Hurricane Florence Recovery MILCON Package 4
Solicitation number
N4008519R9254
Issued by

About this file

This notice solicits design-build construction services for two military construction projects at Marine Corps Base Camp Lejeune in North Carolina. Project 1387 will construct a movable bridge across the Intracoastal Waterway including new approach roads and demolition of an existing bridge. Project 1505 will replace two railroad trestles totaling 2,560 linear feet. The solicitation is for a firm-fixed-price contract with an anticipated period of performance of 1,826 calendar days from award by July 20, 2020. Evaluation factors will include technical approach, corporate experience, past performance, safety, technical solution, project management, and small business utilization. The solicitation is unrestricted with a magnitude between $100-250 million. The NAICS code is 237310 and small business size standard is $39.5 million.

View the file

Other files

File Type Posted
Amendment 0017.pdf PDF
Amendment 0016.pdf PDF
TFF Package 4 Price Proposal updated 4-14-20.pdf PDF
Queens Creek Bridge - Pre Demo HAZMAT Survey.pdf PDF
Onslow Beach Bridge - Pre Demo HAZMAT Survey.pdf PDF
White Oak Bridge - Pre Demo HAZMAT Survey.pdf PDF
Amendment 0015.pdf PDF
Amendment 0013.pdf PDF
Updated Attachment H.pdf PDF
Amendment 0012.pdf PDF
Site Visit Log.pdf PDF
Amendment 0011.pdf PDF
CADD FILES ONSLOW AND TRESTLES.zip ZIP file
Amendment_0010.pdf PDF
Amendment_0009.pdf PDF
Site Visit Waiver.pdf PDF
Site Visit Waiver.pdf PDF
Amendment_0008 PDF
Attachment I Price Proposal Form.pdf PDF
Amendment 0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
One_Day_Pass_Request.xls XLS spreadsheet
Amendment_0002.pdf PDF
Attachment_C_Con_Des_Exp_Proj_Data__Standard.pdf PDF
Amendment_0001.pdf PDF
Attachment_B_SECNAV_5512.pdf PDF
N4008519R9254.pdf PDF
Attachment_G_Sub_Plan.pdf PDF
Attachment_F_PPQ.pdf PDF
Attachment_C_Con_Des_Exp_Proj_Data__Standard.pdf PDF
Attachment_E_SB_Part_Commit_Strat.pdf PDF
Attachment_H_Proposed_Project_Durations.pdf PDF
Attachment_D_SB_Subcontracting_Record.pdf PDF
Attachment_A_-_PPI_Inquiry_Log.xls XLS spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

N40085

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to respond to Pre-Proposal Inquiries (PPIs). This amendment includes answers to all PPIs received by the Government. The proposal due date remains unchanged.

See SF30 Block 14 Continuation Page.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

NAVFAC MID-ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511-3095

SEE ITEM 6

N4008519R9254

1 2

03/19/2020

10/09/2019

03/19/2020

PART 3A - CHAPTER 6 / ESR G40

G4030 SITE COMMUNICATION AND SECURITY, Fourth paragraph, Delete this paragraph in its entirety and replace with the following:

Provide three (3) parallel runs of 1.25-inch HDPE telecommunications conduit for approximately 9,500 linear feet from telecommunications structure PB21 near building 1659 to the proposed bridge site via Sneads Ferry Road (NC 172) and Onslow Beach Road. Provide two (2) parallel runs of 4-inch HDPE telecommunications conduit from the proposed bridge structure controls room to the final new landside hand hole.

G4030 SITE COMMUNICATION AND SECURIT, Fifth paragraph, delete the last sentence paragraph in its entirety and replace with the following:

Provide two (2) 3-way fabric innerduct in one of the 4-inch conduits under the ICW.

PART 3B - CHAPTER 1

PROJECT DESCRIPTION

2. Delete this paragraph in its entirety and replace with the following:

“Both bridges carry Norfolk Southern (NS) freight traffic and will be repaired in accordance with the latest NS standards. The repaired bridges will follow the existing track alignment and will be reconstructed within the same general footprint. The bridges will be replaced under full rail line closure for a two (2) year period. Closure is limited to actual rail movements only. Norfolk Southern, MCBCL PWD and their maintenance contractor, TNC, will require access to the entire rail line (with exception of Queen’s Creek & White Oak River trestles) throughout the closure for routine maintenance and inspections.”

