This document package includes construction drawings and a federal contract opportunity. The construction drawings depict the demolition of above ground storage tanks and pump houses at the Chesapeake Beach Detachment in Maryland. Key details include sawcutting joints between existing and demolition concrete, maintaining access, installing per manufacturer specifications, and restoring disturbed ground with sod.

The related federal contract opportunity is a multiple award indefinite delivery indefinite quantity construction contract for new construction, repair, and renovation projects at various facilities within the Naval Facilities Engineering Command Washington area of responsibility, including Washington D.C., Maryland and Virginia. Design-build and design-bid-build projects are included. The estimated value is $49M over five years. The solicitation number is N4008020R0007 and was issued by the Department of the Navy Naval Facilities Engineering Command. The response due date is not provided.

View the file

Other files

File Type Posted
AMENDMENT 0006.pdf PDF
Site Visit Sheet-13JAN2020.pdf PDF
AMEND 0005-ATTACH #1-Masonry and Paint Spec - Div 04 and 09.pdf PDF
AMEND 0005-ATTACH#3-Revised Price Schedule dated 9 January 2020.docx DOCX document
AMEND 0005-ATTACH #2-Seeding Specification.pdf PDF
AMENDMENT 0005.pdf PDF
AMENDMENT 0004.pdf PDF
AMENDMENT 0003.pdf PDF
17 December Site Visit Attendance Sheet.pdf PDF
Revised Past Performance Questionnaire.docx DOCX document
PC170005.jpg JPG image
PC170001.jpg JPG image
HUBZONE MACC AMENDMENT 0002.pdf PDF
PC170007.jpg JPG image
PC170006.jpg JPG image
PC170004.jpg JPG image
PC170002.jpg JPG image
PC170003.jpg JPG image
AMENDMENT 0001.pdf PDF
CBD Price Schedule dated 3 December 2019.docx DOCX document
CBD CATEX.pdf PDF
Past Performance Questionnaire.docx DOCX document
CBD Basis of Design Final.pdf PDF
CBD SPECS - FINAL.pdf PDF
NRL SECNAV_5512-1.pdf PDF
CONSTRUCTION EXPERIENCE PROJECT DATA SHEET.docx DOCX document
SOLICITATION N4008020R0007 HUBZONE MACC.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D

C

B

A

1 2 3 4

DEMO ABOVE GROUND STORAGE TANKS AND PUMP HOUSES

lEGEND

CD SHEET NOTE

� EXTERIOR ELEVATION MARK

@---- ___j SECTION MARK

I

I DETAIUENLARGED PLAN BUBBLE

I I

L _ _J

FIRST LEVEL FIN. FL.

0'-0" BENCHMARK

SF

ROOMNAME

IRM#I

EW-

LOO-

FINISH FLOOR REFERENCE

NORTH ARROW

REVISION CLOUD REFERENCE

BREAK LINE

SILT FENCE

CONTOUR LINE

ROOM REFERENCE

PHOTO REFERENCE

EXISTING WATER LINE

LIMIT OF DISTURBANCE

CHESAPEAKE BEACH DETACHMENT

GENERAl NOTES

1. INFORMATION IN DRAWINGS REGARDING EXISTING CONDITIONS HAS BEEN

OBTAINED FROM AVAILABLE BUILDING DRAWINGS AND/OR GENERAL FIELD

OBSERVATIONS AND MAY NOT INDICATE ACTUAL EXISTING CONDITIONS IN

DETAIL OR DIMENSION. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING

THE ACTUAL EXISTING CONDITIONS INCLUDING LOCATION OF EXISTING

UTILITIES WITH GROUND PENETRATING RADAR TO PHYSICALLY VERIFY THE

LOCATION AND ELEVATION OF THE EXISTING UTILITIES AND MARK THE SURFACE

OF THE GROUND WHERE EXISTING UNDERGROUND UTILITIES ARE DISCOVERED

PRIOR TO PERFORMANCE OF ANY WORK. SHOULD CONDITIONS BE DISCOVERED

THAT PREVENT EXECUTION OF THE NEW WORK AS INDICATED, THE CONTRACT

OFFICER SHALL IMMEDIATELY BE NOTIFIED IN WRITING AND AWAIT DIRECTION

BEFORE PROCEEDING WITH THE WORK.

