PRE-PROPOSAL INQUIRY ATTACHMENT
Solicitation Number: N40085-22-R-2504 Contractor Name:
Contractor POC (Name and email):
Instructions: DO NOT submit in PDF format. DO submit as a word document
Contractor
PPI#
Section of RFP or Page Number
Paragraph Reference
Drawing Number
Question RESPONSE AMENDMENT
60 01 30 00 1.5 01 30 00 – 1.5 states, “Provide other insurance coverage as required by State Portugal Guam Diego Garcia BIOT Low.” Please confirm this is not applicable to this solicitation.
RESPONSE: Confirmed, insurance required by State Portugal Guam Diego Garcia BIOT is not required.
AMEND 0005
61 01 14 00 1.3.4 The Exclusionary Period in 1.3.4 states no work can be performed during the Basewide Air Show for 3 days during May 202 to June 2020 and May 2021 and June 2021.
Please confirm this is applicable for May-June 2023 and May- June 2024.
RESPONSE: Confirmed revised dates in amendment 0004. Please review entire amendment including continuation page on Amendment 0004.
AMEND 0005
62 52.211-12 The Liquidated Damages – Construction clause is included by Reference but not by full text with a listed cost per calendar
RESPONSE: FAR 52.211-12
clause for Liquidated Damages has been added as Full Text.
AMEND 0005
day.
Please confirm there are no Liquidated Damages. If there are please provide them by the associated phase.
63 Attachment G
– Small Business Subcontracting
Plan
The Subcontracting Plan notes, Attachment 1provides breakdowns for the base year and option periods.
Percentages may be rounded to nearest tenth of a percent.” Page 10-11 of the Attachment provided a break down of Base Period, Option Period 1-4.4.
Please confirm this is not required for this contract as there are not Option Periods. The goals listed should be based on base bid and all options.
RESPONSE:
1. In accordance to Attachment G instructions, do not provide listing of subcontractors without a firm commitment. “If subcontracting firm commitments are not in place, do not add the subcontractor to the Table”.
2. The contents on the Small Business Participation Commitment form will be evaluated.
Instructions state, “If no subcontractors are identified, provide a detailed explanation for why subcontracts are not identified with frim commitments AND how your firm will be able to achieve the proposed small business participation”.
64 52.211-10 When this project previously bid, the government provided an updated 52.211- Commencement, Prosecution, and Completion of Work which noted the period of performance for each Phase and when the work could begin.
Please provide this information again so all offerors will bid based on the same required schedule.
Response: FAR 52.211-10 clause has been added as Full Text.