3. General statement for the design of Project P1505F:

a.White Oak River Trestle Bridge (S882)

iii. Delete this paragraph in its entirety and replace with the following:

“Coordinate routine maintenance and inspections in addition to the closure period with the Military Expeditionary Force (MEF) Military Movement Control Center (MMCC) Mr. R.D. Swink (910-451-4690), Base Public Works Division (PWD) representatives Mr. Jim Kulp /James.kulp@usmc.mil/(910-451-5783, x3233 Office)/(910-545-9196 Cell), and Mr. Barry Rocker/Barry.rocker@usmc.mil/ (910-451-0895 Office)/(910-545-9252 Cell) and Norfolk Southern Railroad (NS) representative Mr. Johnny Gass/Johnny.Gass@nscorp.com”.

b. Queens Creek Trestle Bridge (S880)

iii. Delete this paragraph in its entirety and replace with the following:

Coordinate routine maintenance and inspections in addition to the closure period with the Military Expeditionary Force (MEF) Military Movement Control Center (MMCC) Mr. R.D. Swink (910-451-4690), Base Public Works Division (PWD) representatives Mr. Jim Kulp /James.kulp@usmc.mil/(910-451-5783, SF30 Block 14 Continuation Page mailto:/James.kulp@usmc.mil/(910-451-5783 mailto:Rocker/Barry.rocker@usmc.mil/ mailto:Johnny.Gass@nscorp.com mailto:/James.kulp@usmc.mil/(910-451-5783 x3233 Office)/(910-545-9196 Cell), and Mr. Barry Rocker/Barry.rocker@usmc.mil/ (910-451-0895 Office)/(910-545-9252 Cell) and Norfolk Southern representative Mr. Johnny Gass/Johnny.Gass@nscorp.com.

c. Timber Tie Replacement/track maintenance

i. Delete this paragraph in its entirety and replace with the following:

“Replace timber ties (26,320 ties) and ballast (43,870 tons) for general track maintenance along the 34-mile rail line. Use the following guidance criteria for this work:

1. Replace deteriorated ties as needed. Quantity of tie replacement derivation is based on replacement of every fourth tie throughout the 34-mile rail line. Coordinate timber tie replacement with PWD contacts provided above and as indicated in Section G10.

2. Place ballast as needed.

3. Line, tamp (surface) and regulate all track throughout the 34-mile railroad line”.

mailto:Rocker/Barry.rocker@usmc.mil/ mailto:Johnny.Gass@nscorp.com

SOLICITATION NO. N40085‐19‐R‐9254

PROJECT TITLE/LOCATION: HFRM PACKAGE 4

PREAWARD INQUIRY FORM (TEMPLATE)

Page Para.

2/21/2020 1 2 Factor 5, Section 2 It is our understanding that the railroad will be closed for 2 years, do we need to account for maintaining rail operations within the two year closure? When does the two-year closure start? Is there a coast guard permit required for the trestle, the requirement for a coast guard permit and allowable work windows in the water will drastically cut in the two year time period?

See Amendment 0014 for maintaining operations during closure period. 2 year closure begins based on Contractor's design and construction schedule. A USCG permit is required for the trestles,see “White Oak River and Queen Creek Rail Trestles – Permitting Matrix in the RFP.

2/28/2020 Does NAVFAC have preference for compensatory mitigation for stream and wetland impacts? Are we expected to acquire from Banking Instruments or coordination with DMS? Does NAVFAC have internal banking with approved sites?

The EPA and USACE requires that credits are preferentially purchased from mitigation banks in the same HU as the impact, where available.

2/28/2020

PDF 1451

PDF 279

Applicable Conditions

Natural Constraints

There is mention in the Onslow Beach Bridge Replacement CatEx (Enclosure 3: Applicable Conditions; page 1451 of RFP PDF document) :

o“There are delineated, jurisdictional wetland features within the project area. Coastal wetlands exist along the waterway. Impacts to coastal wetlands are prohibited by NCDCM. Any widening of the approach to the bridge will require additional delineations.”

