and located for forklift access from inside of

Warehouse. Cylinder lock to be pre-set lock box into doors.

Provide egress capability from inside of cage thru locked door. "

Please confirm that this egress capability is intended to through the cage gate and not secondary door providing direct egress from the cage.

Refer to PPI response 47.

616 Part 3, Chapter

Room

Requireme nts

Supply Warehouse PN Cage

E101005 states "Pair of double 8’ wide swing gates centered and located for forklift access from inside of Warehouse. Cylinder lock to be pre-set lock box into doors. Provide egress capability from inside of cage thru locked door." Please confirm that this egress capability is intended to go through the cage gate and not the

Refer to PPI response 47.

secondary door providing direct egress from the cage.

593 Part 3, Chapter

Room

Requireme nts

Supply Warehouse Break Room states that plumbed coffee makers can not be supplied with FFE funds. Please confirm that neither plumbing nor plumbed coffee makers are required.

Plumbing is required. Coffee makers are GFGI.

607 Part 3, Chapter

Room

Requireme nts

Supply Warehouse Shipping and

Receiving requires 2 exterior man doors. However, the affinity diagram only shows 1 exterior swing door connector. Please confirm that 2 exterior doors are not required in the Shipping and

Receiving Room.

Provide 1 exterior man door.

116 SECTIO

N 01 33

10.05 20

2.2.2

Required

Design

Submittals

This required design submittal indicates 35% and 65% Design

Development submissions are required for the non-critical path design packages. Due to the simplicity and scale of this project, and the short CCL, would the Governemnt consider reducing this to 1 typical 65%

Design Development

Submission?

PENDING

692 E102001 E102001 states "If equipment is

6-feet high or taller, equipment must be securely anchored and therefore becomes fixed furnishings / MILCON." The

Room requirements have several rooms where storage shelving is identified. Please confirm that all these shelving units shall be purchased and installed under the construction contract.

Confirmed.

539 PART 3

CHAPT

ER 3

Page 3 Per PART 3 - CHAPTER 3 -

Page 3 “The operational hardstand on the south and west sides of the facility (within the fence) is to be heavy-duty concrete pavement.” Please confirm that what is being described is the vehicle circulation and that no additional hardstand is required from the paraloft facility to the vehicular circulation within the space.

Confirmed.

540 PART 3

CHAPT

ER 3

Page 3 Per PART 3 - CHAPTER 3 -

Page 4 “Planning for Paraloft facility must include a future minimum 3,370 sf future addition to the parachute inspection and packing area to accommodate a third row of tables within the area.” Please confirm that the stormwater design does not need to account for this future extension to be impervious area.

Stormwater design do need to account for future extension to be impervious area. Expansion date of Paraloft is unknown.

Room

Require ments for

Rooms with exterior windows

Room

Require ments

B2020001 B2020001 Exterior Windows makes no mention of window sills and ESR C10 does not indicate a window sill finish. Please provide the preferred window sill finish.

Window sills are to be concrete or stone

Room

Require ments with

Epoxy

Room

Require ments

C103008 C103008 - In each of these room requirements, it states to provide a five-coat flooring system consisting of primer, epoxy mortar, grout coat, and two urethane topcoats. Would a 3-part epoxy that has a 5 layer system, consisting of primer + flake undercoat + pigmented flakes + grout coat + top coat, be a sufficient solution?

PENDING

Room

Require ments

Heads and

Break

Room, Mothers

Room

Room

Require ments

C103008 C103008 - In each of these room requirements, it states to provide a solid surface countertop with backsplash. No height was provided for the backsplash.

Please provide the desired height for both the backsplash and side splashes.

Backsplash to be 4"

645 Part 3

ESR

C103014

C103014 C103014 states, "Provide recessed entrance floor mat system at main building entrances. Provide installed carpet tile mats at other building entrances. Provide entrance mats with recycled tire surface treads."

But there are no room requirements for vestibules, and the room requirements for rooms with exterior access require loose lay entrance mat at exterior door.

Please confirm if a recessed entrance floor mat system is required and please specify location.

Provide recessed entrance floor mat system at main building entrances.

650 Part 3

ESR C30

C3010 C3010 states, "Provide corner guards at all exterior corners.

Apply PETG corner guards at offices, corridors, and work areas.

Provide stainless steel corner guards in work bays, warehouse, and other areas where wheel traffic will be -present." Please provide the preferred height of the corner guards.

Corner guards to be full height.

671 Part 3 D304006 Mechanical Supply warehouse contains approximately 2,400 SF area and the Paraloft contains approximately 4,000 SF area prescribed to be conditioned by chilled water plants. Based on the small square footage, a chilled water plant is not practical or life cycle cost effective. Please confirm alternate systems can be utilized in lieu of chilled water plant if found to be LCCE.

