This document contains an amendment to a solicitation for a design-build and design-bid-build multiple award construction contract from the Naval Facilities Engineering Command. The solicitation is for new construction, repair, and renovation of various facilities within the command's area of responsibility, including locations in Washington D.C., Maryland, and Virginia.
The amendment provides responses to 78 questions from prospective offerors. It clarifies requirements around site access procedures, erosion control measures, hazardous materials handling, supervisory roles, testing responsibilities, and other contractual aspects. It also revises the price schedule and attaches supplemental specifications for masonry, painting, and landscaping work. Offerors are instructed to review the full amendment for updates to the solicitation requirements and pricing terms prior to submitting a response.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0006.pdf | ||
| Site Visit Sheet-13JAN2020.pdf | ||
| AMEND 0005-ATTACH #1-Masonry and Paint Spec - Div 04 and 09.pdf | ||
| AMEND 0005-ATTACH#3-Revised Price Schedule dated 9 January 2020.docx | DOCX document | |
| AMEND 0005-ATTACH #2-Seeding Specification.pdf | ||
| AMENDMENT 0004.pdf | ||
| AMENDMENT 0003.pdf | ||
| 17 December Site Visit Attendance Sheet.pdf | ||
| Revised Past Performance Questionnaire.docx | DOCX document | |
| PC170005.jpg | JPG image | |
| PC170001.jpg | JPG image | |
| HUBZONE MACC AMENDMENT 0002.pdf | ||
| PC170007.jpg | JPG image | |
| PC170006.jpg | JPG image | |
| PC170004.jpg | JPG image | |
| PC170002.jpg | JPG image | |
| PC170003.jpg | JPG image | |
| AMENDMENT 0001.pdf | ||
| CBD Price Schedule dated 3 December 2019.docx | DOCX document | |
| CBD CATEX.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| CBD Basis of Design Final.pdf | ||
| CBD DRAWINGS-FINAL.pdf | ||
| CBD SPECS - FINAL.pdf | ||
| NRL SECNAV_5512-1.pdf | ||
| CONSTRUCTION EXPERIENCE PROJECT DATA SHEET.docx | DOCX document | |
| SOLICITATION N4008020R0007 HUBZONE MACC.pdf |
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5771079
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N4008020R0007, DESIGN-BUILD & DESIGN-BID-BUILD HUBZone MULTIPLE AWARD CONSTRUCTION CONTRACT FOR NEW CONSTRUCTION, REPAIR, AND RENOVATION OF VARIOUS FACILITIES AT NAVFAC WASHINGTON AREA OF RESPONSIBILITY INCLUDING BUT NOT LIMITED
TO WASHINGTON, D.C., MARYLAND AND VIRGINIA.
PLEASE SEE SECTION SF 30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Jan-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008020R0007
X 9B. DATED (SEE ITEM 11)
05-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Jan-2020
CODE
NAVAL FACILITIES ENG COMMAND WASHINGTON
1314 HARWOOD ST
WASHINGTON DC 20374
N40080 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008020R0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
As an amendment to the solicitation, the following is hereby incorporated:
1. RFI Responses
2. Attachments
All other terms and conditions remain unchanged.
RFI RESPONSES
8. Does Miss Utility have access to the base? Should we include provisions for a third-party utility marking contractor?
GOVERNMENT RESPONSE: Miss Utility does not have access to base. Provisions for third part utility marking contractor must be made.
12. General: Where and how many employees will be allowed to park their personal vehicles for the seed project?
GOVERNMENT RESPONSE: Parking will be accommodated and available on site.
13. General: Please confirm the working hours available for the seed project.
GOVERNMENT RESPONSE: Per Spec Section 01 14 Work Restrictions, working hours are 7:00am to 3:30pm. There is also important information regarding installation access in this section.
15. General: Please provide badging/security requirements for personnel to access the site for the seed project.
GOVERNMENT RESPONSE: Per Spec Section 01 14 Work Restrictions
After award, the Contractor must fill out the Temporary Identification Badge Request HQ-NRL 5512/3 (Rev. 4-05)and SECNAV FORM 5512/1 which are available upon request. These forms must be filled out for each employee that requires access to the site, including deliveries, and be provided to CBD Customer Liaison. Each employee will be responsible to pick up badge in person. The forms contain, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall maintain a complete and accurate list of all personnel for whom passes have been requested under this contract. Once forms are approved for access, the contractor will be notified. At that time, badges are ready for pick up at: Naval Research Laboratory 4555 Overlook Ave. S.W. Washington, DC 20375-5320
16. General: Will non-U.S. Citizens be allowed access to the site?
GOVERNMENT RESPONSE: No
17. DWG. C-104: Please confirm the existing concrete pad and curb are to remain as-is except the curb section noted in note C5 on drawing C-104. If not, please provide details/requirements for the repairs/modifications.