There is also mention in the (Section 3.1.1 Natural Constraints; page 279 of RFP PDF document):

o“There are existing wetlands adjacent to the project site; wetland delineations are required before the start of construction.”

We understand if Delineations are needed, but is there clarification on the conflicting information and will we have access to any existing delineations Spatial Data and accompanying documentation including Wetland Determination Data Forms and any USACE (Preliminary or Approved) Jurisdiction Determinations to reference in the permit app or will we be required to go through the JD process or request that as part of the IP application?

No previous delineations exist for this area. A/E-2 will be required to delineated wetlands and obtain JD's where applicable.

2/28/2020

PDF 417 Natural Constraints

There is mention in Part 3b – Chapter 3 – Page 1 (3.1.1 Natural Constraints (pg 417 of the RFP pdf document):

o“There are existing wetlands adjacent to both bridge sites; wetland delineations are required before the start of construction.”

We understand that delineations are needed, but is there clarification on the requirement / preference for any USACE (Preliminary or Approved) Jurisdiction Determinations to reference in the permit application or will we be required to go through the JD process or request that as part of the IP application?

Preference is to obtain a Preliminary Jurisidctional Determination (JPD) as a part of the application process

152 2/28/2020 Will NAVFAC consider allowing causeway for some portion of the White Oak River trestle? No. 14

PDF

Permit Matrix Please define "navigable opening" as it pertains to the USCG permit requirements and timeframes in the Permit Matrix Part 6A Onslow Beach and Part 6B White Oak River Bridges “If navigable opening is modified, USCG may require a navigation impact report (NIR). Allow a 12-24-month duration for Bridge Permit and NIR.”

Navigable opening is the horizontal and vertical clearances available for use by vessels. Navigable opening is a major component of any bridge permit process, which is regulated by the USCG.

2/28/2020 Please confirm any restrictions on crane boom height that may interfere with Camp LeJeune air operations and aircraft travel.

Crane restrictions & stipulations are covered under guidance provided by MCBCL - Tall Structures Working Group (TSWG). Please reference Amendment (13) for additional information.

157 2/28/2020 2-3

PDF 373-374

11th Paragraph (pdf 373) Option Item No. 1 and No. 2

Direct bury cables in conduit or concrete encased duct bank? Direct bore cable plus spare

2/28/2020 2-3

PDF 373-374

11th Paragraph (pdf 373) Option Item No. 1 and No. 2

How many circuits (1 or 2)? The bore is specified to provide redundant cables which is definitely appropriate due to the repair time for a cable fault. However, normal underground has a significant repair time as well. The bridge may have generation but all power to the beach would be out for a significant period if there was a cable fault from where it dips up at 172 (Sneed's Ferry Road).

2 circuits underneath ICW. Both must be energized. Everywhere else, whether overhead or underground, e.g. Option 1 or 2, shall be 1 circuit.

2/28/2020 Power Distribution: What is the purpose of primary metering? Does this need to be maintained in the rebuild? This is especially important if it is converted to buried power.

Maintain primary metering.

2/28/2020 1

1.3.1.1 F2020 1.1 F2020 1.1

What are the requirements for the Private Qualified Person? Provide in accordance with the RFP

2/28/2020 8 H1510 Superstructure RFP Part 3A, Chapter 6 / ESR H15 - Page 8, Superstructure states "The roadway deck shall be open steel grid deck-type system, hot dip galvanized. Provide a solid deck over the machinery room and bascule pier when in the closed position." While on the site visit we noted the roadway deck grid surface was very similar to the sidewalk surface. It is possible that the base may use the roadway for foot traffic including the open grating surface. Please confirm foot traffic on the roadway open grating surface does not have to be considered.

While there will be foot traffic on the bridge deck, foot traffic is not the governing criteria for deck material.

2/28/2020 2 6 Engineering Systems

Requirements The Table of Contents list in 6. Engineering Systems Requirements a Section F10, Special Construction. This Section is not included in the RFP. Should it have been included or should the noted Section be removed from the Table of Contents?

Section F 10 is not used.