PENDING

669 Part 3 D303002 Please provide the sensible heat rejection from any IT equipment located within the Telecomm

Rooms. If this is not available, please provide guidance as to how to size the split systems serving the Telecomm Rooms.

AE2 is responsible to provide system design.

669 Part 3 D303002 Per UFC 3-580-01 2-3.1.3.4

Telecom Rooms loads greater than one ton require two identical units sized for 50-60% of the load each. Please clarify if multiple split systems are required or if a single dedicated split is to be provided per D303002

AE2 is responsible to provide system design.

670 Part 3 D304001 Please clarify where aluminum linear slot diffusers are required.

PENDING

171 Part 2 01 33 29 The RFP sustainability checklist notes compliance with ASHRAE

90.1-2013. UFC 1-200-02

indicates that projects designed after 4/7/23 should be designed for compliance with ASHRAE

90.1-2019. Please confirm which standard applies to this project.

Comply with ASHRAE 90.1-

2019.

659 Part 3 D203004 RFP indicates for sump pump in elevator sump. Please confirm elevator and sump pump is not applicable to project, because

Elevator sump pumps are not applicable.

there is no elevator in these buildings.

669 Part 3 D303002 RFP indicates to provide a dedicated air-cooled direct expansion (DX) ductless split system heat pump unit for the elevator machine room space.

Please confirm elevator machine room and split system is not applicable to project, because there is no elevator in these buildings.

Requirements for elevator machine rooms are not applicabe.

672 Part 3 D304008 RFP indicates to provide energy recovery sections on Air

Handling Units. Please clarify if energy recovery section can be omitted if not required by

ASHRAE 90.1

PENDING

742 G40 G4010 G4010 Electrical Distribution indicates that connection to the existing power system is overhead. However, Phase I included a new underground duct bank. Please confirm that point of connection will be to the nearest above ground 15KV sectionalizing cabinet.

PENDING

686 D50 D501002 Section calls for a main service switchboard to be used as service equipment. A switchboard is typically required when the service is 1200 amps or larger.

Can a main distribution panel be used where the service for the building is 1000 amps or less?

PENDING

684 D50 System description calls for 20 percent spare capacity at all levers of power distribution system, including any "stand-by power systems." No requirement for an emergency generator is indicated in the RFP. Please confirm an emergency generator is not required for the fire pump?

Confirmed

687 D50 D5020 Section indicates that no surface mounted conduit is permitted in interior spaces. Please confirm surface mounted conduit is permitted in unfinished interior spaces.

Confirmed

743 G40 G401005 (a) Please confirm that concrete poles are not required.

(b) Existing distribution system is below grade per Part 6 attachments. Please confirm new routing will also be underground distribution to the buildings' service.

PENDING

743 G40 G401009 Section indicates that no sub-metering within building electrical panels; however, each building shall be metered. It is also states to provide a separate advanced kilowatt demand meter for each pad mounted transformer. Please confirm that only metering for each building will be advanced kilowatt demand meter at each pad mounted transformer.

PENDING

745 G403001 1 Telecommunications Point of

Connection Confirmation

G403001 states the point of connection will be the nearest point of presence (demarcation).

Part 6 Telecommunications Site

Plans TS101 shows the Phase I point of connection as (E) MH

WC-N-1 and a nearby MH02 and

MH03.

Question: please confirm MH02 and MH03 are the points of connection.

PENDING

745 G403001 4 Quantity of 3-Cell Mesh

Innerducts

G403001 states to install 3-cell mesh innerducts and provide more than one 3-cell mesh innerduct where required.

Question: please clarify the quantity of 3-cell innerducts required for bidding purposes.

PENDING

746 G403002 1 CATV Conduit Removal

Confirmation

G403002 states to provide one (1) empty 4-inch conduit with pull strings between the exterior connection point and equipment room for CATV.

Question: please verify if this dedicated empty conduit is needed or it could be put into one of spare (4) 4-inch conduits.

688 D503005 1 & 2 D50 ESS System Infrastructure

D503005 states to provide infrastructure at all exterior man doors.

Question: please clarify which system infrastructure is to be provided: access control, intrusion detection system, and/or

CCTV

Infrastructure at man doors is for intrusion detection system and/or CCTV

746 G403007 G40 ESS System Infrastructure

G403007 states to provide exterior ESS system infrastructure. ESS is a broad term that could cover access control for doors and gates, intrusion detection systems including fence monitoring, CCTV cameras, etc.

Question: please clarify what exterior ESS system infrastructure is to be provided.

