Industry Day 2 Flyer for FY21 MILCON Follow Up.pdf
PDF 773 KB Posted
- Solicitation number
- N4008520R0021
About this file
This document provides details for an industry day follow up regarding a military construction project to construct a partitioned addition to Dry Dock #1 at the Portsmouth Naval Shipyard in Kittery, Maine. The Naval Facilities Engineering Command is developing designs for the project with an estimated cost of over $500 million and anticipated award in the second or third quarter of fiscal year 2021. The scope of work will require deep marine foundations, precast concrete construction including an onsite batch plant, construction and repair of crane rail, caisson acquisition, dredging and underwater bedrock removal, civil site work including excavations in the tidal zone, mooring hardware, utility modifications to electrical, water, sewer, high pressure air and steam, and nitrogen systems. Contractors are invited to register for virtual one-on-one breakout sessions on June 24-25, 2020 to provide feedback on designs by contacting Brittany Cristelli at the provided email.
Additional documentation from prior industry days has been posted to BetaSAM, including attendee lists, presentations, questions and answers, and draft drawings for support of excavation, dockwall, pump station, utility enclosure and civil features.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry Day #2 Follow Up for FY21 MILCON
P-381 – Multi-Mission Dry Dock #1
Portsmouth Naval Shipyard, Kittery, ME
Naval Facilities Engineering Command (NAVFAC) is currently developing the design of the project for FY21 execution, in support of NAVSEA’s submarine maintenance mission at Dry Dock #1. NAVFAC invites contractors to participate in additional one-on-one breakout sessions with the NAVFAC/Stantec design team to continue discussions and provide feedback on the proposed Military Construction Project (MILCON) located at the Portsmouth Naval Shipyard in Kittery, ME.
When: June 24-25, 2020, time to be determined upon registration.
Where: The 45 minute sessions will be hosted virtually, details to be provided upon registration
Who: Contractors (general and specialist) with appropriate experience with construction, repair, and/or renovation of large waterfront structures and suppliers of related equipment and materials.
Project Description: Constructs a partitioned addition to Dry Dock #1 within the super flood basin area to create two new docking positions. The existing dry dock and super flood basin will remain operational throughout construction with the project sequenced to create the northern docking position first, followed closely by the second docking position in front of Dry Dock #1. Scope also includes combined flooding/dewatering pump station, and a utility head end enclosure along with various other supporting site improvements (crane rail, utility distribution/infrastructure).
Project Scope:
Construction methods that will be required as part of this project include:
Deep marine foundations including drilled shafts and marine pile driving Precast concrete construction, including specialty marine concrete and onsite concrete batch plant Construction and repair of ground level crane rail including specialty components Caisson acquisition Dredging and underwater bedrock removal Civil site work including excavations within the tidal zone Mooring hardware, winches, and fender panels Utility distribution modifications
Utility Services that will be expanded, upgraded, or repaired include:
Electrical, water, sanitary sewer, high pressure and compressed air, high pressure steam, and nitrogen
Project Cost Range: $500M+ Anticipated Project Award: Q2/Q3 FY21
Industry Day #2 Follow Up for FY21 MILCON
P-381 – Multi-Mission Dry Dock #1
Portsmouth Naval Shipyard, Kittery, ME
Registration Information: To register for a breakout session, provide company name, physical address, POC, email address, and telephone number to Brittany Cristelli (Brittany.Cristelli@Navy.mil), Contract Specialist, no later than June 22, 2020.
Post-Webinar Documentation: Pursuant to the Industry Day #2 Webinar held on May 20, 2020, the following documentation has since been posted to BetaSAM.
Industry Day #1 Contractor Attendee List
Industry Day #2 Contractor Attendee List
Industry Day #2 Presentation Brief
Industry Day #2 Question and Answers
Additional P-381 Draft Drawings:
o Support of Excavation o Dockwall o Pump Station o Utility Enclosure o Civil Drawings: Crane Rail o Building 191 o Prison Annex o Henderson Point
Documents can be downloaded from BetaSAM at the provided link.
https://beta.sam.gov/opp/101f4c51a5664b638fe84943f9a4dea9/view mailto:Brittany.Cristelli@Navy.mil https://beta.sam.gov/opp/101f4c51a5664b638fe84943f9a4dea9/view