2/28/2020 15 H1060 1.1.5 The RFP states that at-grade crossings within the limits of track replacement are to be replaced. Are at-grade crossings within the limits of tie replacement to be left as-is?

The general track maintenance and tie replacement is for the open track areas only and does not include paved grade crossings. Open track gravel grade crossings are to be included in the track maintenance/tie replacements. The H1060

1.1.5 requirement will come in to play if your approach track work to a new bridge affects any type of existing grade crossing. 14

Posted on Amend No.

REFERENCE

Question No. QUESTION GOVERNMENT RESPONSEDate Received

July 2011

PREAWARD INQUIRY FORM (TEMPLATE)

Page Para.

Posted on Amend No.

REFERENCE

Question No. QUESTION GOVERNMENT RESPONSEDate Received

2/28/2020 3 ESR A10 The first paragraph of the section entitled A1010 Standard Foundations states “Treated timber piles shall be used for the foundation of the fender system.” Given the RFP requirement for a 75-year design life, would NAVFAC allow the use of precast prestressed concrete piling in lieu of treated timber? And/or would NAVFAC allow the use of alternative composite material solutions which offer a longer service life than timber.

Treated timber piles only.

3/4/2020 2 1 The pavement design must be for 25 years and the design parameters are included in G2010. In Addendum 11, the response to Question No. 100 noted that "The military vehicles in Part 6A are in addition to the truck percentages provided"; however, the response did not provide the breakdown of truck volume percentage for TTST, Dual and military vehicles. Please provide the desired breakdown percentages for these vehicles to ensure the design meets the 25-year life.

Please use the following percentages: TTST 15%, Duals 10%, Military 15%.

3/4/2020 27 1 Based on our experience working on MCB Camp Lejeune, we expect that creosote timbers from the rail trestle project will require testing and manifesting for proper disposal. Due to the location of the nearby disposal facilities would it be possible to have these timbers weighed and manifested from MCAS Cherry Point or another approved landfill site as a means of providing a cost savings to the Navy? Trucking this material to Lejeune for manifest and weighing is cost prohibitive

Dispose of hazardous creosote timbers in accordance with EPA regulations at an approved off-installation facility.

3/4/2020 27 1 The referenced RFP section indicates that hazardous waste should not be brought onto installation property. The timbers will require testing to determine if they are hazardous or not, and if they are, will we be able to bring them aboard the installation for weighing based on the stipulation on page 197

No. Dispose of hazardous creosote timbers in accordance with EPA regulations at an approved off-installation facility.

3/4/2020 420 of 2388 1 Does the Governments ROW agreements at White Oak River and Queens Creek provide access for the contractor to use that land for laydown. Specifically, the field and access road currently for sale to the east of the White Oak Trestle and the land adjacent to both sides of the Delgrade–Swansboro Road crossing on the bridge side of that roadway crossing `

Design-builder must restrict operations to government-owned property as shown in Part 6B attachments.

3/4/2020 169 of 2388 3.1.1.4 Can Onslow Beach Rd from approximately station 40+00 to 50+00 be closed for a limited amount of time for the construction of Ocean Dr and Onslow Beach Rd. intersection?

Maintain at least one lane traffic at all times

3/4/2020 5

PDF 376-377

Paragraph 5/PG 376 Paragraph 6/PG 377

Is it the intent for Charter to provide CATV to the Control House and other service connections along Ocean Drive?

Has NAVFAC communicated with Charter in regards to their relocation work within the project limits?

Provide CATV to the Control House. In the event Charter's existing cabling requires relocation, they can utilize the new parallel telecomunications conduit to be bored underneath the Intracoastal Waterway (ICW) and the new underground conduit along Onslow Beach Road. A/E-2 shall coordinate with Charter by contacting Nick Brown at 910-803-0618 or Marlon.Brown@charter.com and MCIEAST-MCB Camp Lejeune G6 Telecommunications Support Division Jeffrey Henry jeffrey.d.henry@usmc.mil 910-450-7693 or Steve Daigle steven.daigle@usmc.mil 910-451-9439. See Amendment 0014 for details 14

3/4/2020 RFP

Part 3B - Chapter 6 / ESR H10 Page 6

H1070 RR Track Tie Maintenance - First paragraph

Will the team's be allowed to perform an existing track inspection prior to the price proposal submission since an existing track maintenance report is not available?

