Answers to GPOL Pre Proposal Inquiries (Last set of RFI's).

View the file

Other files

File Type Posted
N3943014R1405_JA.pdf PDF
ATTACHMENT_7.1_-_NAVFAC_Form_4330-43.xlsx XLSX spreadsheet
SEED_PROJECT_RFP_Part_1_-_Clean _Inspect_and_Repairs _POL_Facilities _NAS_Pensacola_FL.pdf PDF
N39430-14-R-1405_Amendment_0007.pdf PDF
N39430-14-R-1405 _Amendment_0006.pdf PDF
Answers_to_GPOL_RFI_PPI.pdf PDF
Conformed_Solicitation_N39430-14-R-1405.pdf PDF
N39430-14-R-1405_Amendment_0005.pdf PDF
5235953.pdf PDF
5236040.pdf PDF
5236041.pdf PDF
5236043.pdf PDF
5235954.pdf PDF
5236042.pdf PDF
5235948.pdf PDF
5236044.pdf PDF
5236039.pdf PDF
5235952.pdf PDF
N39430-14-R-1405_Amendment_0004.pdf PDF
N39430-14-R-1405_Amendment_0003.pdf PDF
GPOL_Clean _Inspect_and_Repairs_POL_Facilities _NAS_Pensacola_PART_2-6.pdf PDF
GPOL_Pre_Proposal_Conference_Presentation.ppt PPT presentation
GPOL_Seed_Project_Site_Visit_MAP.pdf PDF
SEED_PROJECT_RFP_Part_1_-_Clean _Inspect_and_Repairs _POL_Facilities _NAS_Pensacola_FL.pdf PDF
N39430-14-R-1405_Amendment_0002.pdf PDF
GPOL_Answers_to_PPI_RFI's_01.pdf PDF
GPOL_SEED_PROJECT_Clean_Inspect_Repair_POL_Facilities _Pensacola_FL_Parts_2-6.pdf PDF
GPOL_ATTENDANCE_ROSTER.pdf PDF
ATTACHMENT_7.1_-_NAVFAC_Form_4330-43.xlsx XLSX spreadsheet
GPOL_Amendment_0001.pdf PDF
SEED_PROJECT_PLACE_HOLDER__RFP_Part_1_-_CIR _POL_Facility _MCAS_Beaufort_SC.pdf PDF
GLOBAL_POL_SOLICITATION_RFP_PART_1.docx DOCX document
ATTACHMENT_7_SEED_PROJECT_PLACE_HOLDER_Parts_2-6_CIR_POL_FACILITIES_BEAUFORT_SC.pdf PDF
RFP_Global_POL_MACC_SOW_Combined_Part_2_thru_6.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Reference Question Asnwer 271 GPOL Part 2-6, Sec Part D40 Fire Suppression, D4090 Other Fire Protection Systemes

“Remove existing foam fire suppression system piping attached to fuel tank. For portions of fire suppression system not attached to tank, leave in service and restore system functionality with regard to piping which is removed.” 1.) What is the extent of the AFFF piping to be demolished at the tanks? 2.) Does the underground piping need to be grouted/slurry filled?

The fire suppression system shall be capped at both ends of the system.

Existing piping shall be left in place, but marked "inoperable". Assume piping will not require slurry at this time.

272 GPOL Part 2-6, Sec 01 14 00.05 20, G306003 Liquied Fuel Storage Tanks, 1.3.a/Scheduling

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. No more than two fuel tanks shall be removed from service at the same time. However, of those two, no more than one of the ready fuel tanks (Tanks 5 and 6) can be out of service at the same time. Return a fuel tank to service before removing the next fuel tank from service. Submit written request to the Contracting Officer 60-days in advance for permission to remove a tank from service. G306003-Scheduling No more than one bulk storage tank shall be removed from service at any time (Tank 1, 2, 3, or 4). After a tank is returned to service, another tank of similar size will be allowed to be removed from service. No more than one ready tank (Tank 5 or Tank 6) shall be removed from service. After a tank is returned to service, another tank of similar size will be allowed to be removed from service. No more than one bulk tank and one ready issue tank can be out of service at any one time. Can more than one bulk tank be out of service at a time if no ready tanks are out of service?

