P197_1620400 SIGN RFP_Parts 2 - 5.pdf

PDF 5 MB Posted

Attached to
P197 DB Aircraft Maintenance Hangar, MCAS Cherry Point, NC
Solicitation number
N4008521R2516
Issued by

About this file

This request for proposal (RFP) from the Department of the Navy Naval Facilities Engineering Command solicits design-build services for an aircraft maintenance hangar and parking garage at Marine Corps Air Station Cherry Point in North Carolina. Key requirements include design and construction of the hangar, demolition of existing buildings by October 2022, and compliance with security protocols for work within secure areas. The RFP includes parts covering general project requirements, programming documentation, performance specifications, prescriptive specifications, and various project attachments. The anticipated award date is not specified.

View the file

Other files

File Type Posted
Amendment 0012.pdf PDF
Amendment 0011.pdf PDF
P197_-_Price_Proposal_Form AMD11.pdf PDF
AMENDMENT 0010.pdf PDF
P197_-_Price_Proposal_Form AMD 10.pdf PDF
Amendment 0009.pdf PDF
Specification Section 41 22 13.55 .pdf PDF
5.5_room_requirements_P197.pdf PDF
ENCL 5 AND ENCL 6.pdf PDF
ENCL 3 MCAS Cherry Point P199-197 Permanent UFC Exemption Request (12 Jan 2021) - NAVFAC.pdf PDF
ENCL 4 NAVAIR ASW Approval Letter CPT-35.pdf PDF
ENCL 8 2020 FRD Idle Plume Decay Supplement Rev 2.pdf PDF
ENCL 7 Cherry Point Apron Temps.pdf PDF
M00146-E21-01_HQ_CHENG_FINAL.pdf PDF
P197_-_Price_Proposal_Form - Amendment 0008.pdf PDF
Amendment 0008.pdf PDF
ENCL 2 ML Endorsement UFC Exemption Cherry Point Hangars Sun Shades.pdf PDF
ENCL 1 M00146-E01-21 (P199 P197 AIRCRAFT MAINTENANCE HANGAR).pdf PDF
Amendment 0007.pdf PDF
AMD 07 Site Visit-Attendance Sheet.pdf PDF
PASS and ID_One Day Pass Request Form.xlsx XLSX spreadsheet
ROICC Florence Cherry Point - Google Maps - Office Location.pdf PDF
ROICC Florence Cherry Point - Base Maps - Office Location.pdf PDF
Amendment 0006.pdf PDF
P197_1620400 SIGN RFP_Parts 6 (2 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (11 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (4 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (6 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (9 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (1 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (3 of 11).pdf PDF
Amendment 0005 - Phase II.pdf PDF
P197_1620400 SIGN RFP_Parts 6 (7 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (5 of 11).pdf PDF
P197_1620400 SIGN RFP_Parts 6 (8 of 11).pdf PDF
P197_-_Price_Proposal_Form.pdf PDF
P197_1620400 SIGN RFP_Parts 6 (10 of 11).pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
ATTACHMENT E SPCD.docx DOCX document
ATTACHMENT D HISTORICAL SMALL BUSINESS UTILIZATION.docx DOCX document
Amendment 0001.pdf PDF
ATTACHMENT B Past Performance Questionnaire.pdf PDF
Attachment A - PPI Inquiry Log.xls XLS spreadsheet
ATTACHMENT F SMALL BUSINESS SUBCONTRACTING PLAN.docx DOCX document
ATTACHMENT C Construction and Design Exp Project Data Sheet.pdf PDF
N4008521R2516.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK ORDER NO. 1620400

APPROPRIATION: MCON

P197 - Aircraft Maintenance Hangar and Parking Garage

At the

MCAS Cherry Point, Havelock, NC

SUBMITTED BY:

NAVFAC MID-ATLANTIC

DESIGN AND CONSTRUCTION BUSINESS LINE

9742 MARYLAND AVENUE

NORFOLK, VIRGINIA 23511-3095

PREPARED BY:

Architectural: Brian Bevan, R.A.

Interior Design: Christine McKinley, CID Project Manager: George F. Sparrow, P.E.

Structural: Stacia Keller, P.E.

