Amendment 0006.pdf

PDF 21 KB Posted

Attached to
Design-Bid-Build, P653 Dry Dock Flood Protection Improvements
Solicitation number
N4008520R0063
Issued by

About this file

This document is an amendment to a solicitation for the Design-Bid-Build, P653 Dry Dock Flood Protection Improvements project at the Norfolk Naval Shipyard in Portsmouth, Virginia. The amendment provides responses to contractor questions, modifies the jet grout mix design requirements by removing compressive strength testing, and adds a minimum of three test sections for jet grouting to be located between specific station ranges. The project scope involves constructing a permanent flood wall to protect several dry docks and associated facilities from flooding, modifying dry dock caissons, and installing removable capstans. The Department of the Navy Naval Facilities Engineering Command issued the solicitation.

View the file

Other files

File Type Posted
AMD 0005 DWG2.pdf PDF
Amendment 0005.pdf PDF
AMD 0005 DWG1.pdf PDF
NNSY Map.pdf PDF
20R0063 Site Visit Log.docx DOCX document
20R0063 Amendment 0004.pdf PDF
20R0063 Amendment 0003.pdf PDF
1588810Amend0002-dwg-2of2 (S-E).pdf PDF
1588810Amend0002-dwg-1of2 (G-C).pdf PDF
20R0063 Amendment 0002.pdf PDF
20R0063 Amendment 0001.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
1588810-SPC-03of24-App A02.pdf PDF
1588810-SPC-05of24-App A04.pdf PDF
1588810-SPC-21of24-App F3.pdf PDF
1588810-DWG-05of14 (SURVEY).pdf PDF
1588810-SPC-12of24-App A11.pdf PDF
Attachment B - SECNAV_5512_1_11787-One Day Past Request.pdf PDF
1588810-DWG-12of14 (CU2).pdf PDF
1588810-SPC-23of24-App F5.pdf PDF
Attachment J - CVS-CIA Blank Spreadsheet.xlsx XLSX spreadsheet
1588810-DWG-14of14 (ARCH-ELEC).pdf PDF
1588810-SPC-02of24-App A01.pdf PDF
1588810-SPC-20of24-App F2.pdf PDF
1588810-DWG-09of14 (CS2).pdf PDF
1588810-SPC-11of24-App A10.pdf PDF
1588810-SPC-16of24-App C.pdf PDF
Attachment G - Small Business Participation and Commitment Strategy.docx DOCX document
1588810-DWG-03of14 (GEOTECH1).pdf PDF
1588810-DWG-08of14 (CS1).pdf PDF
1588810-SPC-09of24-App A08.pdf PDF
1588810-SPC-04of24-App A03.pdf PDF
Attachment A - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
1588810-SPC-15of24-App B.pdf PDF
1588810-SPC-07of24-App A06.pdf PDF
1588810-SPC-18of24-App E.pdf PDF
1588810-SPC-24of24-App F6.pdf PDF
1588810-DWG-06of14 (C_CD).pdf PDF
1588810-DWG-11of14 (CU1).pdf PDF
1588810-SPC-06of24-App A05.pdf PDF
1588810-SPC-22of24-App F4.pdf PDF
1588810-DWG-04of14 (GEOTECH2).pdf PDF
1588810-DWG-02of14 (GEN2).pdf PDF
Attachment H - Price Proposal Form.docx DOCX document
1588810-DWG-13of14 (STR).pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
1588810-SPC-14of24-App A13.pdf PDF
Attachment I - ODP Form.xls XLS spreadsheet
Attachment F - Small Business Subcontracting Record.docx DOCX document
1588810-SPC-01of24.pdf PDF
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DESIGN-BID-BUILD, P653 DRY DOCK FLOOD PROTECTION IMPROVEMENTS, NORFOLK NAVAL SHIPYARD, PORTSMOUTH, VA

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Rachel Honecker; rachel.honecker@navy.mil; 757-341-1652

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Jun-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R0063

X 9B. DATED (SEE ITEM 11)

16-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jun-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008520R0063

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0006

The purpose of this Amendment is to provide the following:

1. PPI responses.

Reference Question Response

Page Section Paragraph

181 Section 2.4 Jet Grout Mix Design requires neat grout strength to exceed 1,000 psi at 28 days when tested in accordance with ASTM C109/C109M. This test method is for sanded grouts. The neat cement grout used for jet grouting does not contain sand. It is not generally subject to compression testing since it typically has a water/cement ratio exceeding 1.0 and is an unstable suspension.

In lieu of compression testing per ASTM C109, we suggest specific gravity measurements of the neat grout per ASTM D4380 be taken at routine intervals to verify the water/cement ratio of the grout prior to jet grouting.” How many test sections doe the test program require? Will the test program require test sections in more than one area?

Please see Amendment 0006.

197 24 01 57 19.00

3.3.3.1 How is the contractor compensated for

testing and disposal for hazardous or contaminated groundwater generated during the construction processes such as dewatering?

Bid per contract documents. See specification 01 57 19.01 20.

SECTION 35 41 20

SECTION 35 41 20 CUTOFF WALLS

2.4 JET GROUT MIX DESIGN

Delete the fourth row (subject Neat Grout Strength) of the mix property table in its entirety.

3.5 JET GROUTING TEST PROGRAM

Add the following to the end of subparagraph 3.5.b:

N4008520R0063

“Construct a minimum of three total test sections. One located between STA 7+70 and 9+05, another between STA 25+20 an 26+95, and another between STA 51+60 and 57+75.”

(End of Summary of Changes)