Amendment_0002_-_P680_CH53K_Cargo_Phase_II.pdf

PDF 468 KB Posted

Attached to
P680 CH-53K CARGO LOADING TOWER
Solicitation number
N4008519R9102
Issued by

About this file

This amendment to a solicitation and related federal contract opportunity provide details for a design-build construction project. The project involves constructing a high-bay facility at Marine Corps Air Station New River in North Carolina to house an operations trainer supporting CH-53K helicopter pilot and crew chief training. The 9,795 square foot facility includes a high-bay area for an aircraft frame and pallet storage, as well as ancillary office, classroom, and support spaces. Two advanced aircrew training devices are also included. The estimated value is between $5-10 million.

The amendment initiates Phase II of the solicitation process and sets the new proposal due date of September 12, 2019. It provides instructions for submitting price and non-price proposals, including required forms and evaluation criteria. The federal contract opportunity further describes the project and advises that the solicitation will be issued on May 1, 2019 via the Navy Electronic Commerce Online website. Questions are to be directed to the specified contracting officer by specified deadlines.

Amendment_0002_-_P680_CH53K_Cargo_Phase_II.pdf

View the file

Other files

File Type Posted
Amendment 0011 - Extension.pdf PDF
Amendment 0010 - Wage Determination.pdf PDF
P680_PPI_Log_r3.pdf PDF
Amendment_0009.pdf PDF
CS101.pdf PDF
Amendment_0008.pdf PDF
Fitness_Equip.pdf PDF
Attachment_G_-_Price_Proposal_Form_Rev2.docx DOCX document
P680_PPI_LOG_r2.pdf PDF
P680_Room_Req_Trainer_Room.pdf PDF
Amendment_0007.pdf PDF
Attach_PPI_40.pdf PDF
Amendment_0006.pdf PDF
P680_PPI_LOG_r1.pdf PDF
Attach_PPI_21.pdf PDF
Amendment_0005.pdf PDF
P680_PPI_LOG.pdf PDF
PPI_02b_-_Pages_from_P705_-_IFC_Civil_Drawings_-_032513-2.pdf PDF
Amendment_0004-SignInSheet_and_PPIs.pdf PDF
PPI_02a_-_P705-Lift_Station_Calcs.pdf PDF
Attachment_H_-_MCAS_New_River_Site_Visit.xlsx XLSX spreadsheet
Attachment_I_-_Directions_Map_MCAS_New_River.pdf PDF
Amendment_0003_-_Site_Visit.pdf PDF
Attachment_E_-_Small_Business_Subcontracting_Record.docx DOCX document
Attachment_G_-_Price_Proposal_Form.docx DOCX document
Attachment_F_-_Small_Business_Participation_and_Commitment_Strategy.docx DOCX document
Amendment_0001.pdf PDF
Attachment_B_-_SECNAV_5512.pdf PDF
Attachment_C_-_Construction_and_Design_Exp._Project_Data_Sheet.docx DOCX document
Attachment_A_-_Pre-Proposal_Inquiry_(PPI)_Form.xlsx XLSX spreadsheet
P680_CH-53K_CARGO_LOAD_TWR.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5485063

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to issue Phase II documents, only to those offerors that w ere selected to participate in Phase II of this solicitation.

Phase II proposals are due on Thursday, September 12, 2019 at 2:00 p.m. (EDT).

See Section SF 30 Block 14 Continuation Page The follow ing documents have been included in this amendment:

P680 CH53K Cargo Loading Tow er Final RFP (Large File, provided via AMRDEC to selected Phase II offerors) Wage Determination, General Decision Number: NC20190038 01/04/2019 Attachment E - Small Business Subcontracting Record Template Attachment F - Small Business Participation and Commitment Strategy Attachment G - Price Proposal Form *Site Visit Information w ill be provided via Amendment

1. CONTRACT ID CODE PAGE OF PAGES

1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008519R9102

X 9B. DATED (SEE ITEM 11)

10-May-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Aug-2019

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9102

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

THIS AMENDMENT IS ISSUED TO INITATE PHASE II. ONLY OFFERORS SELECTED SHALL

SUBMIT PROPOSALS FOR PHASE II.