Mechanical: Robert “Ernie” Johnson, P.E.

Electrical: Loreto Pantano, E.I.T.

Fire Protection: Scott Arne, PE Civil: Christopher Schmitt, P.E.

Landscape Architecture: Amy McKay, RLA.

Geotechnical/DM: Robert Huntoon, P.E.

Cost: Thornton Elmore, P.E.

APPROVED BY:

For Commander, NAVFAC MID ATLANTIC:

Date: September 10, 2021

P197 - Aircraft Maintenance Hangar & Parking Garage WON 1620400 MCAS Cherry Point

1.0 Table of Contents (RFP Parts 2-6)

1. PART 2 – GENERAL REQUIREMENTS

01 14 00 WORK RESTRICTIONS

01 20 00.05 20 PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD

01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD

01 31 19.05 20 POST AWARD MEETINGS

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD

01 35 13.05 20 SPECIAL PROJECT PROCEDURES FOR DESIGN-BUILD

01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN-BUILD

01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL

01 45 35.05 20 SPECIAL INSPECTIONS FOR DESIGN-BUILD

01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS FOR DESIGN-BUILD

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT

INFORMATION (eOMSI) 01 78 30.00 22 GIS Data Deliverables

01 91 00.15 TOTAL BUILDING COMMISSIONING

2. PART 3 – PROJECT PROGRAM

CHAPTER 1 & 2. PROJECT DESCRIPTION AND PROJECT OBJECTIVES

CHAPTER 3. SITE ANALYSIS

CHAPTER 4. SPACE TABULATION FORM

CHAPTER 5. ROOM REQUIREMENTS

CHAPTER 6. ENGINEERING SYSTEMS REQUIREMENTS

3. PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS

A10 FOUNDATIONS

A20 BASEMENT CONSTRUCTION

B10 SUPERSTRUCTURE

B20 EXTERIOR ENCLOSURE

B30 ROOFING

C10 INTERIOR CONSTRUCTION

C20 STAIRS

C30 INTERIOR FINISHES

D10 CONVEYING

D20 PLUMBING

D30 HVAC

D40 FIRE PROTECTION

D50 ELECTRICAL

E10 EQUIPMENT

E20 FURNISHINGS

F10 SPECIAL CONSTRUCTION

F20 SELECT BLDG DEMOLITION

G10 SITE PREPARATIONS

G20 SITE IMPROVEMENTS

G30 SITE CIVIL/MECHANICAL UTILITIES

G40 SITE ELECTRICAL UTILITIES

Z10 GENERAL PERFORMANCE TECHNICAL SPECIFICATION

4. PART 5 – PRESCRIPTIVE SPECIFICATIONS

Section 13 31 33.00 22 Pre-Engineered Framed Fabric Structures.

Section 21 13 20.00 20 – Foam Fire Extinguishing for Aircraft Hangars Section 41 22 13.55 - BRIDGE CRANES, UNDER RUNNING, AIRCRAFT HANGAR

5. PART 6 – ATTACHMENTS

• P197 Aircraft Maintenance Hangar Construction Security Plan (Under Separate Cover)

• Topographical Site Survey and Utilities

• P199 Early Site Demolition As-Built Survey Drawings

• Abandoned POL Line Layout

• P235 Flightline Utility Upgrade Drawings

• Elevations of Building 1 at MCAS Cherry Point

• FINAL F35 6th and A St Traffic Plan 20190419

Traffic Study Alt 1 P239 A St Typical Section

• Vehicle Barrier List (June 2020)

• Geotechnical Site Characterization Report prepared by HDR,, Inc.

• Environmental Guidance for Soil Boring Activities Nov 2017

• NAVFAC Fact Sheet Vapor Intrusion

• HAZMAT Reports

• Permits Record of Decision (PROD)

• Air Station Order 5560.6A – Installation Access

• BEAP Cherry Point 113020

• Elevation of Building 1

• OU14 LUC Survey Plat

• Requirements for Offsite Site Soil

• Example Environmental Work Plans

• P199 CERCLA Work Plan Final Submittal Jan 21

• P235 Site Safety and Health Plan

• PFAS Sampling Report and Treatability

• RCRA Work Plan with Appendices

• Existing Building Drawings Building 1670 Building 1699 Building 3745 Building 4157 Building 4158 Building 4159

HANGAR - PART TWO - GENERAL REQUIREMENTS - Page 1

PART TWO - GENERAL REQUIREMENTS

P197-Aircraft Maintenance Hangar & Parking Garage WON 1620400

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 14 00 WORK RESTRICTIONS

01 20 00.05 20 PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD

01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD

01 31 19.05 20 POST AWARD MEETINGS

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

01 33 29.05 20 SUSTAINABILITY REPORTING

01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN-BUILD

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL

01 45 35.05 20 SPECIAL INSPECTIONS FOR DESIGN-BUILD

01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS FOR DESIGN-BUILD

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 60 00.00 22 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION

01 74 19.05 20 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT FOR

DESIGN-BUILD

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT

INFORMATION (eOMSI)

01 78 30.00 22 GIS DATA DELIVERABLES

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 13 - SPECIAL CONSTRUCTION

13 31 33.00 22 PRE-ENGINEERED FRAMED FABRIC STRUCTURES

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.55 BRIDGE CRANES, UNDER RUNNING, AIRCRAFT HANGAR

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. Code (USC)

10 USC 6011 Navy Regulations

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G

Personnel List; G

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. Buildings 4157 and 4158 must be completely demolished in accordance with the project requirements and work limits turned over to the construction contractor of P239 by October 31, 2022.

b. Buildings 1669 and 1670 will remain in use by the government until the end of July 2022. Access to the building and supporting parking is not be disrupted until the facilities are no longer occupied by the government.

d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such

SECTION 01 14 00 Page 1 entry. Mark Contractor equipment for identification.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 Additional Personnel Requirements

1.4.1.2.1 General Construction

General construction of the secure area must be performed by U.S. firms using U.S. persons. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Utility work that penetrates the secure area and installation of doors in these areas are not general construction

1.4.1.2.2 Finish Work

Finish Work within the secure area must be accomplished by U.S. persons (an individual who has been lawfully admitted for permanent residence as defined in 8 U.S.C. 1101(a)(20) or who is a protected individual as defined by Title 8 U.S.C. 1324b(a)(3)) personnel. Finish Work includes construction activities such as insulation, floor/partition/ceiling systems, cabinet work, conveyor systems, specialties, building furnishings/ fixtures/equipment, mechanical/electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.

1.4.1.2.3 Electronic Security Systems Equipment

Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, card readers, cable installation, and system programing, testing and training must be performed by U.S. citizens who have been subjected to a trustworthiness determination.

1.4.1.3 Installation Access

Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.4.1.3.1 Registration for DBIDS

Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:

a. Present a letter or official award document (i.e. DD Form 1155 or SF

SECTION 01 14 00 Page 2

1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .

d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

1.4.1.3.2 DBIDS Eligibility Requirements

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.

The Government is the final authority.

1.4.1.3.3 DBIDS Notification Requirements

a. Immediately report instances of lost or stolen badges to the Contracting Officer.

b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

1.4.1.3.4 One-Day Passes

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.4.1.4 No Smoking Policy

Smoking is prohibited within and outside of all buildings on

SECTION 01 14 00 Page 3 installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.4.4 Exclusionary Period

No work must be performed during the bi annual air show which is a three day event usually during May, inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.

1.4.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and natural gas are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.

SECTION 01 14 00 Page 4

1.5 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

P-197 Aircraft Maintenance Hangar Constuction Security Plan (CSP).

1.5.1 [Enter Appropriate Subpart Title Here] 1.5.2 Citizenship Requirementse

Work under this contract is restricted to U.S. persons defined as individual who has been lawfully admitted for permanent residence as defined in 8 U.S.C. 1101(a)(20) or who is a protected individual as defined by Title 8 U.S.C. 1324b(a)(3)).

1.6 Prohibited Items

Pursuant to the authority contained in 10 USC 6011 and U.S Navy Regulations, Chapter 8, Article 0826, the following items are prohibited:

(1) Personal photographic equipment of any kind, including but not limited to cameras (still and video), film and cellular telephones with cameras.