2. SOIL POTENTIALLY CONTAINS POL (PETROLEUM OIL LUBRICANTS) AND

CHEMICALS ASSOCIATED WITH THE FIRE SUPPRESSANT AFFF TO INCLUDE PFAS.

INCLUDE IN ACTIVITY HAZARD ANALYSIS AND ACCIDENT PREVENTION PLAN. NO

SOILS ARE TO BE TAKEN OFF-SITE.

CONTRACTOR TO MAKE ACCOMMODATIONS TO AVOID SKIN CONTACT WITH

SOIL, ESPECIALLY WHEN MIXED WITH WATER. WHEN WORK IS FINISHED, RINSE

OFF EQUIPMENT AND ANY APPLICABLE PPE TO AVOID EXPOSURE.

3. THE CONTRACTOR SHALL COORDINATE ALL WORK SHOWN IN THE CONTRACT

DOCUMENT SET. THE CONTRACTOR SHALL PROVIDE A COMPLETE SET OF

CONTRACT DOCUMENTS TO ALL SUBCONTRACTORS AND RELATED PARTIES.

4. CONTRACTOR SHALL PROVIDE SAFETY FENCING AROUND ASPECTS OF WORK TO

MAINTAIN A SAFE WORK SITE.

5. CONTRACTOR SHALL PROVIDE POSITIVE DRAINAGE IN FINAL PROPOSED

CONDITION, AND PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS TO

PROTECT THE PROJECT SITE FROM EROSION, PONDING WATER, AND FLOODING.

6. DISPOSE OF ALL RUBBISH OFFSITE.

7. THE CONTRACTOR IS NOT TO TAKE ANY PHOTOGRAPHS. ONLY NRL OR NAVFAC

EMPLOYEES WITH A CAMERA PASS MAY TAKE PHOTOS.

8. ANY DAMAGE OR RUTTING TO THE GROUND MUST BE REPAIRED. ANY GROUND

DISTURBED AREAS MUST BE RESTORED WITH SOD. RESTORE ALL OTHER AREAS

WITHIN LIMITS OF DISTURBANCE TO ORIGINAL SITE CONDITIONS. ALL BARE SOIL

AT THE CONCLUSION OF WORK MUST BE PROVIDED SOD

9. ALL EXISTING UTILITIES MUST BE VERIFIED BY THE CONTRACTOR PRIOR TO

CONSTRUCTION, AND MARKED. CONTRACTOR TO CONTACT CONSTRUCTION

MANAGER IMMEDIATELY IF ANY DAMAGE OCCURS TO EXISTING UTILITIES.

10. THE LOCATION(S) OF THE CONTRACTOR'S MATERIAL LAYDOWN, STORAGE, AND

STAGING AREA(S) MUST BE COODINATED WITH THE CONTRACTING OFFICER.

11. SAWCUT ALL JOINTS BETWEEN EXISTING CONCRETE TO REMAIN AND CONCRETE

PROPOSED TO BE DEMOLISHED.

12.MAINTAIN CLEAR, COMPLETE, AND SAFE ACCESS FOR GOVERNMENT

PERSONNEL AND CIVILIANS TO ALL BUILDINGS WITHIN OR ADJACENT TO THE

PROJECT SITE.

13.ALL MATERIALS AND SYSTEMS SHALL BE INSTALLED PER MANUFACTURER'S

SPECIFICATIONS AND ALL CONSTRUCTION SHALL BE OF INDUSTRY STANDARD OR

BETTER.

PEAKE

6114D CHESAPEAKE

BAY ,31 ROAD

(BC302l

VICINITY MAP

SCALE: NOT TO SCALE

lOCATION MAP

SCALE: NOT TO SCALE

olU � CH ES A�EA!<E

BAV �37

ff□-,fo (BC29)

