BLDG 11
OSP
CONTRACTOR SHALL CONTACT BASE TELEPHONE PRIOR TO CONSTRUCTION; GOV’T SHALL REMOVE
EXISTING OSP CABLING PRIOR TO CONSTRUCTION.
INSTALL (1) 4” PATHWAY AND 50 PR COPPER FROM TELECOM ROOM TO RP400-1, ADJACENT TO BLDG
27 (~125’). LEAVE 10’ SLACK COIL IN RP400-1; GOVT SHALL PERFORM SPLICE.
INSTALL/REUSE (1) 1 ¼” HDPE DUCT FROM TELECOM ROOM IN BLDG 11 TO TELECOMM ROOM IN BLDG
27. TERMINATE BOTH ENDS OF FIBER IN BLDGS 11 AND 27.
BLDG 1
INSTALL (1) 4” FROM NEW MDF TELECOM ROOM TO MECH ROOM/ENTRANCE FACILITY AT REAR OF
BLDG. INSTALL 300 PR OSP COPPER FROM NEW MDF TO MECH ROOM/EF AT REAR OF BLDG.
TERMINATE 300 PAIR OSP IN NEW MDF ON BUILDING ENTRANCE PROTECTORS. LEAVE 20’ SLACK COIL
IN MECH/EF ROOM; GOV’T SHALL PERFORM SPLICE.
INSTALL (1) 4” FROM NEW MDF TELECOM ROOM TO EXISTING NOC SPACE. INSTALL 24 STRAND SM FOC
FROM MDF TO EXISTING NOC SPACE. TERMINATE BOTH ENDS OF SM FOC IN FIBER DISTRIBUTION
CABINET PER SPECS.
BACKBONE CABLING/PATHWAYS
MINIMUM (2) 3” CONDUITS FROM MDF TO ALL IDF’S (IDF “B”, IDF “EOC”, IDF “SIPR CAFÉ”). SIPR CAFÉ
ONLY REQUIRES (1) 3”.
24 SM FOC (MIC), 12 MM FOC (MIC) AND 200 PAIR COPPER RISER FROM NEW MDF TELECOM ROOM TO
IDF “B” TELECOM ROOM.
24 SM FOC, 12 MM FOC AND 100 PAIR RISER FROM NEW MDF TELECOM ROOM TO IDF “EOC”
12 SM FOC ONLY TO IDF “SIPR CAFÉ”
COORDINATE WITH BASE TELEPHONE PRIOR TO THE REMOVAL OF ANY CABLING WITHIN BLDG 1.