No more than one bulk tank can be out of service at any given time.

273 Page 14, GOVERNMNT

SAFETY

REQUIREMEN

TS FOR

DESIGN-

BUILD, Para 1.6.5 01 35 26.05 20

1.6.5 EMERGENCY MEDICAL TREATMENT Contractors

will arrange for their own emergency medical treatment.

Government has no responsibility to provide emergency medical treatment. 1.) Will the government provide confined space entry emergency response?

The base cannot provide confine space entry emergency response.

274 Administrative Requirements for

DB 30 00.05 20,

Para 1.6.5

Provide at least one (1) on-site Project Superintendent/Site Manager per project…. And the Project Superintendent shall mean the individual with the responsibility for quality and production. 1.) Will the Project Superintendent also be the Site QC Manager? 2.) Is a site considered each location if work is going on at both sites concurrently?

Refer to Part 2 01 30 00.05 20 1.5 Supervision. Refer to Part 2 01 45

00.05 20 1.4 QC Organization. The term "work site" shall mean Bulk Storage or Ready Issue and includes associated piping, fire suppression system, and secondary containment. There are two work sites. If work is occuring at both sites, it would be necesary to have two seperate SSHOs, one at each site.

275 Page 6, Sec 01 35 29.13. Para.

Health Safety Emergency

1.9.3.2 (b)

Be assigned to the site on a full time basis for the duration of field activites. The SSHO will have no duties other than Safey and Health related duties. 1.) Is a site considered each location if work is going on at both sites concurrently?

The Contractor shall provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Safety and Health Officer (SSHO). (See Part 2, Sec 01 35 26.05 20 Page 6 of the GPOL MACC SOW Combined Part 2-6).

276 Page 12, Sec 00210, III (a)(ii)

Please confirm that the “Schedule of Price CLIN 0001” required is simply Amendment 0002 Seed Project RFP Part 1, Section 00010 page 2.

Submission requirements are in accordance with page 12 of the Solicitation, (ii) Offeror shall complete - Schedule of prices CLIN 0001 - Seed Task Order Project and NAVFAC Form 4330-43. (iv) Bid Bond. The CLIN 0001 description is located in GPOL Seed Project Part 1, page 2.

277 Page 12, Sec 00210, III (a((ii)

Please verify that only the Schedule of Price CLIN 0001 and NAVFAC 4330-43 are required for the pricing of the Seed Project.

Submission requirements are in accordance with page 12 of the Solicitation, (ii) Offeror shall complete - Schedule of prices CLIN 0001 - Seed Task Order Project and NAVFAC Form 4330-43. (iv) Bid Bond. The CLIN 0001 description is located in GPOL Seed Project Part 1, page 2.

278 Throughout for N39430-14-R- 1405 and page 7 of Amend 2 for N39460-14-R- 1405, Sec 1.2.9

Please specify/clarify the contract number to be used on the bid bond for the Seed Task.

N39430-14-R-1405, Task Order 0001

279 Page 1, 01 14

00.05 20, 1.3(b)

Will the useable remaining fuel in the ready tanks be transferred to the other ready tank or must it be transported to one of the four bulk tanks?

The Government can't specify.

280 Page 2, 01 14

00.05 20, Para 1.3.f

Can the 60 day notice be provided for taking another tank out of service while one tank is still out of service, in anticipation that it will be back in service by the time the next tank is to be taken out of service?

After a government notice to proceed is made, a 60-day notice will need to be requested for initial bulk and ready issue tanks to be made available to the contractor. After all scope work for a tank is completed and it is ready to be returned back to the government, the government will have the next tank ready for turnover to the contractor within 10 working days.

281 Page 4, 01 32

17.05 20, Para 1.6.2.2

Although coating repairs cannot be started within 48 hours of an inspection, can other repairs contained in the SOW be started?

No coating repairs are to occur until a Notice to Proceed is made.

282 Page 14, Part 3;

Chap. 6/ESR G30

General System requirements: ASME B31.4 should not be applicable for this facility. Please confirm ASME B31.3 is the applicable reference instead.

Contractor should use applicalble reference.

283 Page 10, Part 3;

Chap. 6/ESR D20

D4090 Other Fire Protection Systems: Remove existing foam fire suppression system piping attached to fuel tank. For portions of fire suppression system not attached to tank, leave in service and restore system functionality with regard to piping which is removed. This is a tank dedicated foam fire suppression system therefore to what extend does the government want the fire foam system demolished?. ie can the underground piping be left in place and filled with slurry?

The fire suppression system shall be capped at both ends of the system.

Existing piping shall be left in place, but marked "inoperable". Assume piping will not require slurry at this time.

284 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: What is the existing coating on the interior of the tanks and how thick is it? Is the tank interior fully coated or just the floor and a limited distance up the shell wall?

Assume 100 percent coating on interior.

285 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: Is the center column requiring a bearing plate currently welded to the floor? Is it currently welded to the roof? Is this the only column existing in these tanks? This center column consists of what kind of structural member?

Unsure of exact details of center column. Only one column (I beam) in tanks.

286 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: Are the three tank internal pipe supports currently welded to the floor? What kind of structural members make up these pipe supports?

Current pipe supports are directly welded to floor without an reinforcment pad. Angle iron.

287 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: With proper cribbing over the existing HDPE Liner in the dike area, will cranes and/or manlifts and/or forklifts be permitted within the dike area?

Will depend upon vehicle and liner protection design. No cranes or manlifts, bobcat may be permissible.

288 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: In addition to removing and replacing sealant between tank floor and top of ringwall, will the sealant between the ringwall and the concrete walkway surrounding the tank also require replacement?

No, only remove and replace sealant between tank floor and top of ringwall.

289 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: Is there an existing ladder from the roof to the interior? If not, is a ladder required from the roof to access the new IFR? If yes, does it require its own manway ?

No ladders currently existing in any of the tanks.

290 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: Are new striker plates required on the floor under the IFR legs since they have a 2.5 inch polytetrafluoroethylene (PTFE) foot securely fastened to the bottom end of the legs?

No striker plates shall be used if a protectant "cap/cushion" can be used instead.

291 Page 16, Part 3;

Chap. 6/ESR G30

G306003 Liquid Fuel Storage Tanks: UFC 3-460-01 requires a minimum of four 24-inch (600 mm) square inspection hatches on fixed roof tanks with floating pans. Will additional Inspection hatches be required?

Additional inspection hatches are not required, ladder will need to be accessed.

292 Part 3; Chap.

6/ESR G30

G306003 Liquid Fuel Storage Tanks: Is it possible to obtain the latest OOS inspection reports on these tanks?

Past inspection reports will not be provided at this time, however they will be available to the winning contractor after project award.

293 Part 3; Chap.

6/ESR G30

G306003 Liquid Fuel Storage Tanks: Is it possible to obtain the as-builts on the tanks and the diked area?

See Drawings incorporated into the Solicitation via Amendment 0005.

294 Page 16, 09 97 13.15, 3.6.2

Will night shifts and/or weekend work be permitted? The spec calls for dehumidification prior to start and until 4 days after interior coating has cured. Someone will have to be onsite to fuel up and watch equipment 24/7 while it is running. If those working hours are strictly limited, we can’t run the DH equipment 24/7 per spec without someone on night shift. If night shift is to be permitted, will work besides watching the dehumidifier be permitted since we will already have 1 man out there anyways?

See Part 2, Specification 01 14 00.05 20, 1.4.3 Work Hours and 1.4.4 Work Outside Regular Hours. (Note Normal working hours should be 0600 to 1500 for normal work week day.)