GOVERNMENT RESPONSE: Confirmed
18. HAZMAT: Is any hazardous/contaminated soils anticipated? Has any soil testing been performed? If contaminated soils are present, has this been anticipated in the cut/fill amounts
GOVERNMENT RESPONSE: No soil is authorized to be removed from the site. Disturbed soils do not require removal and are to be retained on site. All in-situ soils must remain on site. There are no known hazardous soils per previous testing. No specific soil testing for the project has been performed at the project site. Nearby soil has tested positive for AFFF chemicals.
19. Erosion and Sediment Control: Will any erosion/sediment control measures/plans be required? If yes, please provide specifications.
GOVERNMENT RESPONSE: Silt fence is the only E&S control measure required. Silt fence detail provided on sheet C-104. Place silt fence at beginning of project site work, and remove once site is stabilized. E&S control measures shall be inspected by the Government Civil Engineer prior to any other work. The Government Civil Engineer shall inspect the work for satisfactory stabilization and approve removal of the E&C measures prior to their removal. Two-week’ notice shall be provided for requested inspections.
23. Price Schedule: In item 0001b, it indicates a requirement to provide unit pricing for sheet steel pilings for a "seawall". No drawings or specifications show or indicate a "seawall" is required. Please advise.
GOVERNMENT RESPONSE: Please refer to the Revised Price Schedule dated 9 JAN 2020 uploaded as an attachment to Amendment 0005.
24. Price Schedule: In item 0001b, there is a list of ten (10) unit priced items. Please confirm none of these items are to be included in 0001a price.
GOVERNMENT RESPONSE: All items in 0001b are not to be included in 0001a. Please refer to the Revised Price Schedule dated 9 JAN 2020 uploaded as an attachment to Amendment 0005.
25. Price Schedule: The drawings show requirements for electrical work in the demolition and new construction drawings. Which Item shall electrical work be priced under? 0001a or 0001b?
GOVERNMENT RESPONSE: Electrical work shall be caputed in Item 0001a.
26. Price Schedule: both items 0001a and 0001b have demo/removal of the 7 tanks. Please confirm demo/removal of the tanks shall be priced as a part of item 0001a. If work is to be priced under item 0001b, a general unit rate is not practical as there are different tank sizes which will result in different pricing.
GOVERNMENT RESPONSE: Tank demolition shall be captured in Item 0001a. Please refer to the Revised Price Schedule dated 9 JAN 2020 uploaded as an attachment to Amendment 0005.
27. Price Schedule: If demo/removal of the tanks is to be priced under item 0001b, please confirm removal of all 7 tanks shall be awarded.
GOVERNMENT RESPONSE: All seven tanks will be awarded. Refer to Revised Price Schedule dated 9 JAN 2020 uploaded as an attachment to Amendment 0005.
33. Will there be a 2nd Site Visit planned before 17 January 2020 at 2:00 PM EST?
GOVERNMENT RESPONSE: A 2nd site visit has been scheduled for 13 January 2020 at 10:00 AM.
Please see Amendment 0004 for details.
34. There is a discrepancy regarding the “on Site” personnel required, please clarify the number of on-site representatives required for this project.
GOVERNMENT RESPONSE: There is no discrepancy regarding on site personnel. The site is defined per the contract drawings and located at CBD. Section 01 30 00 paragraph 1.4.2 clearly defines the requirement for the Superintendent on site and limits this individual to performing the duties of Superintendent under the contract. This paragraph also strictly defines that if the awarded contractor intends, or would use the Superintendent as an alternate for the QC Manager or Site Safety and Health Officer (SSHO) then an alternate Superintendent must be approved as well. Section 01 35 26 paragraph 1.7.1.1.1 clearly defines the SSHO, and allows for the SSHO to perform the duties of QC Manager. Section 01 45 00 paragraph 1.5.1.1 clearly defines the duties of the QC Manager, allows for this individual to also perform the duties of SSHO.
35. The Bid form appears to be incorrect i.e. Bid Item 0001b Seawall, clarify Bid Form.
GOVERNMENT RESPONSE: See RFI 23.
36. Reference the Unit Prices on the Bid Form:
a. Are the Unit Price Item cost amounts to be included or omitted in Bid Line Item 0001 & Bid Line Item 0001a?
b. Items that are not identified in the Unit Prices to be only items included in Bid Line Item 0001 and Bid Line Item 0001b?
GOVERNMENT RESPONSE: Item 0001 includes all work described in Items 0001a and 0001b. A further explanation of filling out the price schedule is as follows:
The Offeror shall provide a lump sum price for the work described in Item 0001a, excluding the work in Item 0001b. The Offeror shall provide unit prices for each item described in Item 0001b.
These prices shall not be included in the 0001a price. The Offeror shall add Items 0001a and Item 0001b to get the total Price for Item 0001.
Please refer to the Revised Price Schedule dated 9 JAN 2020 uploaded as an attachment to Amendment 0005.
37. Is the intension of the Unit Prices to be used as Adds and/or Deducts from the Lump Sum Bid?
GOVERNMENT RESPONSE: The purpose is to establish a unit cost, should a Post-Award Modification for additional units be needed.
38. Are there any Liquidated Damages associated with this project?
GOVERNMENT RESPONSE: Liquidated Damages for this project is $97.73 Per Calendar Day. Please refer to pg. 16 of 165 of the SF 1442.
39. Is the web based eCMS currently operational and planned for use on this project?
GOVERNMENT RESPONSE: Yes, eCMS is operational and planned for use on this project.
40. Please confirm that the tank permit closure reports will be submitted to MDE and that permits for new tanks will be obtained through MDE.
GOVERNMENT RESPONSE: Confirmed. Contractor shall follow and provide all formwork and reports necessary per Oil Operations Permit provided in specifications.
41. Will NAVFAC PWD Annapolis provide the CM and Engineering Tech for this project?
GOVERNMENT RESPONSE: Yes, the Government will assign a CM and ET for the project.
42. Can the CIH serve as the QCM/SSHO?
GOVERNMENT RESPONSE: Yes, provided the individual meets the qualification requirements of all three positions and can perform all duties required in a timely, accurate, complete and safe manner.
43. Please confirm if a safety plan, independent of the accident prevention plan, is required per spec 33 01 50.60
GOVERNMENT RESPONSE: Safety plan requirements of section 33 01 50.60 may be independent of, or integrated into the overall Accident Prevention Plan required under 01 35 26.
44. Please provide details for the safety permits in 33 01 50.60 1.5.3
GOVERNMENT RESPONSE: Contractor will need the APP, Confined space plan with permit procedures, Hot work permit, Spill control and notification/reporting procedures, disposal plans for liquid and sludge with NRL Environmental sign the manifests.
45. Please send us the pre-bid sign in sheets as soon as possible.
GOVERNMENT RESPONSE: The Site Visit Sign in sheet from the first site visit was uploaded as an attachment with Amendment 0002 on 12/20/2019. Please refer to Amendment 0002.
46. SECTION 01 11 00 Page 1 - Clean tanks per federal and state codes referenced prior to demolition.
Does the contractor have to remove from site any contaminated cleaning liquids after the cleaning has been completed?
GOVERNMENT RESPONSE: Yes. There are detailed specifications for cleaning petroleum tanks in 33 01.50.60 Cleaning of Petroleum Storage Tanks.
47. SECTION 01 14 00 Page 1 - Soil potentially contains POL (petroleum Oil Lubricants) and chemicals associated with the Fire Suppressant AFFF to include PFAS. Include in Activity Hazard Analysis and Accident Prevention Plan. No soil is to be taken off-site. Please confirm the location were these soils are to be taken and if any special precautions are required for the storage of them?
GOVERNMENT RESPONSE: No soils are to be removed from the site. Soils are to be placed back into the ground where they came from, and stabilized after demolition activity.
48. SECTION 01 45 00.00 20 - Can the Site Super and the QC Manager be the same person, or are you requiring 2 different persons to carry these roles? Also are you requiring a Site Safety and Health Officer in addition to the persons above?
GOVERNMENT RESPONSE: There is to be a Quality Control Manager and Superintendent. QC Manager may serve as Site Safety and Control Officer.
49. TESTING LABORATORY INFORMATION: Who is responsible for paying for any testing?
GOVERNMENT RESPONSE: Contractor is responsible for any testing in relation to cleaning the tanks.
50. C104 Steel bollards any specifications?
GOVERNMENT RESPONSE: Provide 5’-6” inch galvanized standard weight steel pipe as specified in ASTM A53/A53M. Anchor posts in concrete and fill solidly with concrete with minimum compressive strength of 3000 psi. Set pipe guards vertically in concrete piers. Construct piers of, and the hollow cores of the pipe filled with, concrete having a compressive strength of 3000 psi.
51. C104/C105 Landscaping any specifications?
GOVERNMENT RESPONSE: If grass seed does not take, sod shall be provided. Refer to “Seeding Specification” which has been uploaded as an attachment to Amendment 0005.
52. Is the existing concrete to be removed to be considered contaminated? If yes, does it remain on site or does it get removed off site?
GOVERNMENT RESPONSE: The concrete on site is not considered contaminated. It shall be removed from the site and recycled.
53. A101 Masonry work any specifications?
GOVERNMENT RESPONSE: Refer to “Masonry and Paint Spec - Div 04 and 09” which has been uploaded as an attachment to Amendment 0005.
54. Are you requiring new fencing around the new tanks, if yes do you have any specifications?
GOVERNMENT RESPONSE: No new fencing is required.
55. No painting specifications provided for the bollards and roof work provided
GOVERNMENT RESPONSE: Refer to “Masonry and Paint Spec - Div 04 and 09” which has been uploaded as an attachment to Amendment 0005.
56. What level of on-site supervision is required for the seed project i.e. can the on-site supervision be a dual/triple hat?
GOVERNMENT RESPONSE: Site supervision shall be in accordance with the contract as written.
Specifically sections 01 30 00, 01 35 26, and 01 45 00. Additional information can be found in response to RFI question 34.
57. What is the asphalt specification to be used? MDOT standard road?
GOVERNMENT RESPONSE: The asphalt spec is based on the MDOT standard road.
58. Will the contractors receive project length passes or will the employees need to sign in each day?
GOVERNMENT RESPONSE: Per Spec Section 01 14 Work Restrictions
After award, the Contractor must fill out the Temporary Identification Badge Request HQ-NRL 5512/3 (Rev. 4-05)and SECNAV FORM 5512/1 which are available upon request. These forms must be filled out for each employee that requires access to the site, including deliveries, and be provided to CBD Customer Liaison. Each employee will be responsible to pick up badge in person. The forms contain, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall maintain a complete and accurate list of all personnel for whom passes have been requested under this contract. Once forms are approved for access, the contractor will be notified. At that time, badges are ready for pick up at: Naval Research Laboratory 4555 Overlook Ave. S.W. Washington, DC 20375-5320
These Temporary Identification Badge is valid for 90 days.
59. Do light poles being removed get salvaged to Owner or disposed off-site?
GOVERNMENT RESPONSE: Disposed offsite.
60. Note C-9 on sheet C-102 says we are to remove storm structure and any outgoing pipe. Is pipe to be removed from ground or capped and covered / abandoned in place?
GOVERNMENT RESPONSE: Remove the structure shown on photo 3 on sheet C-102. 100 linear foot of underground pipe to be demolished.
61. Are there any restrictions for truck size or weight on base?
GOVERNMENT RESPONSE: No.
62. Do all employees / workers need to be US citizens?
GOVERNMENT RESPONSE: Yes.
63. Will escorts be required while performing work? (If so, how many workers per escort?)
GOVERNMENT RESPONSE: Escorts will not be required. All personnel will be vetted for the site.
64. Can one person be superintendent, SSHO and QC?
GOVERNMENT RESPONSE: There is to be a Quality Control Manager and Superintendent. QC Manager may serve as Site Safety and Control Officer.
65. Drawings E101.The Gasoline Tank specifies class 1 division 1 (explosion proof) rated installation but C315 building does not indicate that rating, which is correct? Also, for the high-low level sensor, Alarm box, and leap detector float switch, do you require all these devices to come with their own explosion proof enclosure?
GOVERNMENT RESPONSE: Both are correct, as they are in different locations with different hazard requirements. Comply with the drawings. The sensors, alarm box, and leak detection float switch can be installed in explosion proof devices, or may come pre-assembled in explosion proof devices from their manufacturer. Provided submitted materials and installation meet code requirements either alternative is acceptable to the Government.
66. Reference: RFP Document – Page 26 last paragraph of Item 8 - Note: states “In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)0.
Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability “unknown” shall be considered “acceptable”. Is this statement correct? As past performance is one of the criteria for being awarded one of the MACC contracts should this be unacceptable in lieu of acceptable. It seems unfair that a company with no experience can submit a low cost and be awarded a contract when a company with outstanding past performance could be eliminated for having a slightly higher cost.
GOVERNMENT RESPONSE: This is a requirement per FAR 15.305(2)(iv). The requirement remains unchanged.
67. Reference: Drawing G-101 – General Note 2 - This note refers to the existing soils potentially containing POL (Petroleum Oil Lubricants) and chemicals associated with the fire suppressant AFFF.
Should we provide unit prices for the removal and replacement of contaminated soils in our proposal?
GOVERNMENT RESPONSE: No. No soils are to be removed from the site. Soils are to be placed back into the ground where they came from, and stabilized after demolition activity.
68. Reference: Building C273 - At the site visit it was noticed that there are two pipes entering Building C273 that is to be demolished. These pipes are not shown on the project documents. What is to be done with these pipes prior to demolition?
GOVERNMENT RESPONSE: The pipes are abandoned. Cut and cap pipes below grade. Abandon in place. Contractor shall document them on redlines in accordance with 01 78 00 Part 3.
69. Reference: Drawing C-104 – Construction Note C8 - Construction Note C8 states “Provide Concrete Bollards (Eight Total) see detail 4/C-104. The plan only indicates 6 bollards. If we are to provide 8 bollards in lieu of the 6 shown, where are these other 2 bollards to be installed?
GOVERNMENT RESPONSE: There are only 6 bollards. Contractor will only be required to provide 6 total bollards.
70. Reference: Superintendent and QCM/SSHO - Do the Superintendent and CQM/SSHO have to be direct employees of the General Contractor?
GOVERNMENT RESPONSE: Yes.
71. Reference: Specification Section 013217 – Paragraph 1.4 Software - This Specification Section calls for the schedule for this project to be done in Primavera P6. As this is a small project would NAVFAC consider allowing the use of Microsoft project for the schedule?
GOVERNMENT RESPONSE: The Government will consider the use of MS Project by the contractor as a variation submittal in accordance with section 01 33 00 after award. Under no circumstances will the data, content, analysis, or information products required by 01 32 17 be lowered if MS Project variation is deemed acceptable after award.
72. Reference: Specification Section 014500 – Paragraph 1.5.2 Commissioning Authority - Is the Commissioning Authority for this project to be provided by NAVFAC or is this person to be hired by the General Contractor?
GOVERNMENT RESPONSE: General Contractor shall provide the Commissioning Authority.
73. Reference: Site Visit - Please advise if there will an additional Site Visit, and if we can have another RFI period to submit questions.
GOVERNMENT RESPONSE: A 2nd site visit has been scheduled for 13 January 2020 at 10:00 AM.
Please see Amendment 0004 for details. The RFI cut off date was extended via Amendment 0003 to COB 3 January 2020.
74. is it possible to do a second site visit? We have some subcontractors that would like to view the site.
GOVERNMENT RESPONSE: A 2nd site visit has been scheduled for 13 January 2020 at 10:00 AM.
Please see Amendment 0004 for details.
75. Reference: Factor 1 – Construction Experience (page 20) states: Use of the attached Construction Experience Project Data Sheet is MANDATORY and SHALL be used to submit project information.
Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page [or two (2) single-sided pages]. Please confirm the first page of the Construction Experience Project Data Sheet is excluded from the “one (1) double-sided page [or two (2) single-sided pages]” page limit.
GOVERNMENT RESPONSE: The first page of the Construction Experience Data Sheet is not excluded from the page limit.
76. Supervision: Please confirm the quality control manager position may be dual hatted by the superintendent or project manager.
GOVERNMENT RESPONSE: No, this is specifically rejected and not in compliance with the contract. Read sections 01 30 00, 01 35 26, and 01 45 00 and comply with the contract.
77. Phasing: Please confirm the project must be completed in two phases, phase 1 being the removal and new work for the 7 fuel tanks, and phase 2 being the removal of the two sprinkler system tanks.
GOVERNMENT RESPONSE: Confirmed. The work must be completed in two separate and sequential phases.
78. Reference: There seems to be inconsistency between self performance limitations per FAR 52.219- 3(d)(3) and the more recently issued SBA’s regulations concerning HubZone firms —namely, 13 C.F.R. § 126.616(d), 13 C.F.R. § 125.6(a)(3), and 13 C.F.R. § 126.700. Is compliance with the SBA's regulations sufficient for this solicitation given its under the broad general contracting NAICS 236220?
GOVERNMENT RESPONSE: CFR would take precedence over the FAR as the small business contracting program fall under SBA’s authority to provide regulatory guidance.
ATTACHMENTS
- Masonry and Paint Spec - Div 04 and 09
- Seeding Specification
- Revised Price Schedule dated 9 JAN 2020
(End of Summary of Changes)