This document is an attachment to a Request for Proposal for design-build services for an aircraft maintenance hangar at Marine Corps Air Station Cherry Point in North Carolina. The Naval Facilities Engineering Command is seeking proposals for the design and construction of a new hangar facility with an estimated award value between $25-35 million. Proposals are due by September 15, 2021 and the contract is expected to be awarded by November 2021, with project completion required by September 2023. Offerors must complete the Construction and Design Experience Project Data Sheet to demonstrate relevant past performance on similar aviation and hangar projects. The selected contractor will be responsible for all design, engineering, and construction services to deliver a fully operational hangar.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT C
CONSTRUCTION & DESIGN EXPERIENCE PROJECT DATA SHEET
Project No. (check one) : Hangar CON #1 Hangar CON #2 Hangar CON #3 Hangar CON #4 Hangar CON #5 Parking Garage CON #1 Parking Garage CON #2 Parking Garage CON #3 Parking Apron & Taxiway CON #1 Parking Apron & Taxiway CON #2 Parking Apron & Taxiway
CON #3
Hangar DESIGN #1 Hangar DESIGN #2 Hangar DESIGN #3 Hangar DESIGN #4 Hangar DESIGN #5 Parking Garage DESIGN #1 Parking Garage DESIGN #2 Parking Garage DESIGN #3 Parking Apron & Taxiway DESIGN #1 Parking Apron & Taxiway DESIGN #2 Parking Apron &
Taxiway DESIGN #3
1. Experience for: Offeror Joint-Venture Other (Explain)
Firm Name:
Address:
Phone Number:
DUNS Number:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain)
Percent of project work performed:
If subcontractor, who was prime (Name/Phone #):
3. Contract Number: Delivery/Task Order Number:
Title:
Location:
4. Award Date (mm/dd/yy): Completion Date (mm/dd/yy):
5. Type of work:
New Construction Renovation Repair Alteration Other (explain):
6. Type of Contract/Task Order: (Check ALL that apply)
Firm-Fixed Price Cost/Time and Material Other (explain):
Complete Block 7 for Construction Projects. Complete Block 8 for Design Projects.
7. Construction Project:
Award Amount: Final Price:
Type of Contract/Task Order: (Check ALL that apply)
Design-Build Design-Bid-Build Delivery/Task Order (IDIQ) Other (explain):
If Design-Build, identify the Lead Design Firm:______________________________________________
8. Design Project:
A/E Design Fee: Total Construction Value:
Type of Contract/Task Order: (Check ALL that apply)
Design-Build RFP Development Designer of Record Engineering Services Full Plans & Specs
Other (explain):
9. Provide a detailed description of the project and the relevancy to the project requirements of this RFP (i.e.: unique features, square footage, construction methods), including any sustainable features or USGBC LEED certifications. If design-build, include a description of the design-effort.
10. Provide a detailed description of what work your firm self-performed on this project:
11. Other Information: