This document provides details of an Industry Day flyer and related federal contract opportunity notice for the construction of a multi-mission dry dock at the Portsmouth Naval Shipyard in Kittery, Maine. The Navy will hold an Industry Day on November 13, 2019 to provide information to contractors on the proposed MILCON project with an estimated cost of over $500 million. The project involves constructing a partitioned addition to Dry Dock #1 to create two new docking positions along with fabrication of two new caisson gates and associated site improvements. The scope of work will require marine foundations, precast concrete construction, crane rail fabrication and repair, dredging, utility upgrades and services. The Navy seeks feedback from contractors on the project design during one-on-one breakout sessions at the Industry Day event. The solicitation is anticipated for award in Q2 FY21. Comments on the project can be submitted until November 29, 2019.
Industry Day Flyer
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry Day for FY21 MILCON
P-381 – Multi-Mission Dry Dock #1
Portsmouth Naval Shipyard, Kittery, ME
When: November 13, 2019 from 0800 to 1700
Where: Boston Marriott Newton, Newton, MA
Who: Contractors (general and specialist) with appropriate experience with construction, repair, and/or renovation of large waterfront structures and suppliers of related equipment and materials.
What: NAVFAC invites contractors to learn, ask questions, and provide feedback, both in a group and one-one-one setting, regarding the proposed Military Construction Project (MILCON) located at the Portsmouth Naval Shipyard in Kittery, ME. Naval Facilities Engineering Command (NAVFAC) is currently developing the design of the project for FY21 execution, in support of NAVSEA’s submarine maintenance mission at Dry Dock No. 1.
Project Description: Constructs a partitioned addition to Dry Dock #1 within the super flood basin area to create two new docking positions. The existing dry dock and super flood basin will remain operational throughout construction with the project sequenced to create the northern docking position first, followed closely by the second docking position in front of Dry Dock #1. Scope also includes the fabrication of two new caisson gates, a combined flooding/dewatering pump station, and a utility head end building along with various other supporting site improvements (crane rail, utility distribution/infrastructure).
Project Scope:
Construction methods that will be required as part of this project include:
Deep marine foundations including drilled shafts, marine pile driving Precast concrete construction, including specialty marine concrete and onsite concrete batch plant Construction and repair of ground level crane rail including specialty components Caisson fabrication Dredging and underwater bedrock removal Civil site work including excavations within the tidal zone Mooring hardware, winches, and fender panels Utility distribution modifications
Utility Services that will be expanded, upgraded, or repaired include:
Electrical, water, sanitary sewer, high pressure and compressed air, high pressure steam, and nitrogen
Project Cost Range: $500M+ Anticipated Project Award: Q2 FY21
Industry Day for FY21 MILCON
P-381 – Multi-Mission Dry Dock #1
Portsmouth Naval Shipyard, Kittery, ME
Agenda:
0800 - 0900 Registration
0900 - 0905 General Introductions
0905 - 0930 Opening Remarks
0930 - 1000 Project Introduction
1000 - 1015 Break
1015 - 1130 Project Presentation
1130 - 1200 Question and Answer
1200 - 1300 Break for Lunch
1300 - 1700 Contractor Breakout Sessions (pre-registration recommended)
Contractor Breakout Sessions:
Contractors are invited to sit down with the NAVFAC/Stantec design team on a one-on-one basis in the afternoon to provide feedback on the project.
Sessions will be approximately 30 minutes and will be conducted informally.
Online Comment Submission:
Contractors are invited to submit questions and/or comments via email to Philip Cole at
Philip.j.cole@navy.mil.
The comment period will close 15 days after Industry Day.
All comments and responses will be posted publicly via Fed Biz Opportunity website.
Other Pertinent Information:
P-381 35% drawings were provided with this flyer in Fed Biz Ops to facilitate advanced contractor involvement before Industry Day. 35% drawings will also be available during Industry Day and in the break out rooms.
Registration Info:
RSVP for this event and/or a breakout session by contacting philip.j.cole@navy.mil no later than 4
November 2019.