Refer to PPI response 78.

688 D503001 All Secured Networks / SIPR

The RFP does not mention if secured networks / SIPR is a project requirement or not.

Question: please confirm secured networks / SIPR is not a project requirement.

Confirmed

Part 3 -

5.0 -

Parachut e -

Training

AV

Estimate d Cost

Summar y

N/A Parachute Maint Training Room

AV:

The room data sheet (RDS) for the Parachute Maintenance

Training Room states to provide one (1) flat screen wall monitor

60"-65" and (16)-(25) ceiling speakers.

The AV cost estimate uses one

(1) 80-90" display and (9) ceiling speakers for the cost estimate.

Question: Please confirm the

Use sizes and quantities referenced in the AV cost estimate.

display size and the quantity of ceiling speakers estimates for the

Parachute Maintenance Training

Room.

1442 MCB 27

10 00

Telecommunications QC

Specialist Confirmation

MCB 27 10 00 section 1.6.2.1

Telecommunications Contractor states the Telecommunications

System QC Specialist is required on site, full time.

Questions:

1 - Please confirm if this

Telecomm Systems QC specialist is required to be onsite full time or only when Telecommunication work is being performed?

2 - Please confirm if this specialists can have other duties beside QC.

PENDING

2.3.7

D306001

D503006

Cybersecurity UMCS/EMCS:

The RFP appears to utilizes the terms Utility Management

Control System (UMCS) and

Energy Management Control

System (EMCS) interchangeably.

The RFP states the UMCS current

ATO impact rating is L-M-M.

The RFP states the EMCS current

ATO impact rating is both L-M-

M and L-L-L.

Questions:

1. Please confirm the UMCS and

EMCS are the same systems and can be covered by a single 25 05

11 spec section.

2. Please confirm the ATO impact rating that should be used for

UMCS/EMCS or EMCS if separate than UMCS.

1. The terms UMCS and EMCS are used synonymously. The

UMCS/EMCS can be covered by one 25 05 11 specification, if the FRCS addressed by that specifically address the needs of the facility's Heating, Ventilation, and Air

Conditioning (HVAC) and connected Electrical Systems

(ES). Note: The DPW department will perform the integration of the new

EMCS/UMCS systems.

2. The UMCS/EMCS ATO

Impact Rating is L-M-M.

533 2.3.7

Cybersec urity

N/A Cybersecurity ATO & RMF

Confirmation

The cybersecurity scope listed in the RFP indicates that an existing

Authority to Operate (ATO) is available for each facility-related control system applicable to this project. Please confirm

Cybersecurity ATO & RMF

Confirmation (RMF) and spec

Specification 25 08 11.00 20

Preamble Notes, indicate “Only use this specification on control systems which are obtaining a new ATO.”

This specification is not required because there are existing ATOs for the systems indicated in the RFP.

section 25 08 11.00 20 Risk

Management Framework for

Facility-Related Control Systems are not required for this project.

Part 3

Chapter

Floor Box Locations

Most room data sheets for telecom state to follow base modification spec 27 10 00.

Question: for bidding purposes, please confirm which rooms require floor boxes and please provide estimated quantity of floor boxes.

Provide floor boxes within the

Paraloft Training Room. One box per four occupants

Part 3

Chapter

D4020 In accordance with UFC 3-600-

01, the DFPE must determine if a

Reliable Power Source is available to the Installation or

Facility in the planning stages of the project in order to ensure that the cost and space associated with secondary power is considered and included in the project. Please confirm the site power is considered reliable, and secondary power is not required.

Emergency generators are not required.

Part 3

Chapter

D4020 In accordance with UFC 3-600-

01, warehouse sprinkler protection, at a minimum, must be based on Class IV, nonencapsulated commodities, as defined by NFPA 13, unless a more severe class of storage is anticipated, and must be based on the maximum potential height of storage. Please confirm if a more severe class of storage than Class

IV, nonencapsulated commodities

(including Group A Plastics) will be stored within any portions of the facilities, and confirm maximum potential height of the this storage.

PENDING

Part 3

Chapter

D4040 In accordance with the RFP, the fire pump must be located within the building enclosure that it is protecting. NFPA 20 does not require Fire Pumps to be housed in the building they are serving and allows for Fire Pumps to be housed in a neighboring enclosure. Please confirm if the

Government would accept a

NFPA 20 code compliant solution.

650 Part 3, Ch-6, C30

C3010

Wall

Finishes

Wall tile type is defined as

"through body" in the ESR and in

Part 4/ C301004 1.1.2 as "through color". These definitions have different cost grades, "through body" being a premium. Clarify which porcelain tile composition is required.