No

3/4/2020 RFP

Part 3B - Chapter 1 -

Paragraph 3.c. - Timber Tie Replacement/track maintenance

The RFP states to "replace deteriorated ties as needed". Is the Designer of Record, NAVFAC, or Norfolk Southern responsible for the inspection of the ties to be replaced?

Designer of Record

3/4/2020 RFP

Part 3B - Chapter 1 -

Paragraph 3.c. - Timber Tie Replacement/track maintenance

The RFP states to "replace deteriorated ties as needed". Is the Designer of Record, NAVFAC, or Norfolk Southern responsible for the final determination of the ties to be replaced?

See Amendment 0014

3/4/2020 RFP

Part 3B - Chapter 6 / ESR A10 - Page 5

2nd Paragraph The RFP states, "Piles shall be precast prestressed concrete…" Would reinforced, cast-in-place piles be allowable for the trestle bridges if the casing is considered to be sacrificial? If allowed, would the sacrificial casing be allowed to be left in place up to bottom of pile cap?

Yes. The design documents must clearly demonstrate the casing is sacrificial and not needed for pile support capacity.

The casing shall not pose a detrimental affect to the concrete pile or cap interface if it corrodes. The concrete portion of this type of pile will require corrosion protection as specified.

3/4/2020 RFP

Part 3A - Chapter 2

2nd Paragraph RFP requires compliance with UFC 1-200-02 High Performance and Sustainable Building Requirements. The Control House is less than 10,000 sf, so the scope of the UFC is limited to the “UFC requirements relevant to the scope of work of the project/work, as determined by the Project Delivery Team as early as possible during the project process.” Since required HVAC and plumbing systems have been specified in the RFP, please confirm a life cycle cost analysis to select systems and solar hot water systems are not required due to the small size of the project. Please state the UFC requirements in UFC 2-200-02 that are relevant to this project.

Life Cycle Cost Analysis (LCCA) is not required for the Control HVAC system.

3/4/2020 RFP

Part 3A - Chapter 6 / ESR D20 - Page 2

3rd Paragraph The RFP requires the offeror to determine if a pump pressure booster system will be required. Please provide the base flow/pressure information for the existing waterline that will service the control house to facilitate this determination.

DOR to determine requirements in accordance with the RFP.

3/4/2020 RFP

Part 6A, Attachment 3

1st Paragraph Please provide any and all existing utility information (as-built information) for all underground and aerial utilities and the septic tank and drain field.

No additional information available.

3/4/2020 RFP

Part 6A, Attachment 5

Sheet V-105

On the topographic survey Sheet V-105, there is an existing water logger device attached to the wood access pier near the bank on the each side of the ICW that will be demolished as part of this project. Please identify the owner of this device and provide direction on the disposition of this device (i.e., dispose, salvage and reinstall, etc.). If the device is to be reinstalled, please provide requirements for the reinstallation.

Salvage and deliver to the Contracting Officer.

3/4/2020 RFP

Part 3A - Chapter 6 / ESR G40 - Page 4

1st Paragraph Please identify any specific requirements for the permanent lighting system that will make it loggerhead sea turtle friendly.

DOR to determine

PREAWARD INQUIRY FORM (TEMPLATE)

Page Para.

Posted on Amend No.

REFERENCE

Question No. QUESTION GOVERNMENT RESPONSEDate Received

3/12/2020 1457-1458 & 2206-

Our research on the In-Water Work Moratorium indicates that there are no federally protected fish species according to NOAA and Fish & Wildlife at Onslow Beach, White Oak River and Queen Creek. North Carolina Marine Fisheries states that White Oak River is an Anadromous Fish habitat subject to April 1 to Sept 30 Moratorium per 2015 North Carolina Coastal Habitat Protection Plan. A. Our position is there are no work Moratoriums at Queen Creek and Onslow Bridge.