295 Page 16, 09 97 13.15, 3.6.2

Will 100% containment be required for the exterior sand blasting of the tank for coating?

Yes, following exterior coating specification.

296 General Question

Please verify that Tank #1 requires cleaning. Assume Tank 1 will be inservice and will require removal from service and will require cleaning.

297 General Question

Does NAVFAC intend to extend the project POP to compensate for reducing the simultaneous number of tanks available to the contractor from 3 to 2?

The Seed Project Period of Performance has been extended from (365 days) 12 months to 22 months.

298 General Question

Does NAVFAC intend to extend the proposal due date to allow adequate time to review and analyze Govt responses to contractor questions?

The Proposal due date has been extened from 26 Mar 2014 to 09 Apr 2014 no later than 02:00 PM PST, see Amendment 0004.

299 Seed Project, Part 1, Section 00100, Section

II(5)

Seed Project Part 1, section 00100, section II (5): The Period of performance is shown as 365 days. Considering the change in scheduling requirements that allows only one of Tanks 1-4 to be out of service at a time, will a Schedule that goes beyond the 365 days be acceptable or would that result in disqualification of the technical proposal for the seed project?

The Seed Project Period of Performance has been extended from (365 days) 12 months to 22 months.

300 Seed, Part 2-6, general

Seed Project Part 2-6, general: Are all repairs to Tanks 1-6 to be in accordance with the DoD Design Standard drawings AW 78- 24-27 for Aboveground Vertical Steel Fuel Tanks with Fixed Roofs?

TBD by Design-Build DOR.

301 Page 172-178, Seed, Part 2-6

Seed Project Part 2-6, page 172-178 of 329: Are interior coating repairs required where welding is performed to install the new overflow vents, roof vents, and other items related to the floating pans which are located above the 40” shell height anticipated for interior coating repairs?

Interior coating repairs above the liquid level are not request.

302 Page 167, Seed, Part 2-6, G2010 and G2030

Seed Project Part 2-6, page 167 of 329, G2010 and G2030: The Seed project includes the statement to “Provide repairs to cracked, damaged, and deteriorated curbs, walls, and dikes on Tanks 2, 3, 4, 5, and 6 to restore containment functionality and in accordance with UFC 3-460-01.” Please verify if the work is to be included as part of the scope of the seed project and, if so, provide quantities for bidding purposes.

No repairs to cracked, damaged, and deteriorated curbs, walls, and dikes are part of this project at this time.

303 Page 5, Sec 01 14 00.05 20, Para. 1.4.3

Paragraph 1.4.3 States: Working Hours Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday throughFriday, excluding Government holidays. Coating and blasting operations must generally be completed on at least a six day work week with variable start and stop times each day in order to insure compliance with recoat windows and to work around inclement weather. Please confirm that the working days and hours will be adjusted to accommodate tank coating requirements

See Part 2, Specification 01 14 00.05 20, 1.4.3 Work Hours and 1.4.4 Work Outside Regular Hours. (Note Normal working hours should be 0600 to 1500 for normal work week day.)

304 Will FAA Permits be required if a crane is used at either site Yes. Refer to Part 2, 01 14 00.05 20 1.4.7 Air Operations Obstruction Evaluation. Expect 45 to 90 days for approval.

305 Page 6, 01 35

26.05 20, Sec 1.6.1.1

Can the On Site Project Manager or Superintendent perform the duties of the SSHO?

Refer to Part 2, 01 35 26.05 20 1.6.1.1 Site Safety and Health Officer

306 Page 4, Sec 01 35 29.13, 1.7.1.1

Please provide the NEPA document Not available at this time.

307 Page 5, Sec 01 14 00.05 20, Para. 1.4.1

Can the On Site Project Manager or Superintendent perform the duties of the QC Manager?