(2) Weapons or other dangerous materials of any kind, including but not limited to firearms, ammunition, knives (with blades longer than 2 inches), explosives, incendiaries, personnel defense aerosols/sprays.

(3) Personal reproduction equipment of any kind, including but not limited to photocopying, copying, and recording devices.

(4) Alcoholic beverages of any kind.

(5) Personally owned portable electronic devices (PEDs) used for storing data, including, but not limited to removable storage devices (e.g., memory sticks, rewriteable CDs and DVDs, Zip and floppy disks).

(6) Personally Owned Portable Electronic Device (PED) Functionality Matrix.

SECTION 01 14 00 Page 5

SECTION 01 20 00.05 20

PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD

01/12

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20

DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Earned Value Report; G

1.3 EARNED VALUE REPORT

1.3.1 Data Required

This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer an Earned Value Report (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs must be summarized and totals provided for each construction category.

1.3.2 Schedule Instructions

Payments will not be made until the Earned Value Report from cost-loaded NAS has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM must include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report must be fully developed with detailed construction line items as design progresses. The complete design and construction Schedule of Prices or Earned Value Report must be submitted and accepted prior to starting construction work.

SECTION 01 20 00.05 20 Page 1

For Fast-Tracked or Critical Path Submittals of construction projects, the Earned Value Report must include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.

Additionally, the Earned Value Report must be separated as follows:

a. Primary Facility/s Cost Breakdown:

Defined as work on the primary facility/s out to the 5 foot line. Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC equipment, that may extend beyond the 5 foot line.

Provide a cost breakout for all Primary Facility features that support Low Impact Development (LID), such as vegetated roof and rainwater harvesting features. The sum of the Primary Facility Cost above - a. and these Primary Facility LID sub-items - (1) must equal the total Primary Facility cost. Provide a subtotal cost of all Primary Facility LID sub-items on the Earned Value Report at design complete and project closeout.

b. Supporting Facilities Cost Breakdown:

Defined as site work, including incidental work, outside the 5 foot line.

Provide a cost breakout for all Supporting Facilities features that support LID, such as bioswales, permeable paving, infiltration basins, tree box filters, etc.. The sum of the Supporting Facilities Cost above -

b. and these Supporting Facilities LID sub-items - (1) must equal the total Supporting Facilities cost. Provide a subtotal cost of all Supporting Facilities LID sub-items on the Earned Value Report at design complete and project closeout.

1.3.3 Real Property Assets

Provide the Draft and Interim DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes. Provide the Draft DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the designed real property assets that apply to this contract and include all associated cost. The Contractor must meet with the Contracting Officer and the Real Property Accounting Officer during the Post Award Kickoff Meeting and the Project Closeout Meetings to modify and include any necessary changes to the DD Form 1354. Provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost. Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs / Category Codes.

Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/ Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during the course of the work.

Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.

SECTION 01 20 00.05 20 Page 2

Real Property Assets identified in Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES paragraph "REAL PROPERTY RECORD" apply to work covered by this specification.

Cost data accumulated under this section are required in the preparation of DD Form 1354. Coordinate with Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES in paragraph titled "DD Form 1354".

1.3.4 Schedule Requirements for HVAC TAB

The field work requirements of TAB work required by RFP Part 4 D30, HVAC must be broken down in the Earned Value Report from the cost-loaded NAS by separate line items which reflect measurable deliverables. Specific payment percentages for each line item will be determined on a case by case basis for each contract. The line items are as follows:

a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit resulting findings to the Government to allow correction of the design. The progress payment will be issued after review and approval of the report.

b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.

c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).

d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.

e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.

f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data must be compiled into a report and submitted to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.

SECTION 01 20 00.05 20 Page 3

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates will be based upon the applicable provisions of the EP 1110-1-8 .

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract.

Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The Requests for payment must include the documents listed below:

a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the contract.

b. The Earned Value Report from the cost-loaded NAS, showing in detail:

the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC Form 4330/110 on NAVFAC contracts when a Monthly Estimate for Voucher is required.

c. Updated Project Schedule and reports required by the contract

d. Contractor Safety Self Evaluation Checklist

e. Other supporting documents as requested

f. Updated copy of submittal register.

g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.

h. Subcontractor and supplier payment certification.

i. Materials on Site.

j. Affidavit to accompany invoice (LANTDIV NORVA Form 4-4235/4 (Rev.5/81)).