DRAWING INDEX

DRAWING NO. DRAWING DESCRIPTION

G-101 TITLE SHEET

C-101 EXISTING CONDITIONS PLAN

C-102 EXISTING CONDITIONS AND DEMO PLAN FOR FUEL TANK AREA

C-103 EXISTING CONDITIONS AND DEMO PLAN FOR SPRINKLER WASTE WATER TANK AREA

C-104 PROPOSED CONDITIONS PLAN FOR FUEL TANK AREA

C-105 PROPOSED CONDITIONS PLAN FOR SPRINKLER WASTE WATER TANK AREA

C-106 REFERENCE DRAWING FOR CONCRETE STRUCTURES AT FUEL TANK

C-107 REFERENCE DRAWING FOR FUEL TANK ELEVATIONS

A-101 ARCHITECTURAL SITE PLAN

M-101 1000 GALLON DOUBLE WALL GASOLINE TANK

M-102 REFERENCE DRAWING FOR PIPING DESIGN AT FUEL TANKS

M-103 REF DRAWING FOR SPRINKLER TANK MECHANICAL PUMP HOUSE

ES101 SITE ELECTRIC PLAN

ED601 ELECTRICAL RISER DIAGRAM WITH DEMOLITION

E-601 ELECTRICAL RISER DIAGRAM NEW WORK

E-101 ENLARGED ELECTRICAL DIAGRAMS

APPROVED

FORCOMMANDER�VFAC

ACTIVITY

SATlSFACTORYTO DATE

DES DRW

SEAL

Alf.INFO

CHK

PM/DM John Jones

BRANCH MANAGER

CHIEF ENG/ARCH

FIRE PROTECTION

" (.) ":l! Cl !" :::, � z � 0 0 <( " z " I- ;, ,; C!) <(a: z w z "'w C, z--I � en i� :::J -u Cl �z

�::i: z ::i:

C!)

z a:w w z

C!)

zw enw

� I- � ...J r-- zw (.) wI

I- ii' "- LL « 0 _J fb I- C z <( "'w > "

0:

� <( �c.. z ::J w "'" �

Cl

I-� w � (!J w <( � a: w

�0(1) � 1-W I (/) (/)

�o ::>I Oc..

a:� (!J ::> w e..

>o

1-0z r5 CD<(

Cl) �o� ��z � w � <( Cl w

III . .

\!:! Cl i1i en en w

I

SCALE N.T.S.

EPROJECT NO.: 1617903

CONSTR. CONTR. NO.

NAVFAC DRAWING NO.

13110968

SHEET 1 OF 16

G-101

N/A

I-w w I en w I- I-

DRAWFORM REVISION: 10 MARCH 2009

D

C

B

A john.c.jones Typewritten Text

AND PAVING FABRIC

G-101
C-101 Existing Conditions (1)
C-102 Exist FUEL
C-103 Exist WW (1)
C-104 Proposed FUEL
C-105 PROP Cond WW (1)
C-106 Existing Information 1
C-107 EXISTING INFO 2
A-101
M-101
M-102 EXISTING INFO 3
M-103 EXISTING INFO 4
ES101
ED601
E-601
E-101

2019-08-07T13:54:45-0400

2019-08-07T13:55:16-0400

2019-08-07T13:55:25-0400

2019-08-07T13:55:29-0400

2019-08-07T13:55:30-0400

2019-08-07T13:55:31-0400

2019-08-07T13:55:32-0400

2019-08-07T13:55:38-0400

2019-08-07T13:55:46-0400

2019-08-07T13:55:51-0400

2019-08-07T13:55:58-0400

2019-08-07T13:56:04-0400

2019-08-07T13:56:09-0400

2019-08-07T13:56:10-0400

2019-08-07T13:56:15-0400

2019-08-07T13:56:22-0400

2019-08-08T10:52:02-0400

2019-08-08T10:52:17-0400

2019-08-08T10:52:18-0400

2019-08-08T10:52:20-0400

2019-08-08T10:52:21-0400

2019-08-08T10:52:22-0400

2019-08-08T10:52:23-0400

2019-08-08T10:52:24-0400

2019-08-08T10:52:26-0400

2019-08-08T10:52:27-0400

2019-08-08T10:52:28-0400

2019-08-08T10:52:29-0400

2019-08-08T10:52:31-0400

2019-08-08T10:52:32-0400

2019-08-08T10:52:33-0400

2019-08-08T10:52:34-0400

2019-08-08T10:52:57-0400

2019-08-08T10:53:32-0400

2019-08-08T10:53:41-0400

2019-08-08T10:53:42-0400

2019-08-08T10:53:49-0400

2019-08-08T10:53:50-0400

2019-08-08T10:53:51-0400

2019-08-08T10:53:58-0400

2019-08-08T10:54:11-0400

2019-08-08T10:54:20-0400

2019-08-08T10:54:27-0400

2019-08-08T10:54:28-0400

2019-08-08T10:54:38-0400

2019-08-08T10:54:43-0400

2019-08-08T10:54:44-0400

2019-08-08T10:54:50-0400

File details come from the government source that posted it. Updated .