Amendment 0017.pdf

PDF 68 KB Posted

Attached to
Hurricane Florence Recovery MILCON Package 4
Solicitation number
N4008519R9254
Issued by

About this file

This solicitation and amendment seek proposals for a design-build contract to complete two military construction projects at Marine Corps Base Camp Lejeune in North Carolina. The projects include replacing the Onslow Beach Bridge over the Intracoastal Waterway and rebuilding two railroad trestles over the White Oak River and Queens Creek. Offerors must provide technical approaches, past performance histories, safety plans, technical solutions, project schedules, and small business utilization proposals. The Navy will evaluate non-price factors first and price second, with non-price factors significantly outweighing price. The solicitation issued on October 7, 2019. Proposals are due by July 20, 2020 and award will occur shortly thereafter. The work must be completed within 1,826 calendar days. The NAICS code is 237310 and the size standard is $39.5 million. The magnitude of construction is between $100-250 million.

View the file

Other files

File Type Posted
Amendment 0016.pdf PDF
TFF Package 4 Price Proposal updated 4-14-20.pdf PDF
Queens Creek Bridge - Pre Demo HAZMAT Survey.pdf PDF
Onslow Beach Bridge - Pre Demo HAZMAT Survey.pdf PDF
White Oak Bridge - Pre Demo HAZMAT Survey.pdf PDF
Amendment 0015.pdf PDF
Amendment 0014.pdf PDF
Amendment 0013.pdf PDF
Updated Attachment H.pdf PDF
Amendment 0012.pdf PDF
Site Visit Log.pdf PDF
Amendment 0011.pdf PDF
CADD FILES ONSLOW AND TRESTLES.zip ZIP file
Amendment_0010.pdf PDF
Amendment_0009.pdf PDF
Site Visit Waiver.pdf PDF
Site Visit Waiver.pdf PDF
Amendment_0008 PDF
Attachment I Price Proposal Form.pdf PDF
Amendment 0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
One_Day_Pass_Request.xls XLS spreadsheet
Amendment_0002.pdf PDF
Attachment_C_Con_Des_Exp_Proj_Data__Standard.pdf PDF
Amendment_0001.pdf PDF
Attachment_B_SECNAV_5512.pdf PDF
N4008519R9254.pdf PDF
Attachment_G_Sub_Plan.pdf PDF
Attachment_F_PPQ.pdf PDF
Attachment_C_Con_Des_Exp_Proj_Data__Standard.pdf PDF
Attachment_E_SB_Part_Commit_Strat.pdf PDF
Attachment_H_Proposed_Project_Durations.pdf PDF
Attachment_D_SB_Subcontracting_Record.pdf PDF
Attachment_A_-_PPI_Inquiry_Log.xls XLS spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to update the specifications and revise PPI number 120. The proposal due date remains unchanged.

See SF30 Block 14 Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9254

X 9B. DATED (SEE ITEM 11)

09-Oct-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-May-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9254

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0017

Part 3B Project Program ESR A1010, Add to the end of this section the following:

For permanent steel casings to be left in place, remove steel casing above Mean Low Water (MLW) or provide concrete aesthetic covering on all exposed steel casings above Mean Low Water (MLW). All exposed concrete, including aesthetic covering, shall require corrosion protection as specified. Aesthetic covering service life shall match the service life of the primary structure.

Revise PPI 120 response to read:

Concrete filled steel pipe piles are permitted, however, for sections ABOVE a point 5‐feet below the scour elevation of the 100‐yr storm event is considered 100% sacrificial and not available for permanent strength or capacity. No additional corrosion protection is required of the steel pipe pile shell below this point. The concrete portion of this type of pile will require corrosion protection as specified. See Amendment 0017.

(End of Summary of Changes)