1.5.2 Submission of Invoices

If DFARS Clause 252.232-7006 is included in the contract, the documents listed in paragraph CONTENT OF INVOICE above must be provided in their entirety as an attachment in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it must be provided as instructed by the Contracting Officer. All other paper invoices must be forwarded with specific marking on the envelope. This marking must be in the front lower left hand corner, in large letters, "INVOICES - ENCLOSED."

Monthly invoices and supporting forms for work performed through the anniversary award date of the contract must be submitted to the

SECTION 01 20 00.05 20 Page 4

Contracting Officer within 5 calendar days of the date of invoice For example, contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

SECTION 01 20 00.05 20 Page 5

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs) and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval of the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 20 00.05 20 Page 6

SECTION 01 30 00.05 20

ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD

03/13

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20

DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Insurance

1.2 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

a. Comprehensive general liability: $500,000 per occurrence

b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage

c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.

d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,

e. Others as required by the State.

Refer to Section 01 33 00.05 20, CONSTRUCTION SUBMITTAL PROCEDURES for typical preconstruction submittals similar to insurance.

1.3 CONTRACTOR PERSONNEL REQUIREMENTS

1.3.1 Subcontractor Special Requirements

1.3.1.1 Asbestos Containing Material

All contract requirements of PART 4, F20 SELECTIVE BUILDING DEMOLITION, assigned to the Private Qualified Person (PQP) must be accomplished directly by a first tier subcontractor.

1.3.1.2 HVAC TAB

All contract requirements of TAB work required by PART 4 D30, HVAC, must be accomplished directly by a first tier subcontractor. No TAB work

SECTION 01 30 00.05 20 Page 1 required by PART 4, D30, HVAC, is allowed to be accomplished by a second tier subcontractor.

1.3.1.3 Qualified Testing Organization

All contract requirements of work required to be performed by a Qualified Testing Organization in PART 4, D50 ELECTRICAL and G40 SITE ELECTRICAL UTILITIES, must be accomplished directly by a first tier subcontractor.

No work to be performed by a Qualified Testing Organization, required by PART 4, D50 and G40 is allowed to be accomplished by a second tier subcontractor.

1.4 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, the Quality Control (QC) representative must also have fluent English communication skills.

1.5 AVAILABILITY OF CAD DRAWING FILES

After award and upon request, the electronic "Computer-Aided Design (CAD)" drawing files will be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CAD drawing files are not construction documents.

Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CAD files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these CAD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates or modifies these electronic CAD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) must be removed.

SECTION 01 30 00.05 20 Page 2

1.6 CLEANUP

Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances;

polish transparent and glossy surfaces; vacuum carpeted and soft surfaces. Clean equipment and fixtures to a sanitary condition. Replace filters of operating equipment (reusable filters can be cleaned). Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site.

1.6.1 Extraordinary Cleanup Requirements

The following cleanup requirements apply: Foreign Object Damage (FOD) Control: Demolition, alteration and construction operations under this contract will be performed in proximity to the runways, taxiways, access runways, fueling locations, and aprons. Exercise due care at all times for the entire duration of this contract to prevent materials, debris, trash or other items from creating hazards to aircraft and vehicles. Inspect all exterior grade surfaces areas and streets accessible to the runways and taxiways within the security perimeter of this project. Sweep all applicable areas when FOD presents a hazard..