Please confirm that there will be no In-Water Work Moratorium for the Queen Creek location and Onslow Beach location. B. There is no federal agency documentation that we could find with a Moratorium from Jan 1 to Sept 30 for White Oak River. Please confirm that the White Oak River In-Water Work Moratorium is April 1 to Sept 30. C. Will the In- Water Moratorium apply to wetlands that are inundated with water due to high tide, flooding, or any other reason? D. If the In-Water Moratorium is firm to Jan 1 to Sept 30 regardless of the presence of threatened and endangered species will the project schedule be extended and the Design to Budget Package 4 Total be increased?

The in-water work moratoria stated in the RFP results from a combination of protections for the federally endangered Atlantic sturgeon (regulated by National Marine Fisheries and known to occur in the AIWW, White Oak River, and Queens Creek), Anadromous Fish Spawning Areas (AFSA), and both Primary (PNA) and Secondary Nursery Areas (SNA). In-water work moratoria described in the RFP is based on the February 15 – September 30 in-water work moratorium for PNA/SNA, February 15 – June 30 in-water work moratorium for AFSA, and the February 1 – June 30 in-water work moratorium for sturgeon. The January 1 start date has been requested by NMF for sturgeon protection on recent projects in adjacent waters with the same or similar protected resources, resulting in the RFP stating January 1 – September 30 for in-water work moratoria. Contractor/Bidder should be aware that these in-water work moratoria can be required by resource agencies when the protected species is known from a recorded occurrence in the area, or when suitable habitat for the species is present. NAVFAC nor Camp Lejeune determines the applicable in-water work moratoria, but dates are provided in the RFP for the Bidder’s information. The RFP states that the resource agencies “may alter these dates based on project design specifics on a case-by-case basis” and that the “contractor is responsible for confirming and adhering to in-water work moratoria due to protected species”. 14

3/12/2020 305 and 997 of 2388 6 A10 and H10 1.2.1.1 These paragraphs list one of the specifications that the bridge foundation systems should be in accordance with as NCDPT Standard Specifications for Roads and Bridges. Within those specifications Section 450 Piles notes in Paragraph 450-3(D)(1) the following, "When noted in the plans or predrilling in water or wetlands, use temporary steel casings that meet Sub-article 450-3(E)(1), except use steel casings with inside diameters no more than 2 inches larger than predrilling diameters. Use temporary casing from at least 2 feet above the static water elevation of the ground line, whichever is higher, to at least 5 feet below the ground or mud line. More than 5 feet embedment may be necessary if temporary casings are not stable or predrilling or spudding disturbs material outside casings. Is this requirement applicable to the water work on this project?

Specific design and construction decisions are the purview of the bidder. In making those decisions bidder shall conform to the criteria currently contained in the RFP with Amendments.

3/16/2020 Amendment 0007

Due to growing concerns regarding the spread of Coronavirus (COVID-19) and current travel restrictions, will NAVFAC consider postponing the Phase II Non-Cost/Price Proposal due date?

Bid per the RFP

3/17/2020 PDF Page 380 of

2388, Part 3A 2nd to last bullet on bottom of page Is the bascule span structural steel painted and metalized? Yes or no. See responses to PPIs 44, 76 and 217.

3/17/2020 The following modification to the contract language is requested for consideration due to the significant market fluctations as a result of current world events having unknown impacts on future market prices in conjuntion with extensive agency review timeframes involved with coordination of multiple permit applications. Please consider modified contract language to include a Producer Price Index (PPI) that will add or subtract payments based on the amount of monies earned by the contractor in a particular month. The PPI will be determined by the United States Department of Labor, Bureau of Labor Statistics for the category of “Highway, Street, and Bridge Construction.” The baseline PPI will be the month price proposals are submitted, April 2020. This PPI adjustment will be in lieu any other price adjustments, if referenced in the contract, but will be based on all items earned and billed in a given month rather th l t d it f k

Bid per the RFP

3/17/2020 Is there a process where the contractor can secure an exemption from sales and use taxes for itself and its subcontractors in connection with this project? If so, please provide guidance on this process.

There is no exemption process in North Carolina.

232 3/18/2020 With the current uncertainty with COVID-19, how do you want us to address potential escalation and schedule impacts in our bid?

Bid per the RFP

Amendment 0014
Amendment 0014
Continuation Page
Amendment 0014 PPIs

Amendment 0014 PPIs