UPDATED REVISED BID SCHEDULE FOR P228.pdf

PDF 453 KB Posted

Attached to
Design Bid-Build P228 ATC Tower and Air Operations, Marine Corps Air Station, Cherry Point, North Carolina
Solicitation number
N4008522R2504
Issued by

View the file

Other files

File Type Posted
AMEND 0010 UPDATED WAGE DETERMINATION FOR P228.pdf PDF
AMENDMENT 0011 FOR P228 ATC TOWER.pdf PDF
AMENDMENT 0009.pdf PDF
Amendment 0008.pdf PDF
AMENDMENT 0007 FOR P228.pdf PDF
AMENDMENT 0006 FOR P228.pdf PDF
PPI LOG 04 FOR P228.pdf PDF
AMENDMENT 0005 FOR P228.pdf PDF
UPDATED BID SCHEDULE FOR P228.pdf PDF
P228 PPI LOG 03.pdf PDF
P228 AMENDMENT 0004.pdf PDF
PPI LOG 02 FOR P228.pdf PDF
P228 AMENDMENT 0003.pdf PDF
P228 AMENDMENT 0003 DOCUMENT FOR PPI 4-7.pdf PDF
P228 AMENDMENT 0002.pdf PDF
AMENDMENT 0002-DRAWING REFERENCES.pdf PDF
P228 PPI LOG 01.pdf PDF
AMENDMENT 0001 FOR P228.pdf PDF
Site Visit Log P228.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
1596300_dwg_24of35_V2_Architectural.pdf PDF
1596300_dwg_16of35_V1_Civil.pdf PDF
1596300_dwg_28of35_V3_Equipment.pdf PDF
1596300_dwg_05of35_V1_Civil.pdf PDF
1596300_dwg_14of35_V1_Civil.pdf PDF
1596300_dwg_33of35_V4_Electrical.pdf PDF
1596300_dwg_12of35_V1_Civil.pdf PDF
1596300_dwg_06of35_V1_Civil.pdf PDF
1596300_dwg_21of35_V1_Landscape.pdf PDF
RFP FOR P228 ATC TOWER.pdf PDF
1596300_dwg_23of35_V2_Structural.pdf PDF
1596300_dwg_01of35_V1_General.pdf PDF
1596300_dwg_22of35_V2_General.pdf PDF
Attachment A - Pre-Propsal Injuiries Log.doc DOC document
1596300_dwg_17of35_V1_Civil.pdf PDF
1596300_dwg_09of35_V1_Civil.pdf PDF
1596300_dwg_15of35_V1_Civil.pdf PDF
Attachment E - Historical Small Business Utilization.docx DOCX document
1596300_dwg_04of35_V1_Survey-Geotechnical.pdf PDF
1596300_dwg_34of35_V4_Telecommunications.pdf PDF
1596300_dwg_26of35_V2_Interiors.pdf PDF
USCG MULTI-USE COMPLEX - 00 01 15 LIST OF DRAWINGS 100422.pdf PDF
Attachment F - Small Business Participation Commitment Document.docx DOCX document
ATTACHMENT B BID SCHEDULE FOR P228 ATC TOWER.pdf PDF
JA ML-23-07 CHPT P228 Fire Protection_Redacted.pdf PDF
Attachment H- PIEE Vendor Access Instructions.pdf PDF
1596300_dwg_35of35_V4_Telecommunications.pdf PDF
1596300_dwg_11of35_V1_Civil.pdf PDF
1596300_dwg_27of35_V3_General.pdf PDF
1596300_spc01of01.pdf PDF
Show 40 more

Latest 50 of 68 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

Provide line item prices, where indicated by blank underlines, for the following items:

CLIN 0001 - BASE PRICE. Price includes the following: Total Price for the entire work for Project P228

– Air Traffic Control Tower & Airfield Operations in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.

CLIN 0001A -Subtotal of Base Price for the entire work for Air Ops Building complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item.

CLIN 0001 B-. Subtotal of Base Price for the entire project sitework, outside the facility 5-foot line, for Air Ops Building complete in accordance with the drawings and specifications, but excluding work described in another line Item.

CLIN 0001 C- Subtotal of Base Price for the entire work for Air Traffic Control Tower and TRACON Building complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item.

CLIN 0001 D- Subtotal of Base Price for the entire project sitework, outside the facility 5-foot line, for Air Traffic Control Tower and TRACON Building complete in accordance with the drawings and specifications, but excluding work described in another line Item.

CLIN 0001 E- Unit Price for providing Foundation Piling complete in accordance with the drawings and specifications, but excluding work provided in another line item.

ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0001E

(UNIT PRICE X

NO. UNITS)

PILING LINEAR FEET $ 6,580 $

CLIN 0001 F- Unit Price for removal and disposal of contaminate stockpiled soils impacted above North Carolina action limits and Per-- and Polyfluoroalkyl Substances complete in accordance with the drawings and specifications, but excluding work provided in another line item.

ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0001E

(UNIT PRICE X

NO. UNITS)

SOIL REMOVAL

AND DISPOSAL

TONS $ 25,000 $

CLIN 0001 G- Unit Price for collection, storage, testing and disposal impacted groundwater from fuel and Per- and Polyfluoroalkyl substances, complete in accordance with the drawings, but excluding work provided in another line item.

ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0001E

(UNIT PRICE X

NO. UNITS)

GROUNDWATER

TREATMENT

AND

DISCHARGE

GALLONS $ 650,000 $

CLIN 0001 H- Unit Price for demolition, handling, collection, storage, testing, removal, transportation and disposal of Per- and Polyfluoroalkyl impacted concrete, complete, in accordance with drawings, but excluding work provided in another line item.

ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0001E

(UNIT PRICE X

NO. UNITS)

POTENTIALLY

IMPACTED

CONCRETE

TONS $ 2,500 $

CLIN 0002- Option Item No. 1: Price for providing all work in connection with relocating the existing airfield lighting within B199 including demolition of the existing facility and procurement of new equipment, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0003- Option Item No. 2: Price for providing all work in connection with Demolition of the Existing tower site to include buildings BB1639, B3923, B1640, B1641, B4327, B199, concrete, barriers and asphalt, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0004- Option Item No. 3: Price for providing all work in connection with the Air Ops Canopy, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0005-Option Item No. 4: Price for providing all work in connection with the MTRACON site parking (80 parking spaces), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0006- Option Item No. 5: Price for providing all work in connection with the MTRACON/RMD facility south portion of asphalt perimeter road, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

CLIN 0007- Option Item No. 6: Price for providing all work in connection with removal and replacement of geotechnically unsuitable subgrade soils, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0007

(UNIT PRICE X

NO. UNITS)

GEOTECHNICALLY

UNSUITABLE

SUBGRADE SOILS

REMOVAL AND

DISPOSAL

TONS $ 2,000 $

CLIN 0008- Option Item No. 7: Price for providing Electronic Security System (ESS) equipment, testing, and associated training, but excluding work provided in another Priced line item. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Video Systems complete in accordance with the drawings and specifications. Equipment includes items such as Premise Control Units (PCU), central processing units, field panels, sensors, card readers, keypads, cameras, switches, video recorders, workstations, and the communication cabling connecting these devices together. Include the price for supporting, permanent infrastructure under the Base Price.

Interior supporting infrastructure includes items such as conduit, junction boxes, electronic door strikes, door-hardware, mounting hardware, and power connections. Exterior supporting infrastructure includes items such as exterior duct banks, manholes, utility poles, utility connections, and power connections.

CLIN 0009- Option Item No. 8: Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications, but excluding work provided in another Priced line item. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together. Include the price for supporting, permanent infrastructure under the Base Price. Interior supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.

Government A/V Estimate

HAR (NTE 5%) HAR Amount (Govt A/V Estimate x

HAR%)

Total FF&E Estimated amount (GOV A/V Estimate + HAR Amount)

$944,600.00 % $ $

CLIN 0010- Option Item No. 9: Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

Government FF&E Estimate

HAR (NTE 5%) HAR Amount (Govt FF&E Estimate x

HAR%)

Total FF&E Estimated amount (GOV FF&E Estimate + HAR Amount)

$1,227,037.00 % $ $

1.2 GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Items 1 which includes subtotals of CLINS 1A, 1B, 1C, and 1D along with the sum of the extensions under Contract Line Items 1E, 1F, 1G, and 1H. For CLINs 1E, 1F, 1G, and 1H enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

b. The Government reserves the unilateral right to award CLIN 00002 thru CLIN 0008 to the Contractor at the proposed price. A firm fixed proposed price is required for CLIN 0002 thru CLIN 0008 within 120 calendar days after the contract award. No provision is made for economic price adjustment. If CLINS 0002, 0004 through 0007 are exercised, the contract completion date remains 850 calendar days after award of the contract. If CLIN 0003 is exercised, the contract completion date will be extended 240 days.

c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

d. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

e. If CLIN 2, 3, 4, 5, 6, 7, and/or 8 are exercised, additional bonding and consent of surety is required.

Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.

1.3 OPTIONS 8 AND 9 BID NOTES

These notes apply to CLINs 9 and 10.

a. The estimated amount for FF&E and A/V has been supplied by the Government, to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E and A/V including freight and installation charges. The Government FF&E and A/V Estimate is only an estimated amount.

b. If awarded, line items will be funded separately after completion of FF&E and A/V design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in Section 01 30 01.00 20 DESIGN PROCUREMENT AND INSTALLATION OF

FURNITURE, FIXTURES, AND EQUIPMENT.

c. Bonding is not required for the design, procurement and installation of FF&E and A/V equipment.

d. Offerors may propose a Handling and Administration Rate (HAR) for the FF&E and A/V not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E and A/V. The proposed HAR is a fixed percentage. The HAR amount will be determined/adjusted as the FF&E and A/V amounts are finalized.

e. The Government is not obligated to award the Planned Modification line item(s). Should the Government choose to award the Planned Modification, the line item will be awarded as a negotiated modification to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V.

f. If awarded, the FF&E and A/V modification will be awarded at least six months prior (to the best of the Government’s ability) to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E and A/V without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the FF&E and A/V as a modification. No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor sufficiently demonstrates that an accepted Final FF&E and A/V package was submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V is not available and the Government's award of the modification is in the last six months of the contract.

g. Adequate time for the installation of FF&E and A/V must be allotted in the Construction Schedule after all other trades have completed their work in the installation areas. The projected installation periods required by the vendors in the FF&E and A/V proposals must be honored in the construction schedule, with additional time allotted for complete FF&E and A/V punch lists, prior to building turnover.

Overtime costs for FF&E and A/V installation must not be passed along to the government as part of the Planned Modification costs, unless a compressed schedule has been required/approved by NAVFAC and the contractor conclusively demonstrates that error or delay was caused by the Government.