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 30 00.05 20 Page 3

SECTION 01 31 19.05 20

POST AWARD MEETINGS

09/15

PART 1 GENERAL

1.1 SUMMARY

This document includes post-award requirements for project kickoff and subsequent design and preconstruction meetings.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20

DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Design Submittal Packaging Proposal; G

Design Baseline NAS; G

Construction Baseline NAS; G

Performance Assessment Plan (PAP); G

Design Presentation Concept Site and Floor Plans; G

CDW Facilitator Experience Resume; G

CDW Preliminary Concept Design; G

CDW Cost Estimate; G

Concept Design Workshop Report; G

1.3 POST AWARD KICKOFF MEETING

The Post Award Kickoff (PAK) meeting is made up of Contract Administration, Concept Design Presentation/Design Development or Concept Design Workshop (CDW), Partnering, and Scheduling. If mutually beneficial to the Contractor and the Government, these four elements may be addressed in a single multi day meeting, but most often multiple scheduled meetings are required. Schedule a separate meeting or a separate day of the multiday PAK, to accomplish the Design Presentation/Design Development Meeting or Concept Design Workshop(CDW).

1.3.1 PAK Meeting Schedule and Location

Within 35 calendar days after contract award, and prior to commencing work, meet with the Contracting Officer for the PAK meeting(s). The meeting will be located at a specific time and place to be determined by

SECTION 01 31 19.05 20 Page 1 the Contracting Officer.

1.3.2 PAK Meeting Outcomes

The meeting(s) outcomes are:

a. Integrate the Contractor and all client representatives into the project team.

b. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements. Confirm the design is within the project budget.

c. Establish and explain policies and procedures for completion of a successful project.

d. Establish clear lines of communication and points of contact for Government and Contractor team members.

e. Obtain an acceptable conceptual design including floor and site plans, signed by the client, Contractor and other key team members.

f. Establish project design schedule, design submittal packaging, and preliminary construction schedule in accordance with Section

01 32 17.05 20 COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS) FOR

DESIGN-BUILD. Discuss design milestones and events that will be included in the Quality Control Communication Plan.

g. Establish clear expectations and schedules for facility turnover, providing DD Form 1354 asset management records, eOMSI submittals, Guiding Principle Validation, Third Party Certification (if applicable), and training of Government maintenance personnel.

h. Establish procedure for design packages reviews, Contractor's resolution to comments, and Government's role in review of packages.

i. Establish clear expectations for the Concept Design Workshop.

j. Establish clear expectations for Design Model presentations for projects implementing Building Information Management/Modeling (BIM).

1.3.3 PAK Meeting Contractor Attendees

The following Contractor key personnel must attend the PAK: Project Manager, Project Scheduler, Lead Designer-of-Record (DOR), Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Superintendent, QC Manager, and the DQC Manager.

Optional attendees include: Principal, Assistant Project Manager, major subcontractors and specialized supplemental QC personnel.

1.3.4 Contract Administration

Contract administration roles and responsibilities will be addressed.

1.3.5 Concept Design Workshop (CDW)

Provide a CONCEPT DESIGN WORKSHOP that meets the following requirements;

SECTION 01 31 19.05 20 Page 2

1.3.5.1 CDW General Requirements

a. Methodology. Concept a CDW for this project. This effort will examine project functions and requirements, quality and life safety costs, analyze alternate design concepts, expose and resolve project issues, and develop the final conceptual design.

b. Facilitator. Provide a Facilitator who is experienced in conducting Concept Design Workshops. Submit a CDW Facilitator Experience Resume to the Contracting Officer describing his experience. He or she will be responsible for leading the team in a timely manner, making sure that issues are pursued and resolved to the maximum extent possible, documenting meetings, organizing the design concept documents for on-site approval, and providing the Concept Design Workshop Report.

c. Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop effort and provide assistance to the Facilitator in development of the Concept Design Workshop Report, including most of the required documentation.

d. Concept Design Workshop Report. Produced almost entirely on-site, the Concept Design Workshop Report must summarize the final conceptual design.

e. Award Amount. At each contract stage, the Contractor must verify that the concept is within the contract award amount.

1.3.5.2 CDW Procedures

a. Preliminary Work.

The Contractor's Design Team must complete the following prior to the on-site workshop:

(1) Review the contract documents and references explaining the project scope and history.

(2) At the Post Award Kickoff meeting, the User(s) makes a presentation of their functional requirements.

(3) Prepare and submit, at least 21 days in advance of the CDW, 15 copies of a CDW Preliminary Concept Design (Concept #1), a Basis of Design, and a statement that the concept provided is within the award amount.

(4) Make arrangements for and provide an appropriate conference room convenient to the project site and Users for use by the Design Team and government participants during the workshop.