PROPOSAL DUE DATE: Thursday, September 12, 2019 at 2:00 p.m. (EDT)

PROPOSAL SUBMISSION INSTRUCTIONS: SEE PROPOSAL SUBMISSION INSTRUCTIONS INCLUDED

IN THE ORIGINAL SOLICITATION. The evaluation factors, including both non-price/technical and price submittal requirements are available in the original Request for Proposal document (and any applicable amendments) and have not been reproduced in this amendment.

(See N40085-19-R-9102 for Phase II Evaluation Factors and Submittal Requirements).

PRICE FACTOR submission instructions begin on page 6 (include all information in the “Additional information to be submitted with Price Proposal Package (PHASE II).

Attachment G - Price Proposal Form is included in this amendment notice.

NON-PRICE FACTORS submission instructions begin on Page 16 (Factors 5-7).

Proposals may be sent via Express Mail Carriers or Hand-Delivered to the following address:

(MAILED PROPOSALS ARE PREFERRED DUE TO RECENT SECURITY CHANGES

REQUIRED TO GAIN BASE ACCESS)

NAVFAC MIDLANT

9324 Virginia Avenue, Building Z-140, Room 225 Norfolk, Virginia 23511-3624 Attn: Deanna Ward, Contract Specialist – ACQ21

Important note: Contractors are not permitted to work in Room 225 prior to delivery while finalizing the proposal.

Once the proposal is formally delivered, the contractor’s business is considered complete and the contractor is expected to promptly depart Room 225.

See original solicitation for instructions regarding new access using the SEC-NAV 5512. ALL REQUESTS FOR HAND DELIVERING PROPOSALS (i.e. Form SEC-NAV 5512) MUST BE RECEIVED NO LATER THAN Thursday, August 29, 2019 by 2PM EST.

PRE PROPOSAL INQUIRIES (PPIs): See original solicitation. PPI Form is within the additional documents. PPI cutoff is Tuesday, September 3, 2019 by 2PM EDT.

SITE VISIT INFORMATION: The site visit details will be provided via amendment.

WAGE DETERMINATION

General Decision Number: NC20190038 01/04/2019

Superseded General Decision Number: NC20180038

State: North Carolina

Construction Type: Building

County: Onslow County in North Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019

* IRON0848-005 02/01/2018

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 25.00 13.50

PLUM0421-003 07/01/2017

Rates Fringes

PIPEFITTER.......................$ 28.65 10.45

SUNC2011-019 08/24/2011

Rates Fringes

BRICKLAYER.......................$ 19.00 0.00

CARPENTER (Drywall Hanging Only)............................$ 13.83 0.00

CARPENTER (Form Work Only).......$ 13.38 1.80

CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.39 4.26

CEMENT MASON/CONCRETE FINISHER...$ 15.80 0.00

ELECTRICIAN......................$ 20.64 6.68

HVAC MECHANIC (HVAC Duct Installation Only)...............$ 17.37 1.82

LABORER: Common or General......$ 11.13 0.32

LABORER: Landscape & Irrigation.......................$ 9.13 0.28

LABORER: Pipelayer..............$ 13.35 2.80

LABORER: Mason Tender-Brick/Cement/Concrete.....$ 12.00 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 18.47 2.41

OPERATOR: Bulldozer.............$ 16.00 1.87

OPERATOR: Crane.................$ 19.77 4.48

OPERATOR: Forklift..............$ 13.86 0.00

OPERATOR: Grader/Blade..........$ 15.72 1.49

OPERATOR: Loader................$ 16.17 0.25

PAINTER: Brush, Roller and Spray............................$ 12.35 0.00

PLUMBER..........................$ 18.48 3.93

ROOFER...........................$ 11.75 1.06

SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 15.81 1.40

TRUCK DRIVER.....................$ 13.38 1.48

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

(End of Summary of Changes)

END OF GENERAL DECISION

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.