Porcelain tile to have same color and design throughout the entire thickness of the tile.

Drawing s

Part 6, Ch-B

Are there functional furniture layout plans available for this project?

AE2 to provide furniture layout plans

Training

Area

Part 3, Ch-5

D502001 Floor mounted receptacles have been requested for dedicated tables however in Part 6, Chapter

G FF&E estimated cost listing, there are no tables noted, only 48 chairs. Clarify how many tables will need access to a floor mounted receptacles. Will there be a requirement for the tables to have integrated power and data?

There are no tables within the

Paraloft Training Area.

Secure parachut e storage room

Part 3, ch-5

E102001 There is a high density rolling storage requirement for the secure parachute room. Is there a performative or prescriptive specification for this system?

Manufactured storage system to be mounted on track-guided carriages to form a compact storage system. System permits access to any single aisle by manually moving units until aisle is opened. Carriage/rail system to provide uniform carriage movement along the total length of travel.

Carriage system consists of a formed steel frame with hardened steel wheel riding on steel rails recessed mounted to the floor for smooth operation and self-centering of mobile storage units during travel without end play or binding.

Provide control handles on accessible ends, centered on the end panel of each unit permitting units to be moved to create a single aisle opening

8 01 57 19 1.3 A "dewatering permit" is listed among the required

Preconstruction Submittals;

however, no specific information has been provided regarding the requirements or process for obtaining this permit. Please provide additional details or guidance on what is needed to secure this permit.

PENDING

21 01 57 19 3.3.1 The specification section contains several bracketed placeholders indicating missing or incomplete information, including the

Nationwide Permit Number and multiple points of contact. Please provide the missing details to complete this section.

PENDING

Existing

Condition /

Current

Constructio n

Will CAD files of the previous design be provided to use as existing conditions for this project? Or as-builts?

PENDING

1846 Chapter

B

Drawing s

CS100 Please confirm that the water and sewer are sized for the proposed demand and specify if there is a required connection point

PENDING

1846 Chapter

B

Drawing s

CS100 What will be the largest vehicle around the warehouse and around the Paraloft?

PENDING

738 Part 3

Chapter

G303007

Storm

Water

Manageme nt

Section states The DOR is responsible for acquiring approval from NCDEQ for any BMP’s'.

Please confirm that there is no stormwater management for this project and the BMP currently in construction is sized to control this development.

AE2 to validate size of BMPs is adequate to handle anticipated requirement.

Existing

Site

What should be assumed to be the existing conditions of the site for construction regarding grades, status of current construction and temporary structures?

Refer to Part 6, Chapter B.

1879 Chapter

B

Has the underground duct bank from the overhead line to buildings already constructed been installed? If so does this duct bank pass the area of new building construction for connection?

Underground duct bank is installed as indicated in Part 6, Chapter B.

684 D50 Second paragraph of section indicates Emergency lighting and power. However, there is no section in D50 for emergency generator. Is a generator required for this project?

An emergency generator is not required.

Due Date Please consider extending the proposed due date of 30 April

2025 to May 14 2025 due to the easter holiday & amount of unanswered PPIs. Lost time due to holiday time period and pending PPIs questions necessitates lost coordination to obtain appropriate bid information.

Due date was extended to 07

May 2025 via Amendment 003.

1885 &

Part 6, Chapter

B

TS-series TS101 & TS102 plans is showing

MH01, MH02 & MH03 with connection back to existing MH along Battalion Complex road, Has this duct bank been installed?

Is it in support of the new facilities and have they been sized to accommodate these new facilities?

MH01, MH02 & MH03 have sized and installed to support new facilities.

&689

Does this base have a central monitoring station for ESS signal and alarms? If yes, what is the

BLDG number and estimated distance from parachute facility?

How will local alarms connect to base wide system?

PENDING

689 AV D503095 The audio/visual (AV) equipment must be purchased using separate funding supplied by the Activity.

The AV system must include but is not limited to: infrastructure consisting of conduit, boxes, receptacles, jacks and cabling, sound reinforcement systems including speakers, mixers/amplifiers, microphones, front-end equipment, interactive smartboard or wall display systems, flat screens, projectors, video teleconferencing including

Closed-Circuit Television

(CCTV) cameras and associated cabling and equipment hardware.

The Government AV budget on the Bid Schedule/Price Proposal

Form is $14,396 and does NOT include the Contractor’s Handling and Administration Rate (HAR).

Audivisual equipment includes the cost of the AV equipment, speakers, and AV cabeling.

The AV budget does not include conduit, boxes, electrical wiring, etc. HAR is included in the AV budget.

Refer to Part 6,…