(5) Incorporate government comments in a revised Concept #1 and produce at least 20 copies of the revised Concept #1 documents for distribution at the workshop.

(6) Facilitator conducts meeting with NAVFAC representatives before the CDW to review preparations, relationships, and the status of work to be accomplished.

SECTION 01 31 19.05 20 Page 3

b. On-Site Workshop.

Conduct an on-site CDW for a minimum of five working days to allow the Design Team to accomplish the following items during the on-site phase of the CDW. The Design Team should expect longer than normal workdays.

(1) On the first day of the workshop, meet with the using activity, Station and other Government representatives. The Facilitator will describe the CDW process and review the workshop agenda. The user(s) will provide a functional presentation. This is to reiterate to all participants the User(s) needs and desires. The intent is to make the design solution and issue resolution function-oriented.

(2) Present the revised Concept #1 and respond to questions.

(3) Participate in a comment/creative session to generate ideas to improve this project in the areas of function, quality and total life cycle cost, issue resolution and sustainable design within the award amount. It is often helpful to request User comments in writing so they may be considered, responded to, and presented at subsequent presentations.

(4) Create a new concept design. Design concepts must include drawings, sketches, and other graphics as necessary to fully describe the concept. Prepare at least 20 copies for distribution at all presentations.

(5) Repeat applicable steps as necessary. Usually, three concepts are required. The final concept must be within the contract award amount.

(6) The final concept must include the following:

(a) Site Plan: Show the layout of the proposed facility in relation to major landmarks. Show all buildings, access roads, parking, pedestrian walkways, roads, sidewalks, landscaping, and major utilities. Indicate major dimensions and orientation.

Provide a building code analysis, relating the proposed building site, size, and construction type to maximum allowable limits of the International Building Code.

(b) Building Floor Plans: Provide floor plans depicting functional utilization of spaces and furniture and equipment layout. Show room sizes or dimensions. Provide a Life Safety Code analysis with the floor plan to identify required life safety and egress features.

(c) Perspective Sketches: Provide at least one sketch to show a perspective of major buildings. The sketch should not be elaborate but must show the proposed form and massing, colors to be used, and an indication of materials used.

(d) Mechanical Plans: Provide plans as necessary to show the essential work and intent of the design. Suggestions include equipment layouts, zones, etc.

(e) Electrical Plans: Provide plans as necessary to show the essential work and intent of the design. Suggestions include

SECTION 01 31 19.05 20 Page 4 special light fixture types, locations, switching, power outlets and panelboard location. Provide electrical distribution single line diagram.

(f) Cost Estimate: Provide a CDW Cost Estimate and statement that the concept presented can be constructed within the award amount.

(g) Basis of Design: Describe the intent of the design by discipline. Address material quality, energy efficiency and life cycle costs.

(h) Sustainable Design: Demonstrate ability to achieve identified Guiding Principle sustainability goals and also Third Party Certification sustainability goals, if applicable. Provide Preliminary Sustainable Notebook, refer to Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD for requirements.

(i) System Safety Engineering

(j) Secure Space Construction: Provide floor plans depicting functional utilization of spaces and furniture and equipment layout within the secure spaces. Show room sizes or dimensions. Provide a Life Safety Code analysis with the floor plan to identify required life safety and egress features.

Provide secure space plans as separate package from remaining Building Floor Plans. See ESR F10 for additional requirements.

(7) Prepare 20 copies of the final concept (drawings, basis of design and statement that the concept is within the award amount) for distribution at the final presentation.

(8) Dependent upon the project, the Concept Design Workshop Report is provided by the Facilitator, includes all items included in the final concept design and the following:

(a) Endorsements: Include a copy of the signature/endorsement sheet.

(b) Comments: Include comments and resolutions concerning the final concept design.

(c) Executive Summary: Summarize the workshop, including how the various concepts differed and were improved during the workshop.

(d) Special Design Features: Identify and describe unique project needs and features, e.g., pile foundations, physical security, intrusion detection systems, access control, construction in humid climates, pollution abatement, tempest, HEMP, etc.

(e)…

This is the start of the file's text. The full file is on GovTribe.