Refer to Part 2, 01 30 00.05 20 1.5 Supervision

Refer to Part 2, 01 45 00.05 20 1.4 QC Organization

308 Page 12, Sec 6, G20

G20 SITE IMPROVEMENTS SYSTEM DESCRIPTION

States: Provide site improvements that support project goals.

G20 is intended to encompass aboveground fuel tank secondary containment areas and systems. G2010 Roadway is intended to include containment areas hich might receive vehicular traffic.

G2030 Pedestrian Paving is intended to include containment areas which do not receive vehiculartraffic. The site improvements system consists of tank secondary containment areas and systems, liner systems, pavements and pavement related features, and other exterior site development work related to this project. As required by this RFP, provide a design by a licensed Professional Engineer familiar with conditions local to the project site. Site design, including but not limited to design of containment, linear repair, fuel receipt and issue, parking and pedestrian circulation, will include coordination with the Civil Engineer and the Mechanical Engineer. Please verify that there will be no liner repair or concrete dike repair associated with this project.

No repairs to cracked, damaged, and deteriorated curbs, walls, and dikes are part of this project at this time.

309 Page 3, 01 31

19.05 20, 1.4.2

This specification section states that the design QA meeting may be held in a determined location or electronically. Is it the Government’s preference to hold the meeting electronically?

There are costs associate with holding the meeting at a physical location

Design meetings can be electronic or telephonic.

310 Page 1 & 17, Sec 01 14 00.05 20 & Part 3, 1.3 & Scheduling

There appears to be a phasing discrepency for the number of bulk tanks that can be brought out of service at any given time.

Section 01 14 00.05 20 implies that only the ready fuel tanks have a restriction that only one can be out of service at any given time, and that up to two bulk fuel tanks can be out of service at any given time. However, Part 3 Page 17 explicitly states that only one bulk tank can be out of service at a time.

Please clarify.

See Part 2, 01 14 00.05 20, 1.3a

No more than one bulk tank can be out of service at any given time.

311 Page 20, Sec 099713.15, 3.9.7.2

Does the owner have "as built" information containing the pre-test readings for 099713.15, Pg. 20,3.9.7.2 on tanks involved with this SOW? Other Base fuel tank interiors recently recoated with this spec.?

"As builts" information is not available.

312 Page 15, Sec 01 35 26.05 20, Para 1.8

The specification requires an NFPA certified marine chemist for all hot work around flammable material and confined spaces.

Does this mean that the marine chemist is required to be on site for the duration of these activities, or only for the initial assessment of the hot work permit for these activities?

Marine chemist is required for the initial assessment of the hot work permit for each hot work activity.

313 Page 1, Sec Part 2, 01 14 00.05 20 Part 2, 01 14

00.05 20 , 1.3.b(1)

“Removal of remaining fuel from fuel tanks: ”…Would it be possible to execute a tank-to-tank transfer utilizing a portable pumping system in order to avoid the expense of a vacuum tanker on-site?

It is permissable, but up to contractor to execute and only with governement approval.

314 Page 1, Sec Part 2, 01 14 00.05 20 Part 2, 01 14

00.05 20 , 1.3.b(1)

“(tank truck minimum size 8,000 gallon)”…Is it allowable to use smaller tank trucks and/or a contained FRAC tank in lieu of the 8,000 gallon tank truck?

Smaller tank truck is also acceptable. Fuel cannot be transferred until testing is complete and acceptable. Assume up to a 2 hour standby for test results.

315 Page 10, Part 3, Chapter 6, ESR D4090

What are the limits of the demolition? Are the existing lines inside the dikes to be capped and left in-place?

The fire suppression system shall be capped at both ends of the system.

Existing piping shall be left in place, but marked "inoperable". Assume piping will not require slurry at this time.

316 Page 10, Part 3, Chapter 6, ESR D4090

This statement is unclear: “For portions of fire suppression system not attached to tank, leave in service and restore system functionality with regard to piping which is removed.” What portion of this system will be functional?

The fire suppression system shall be capped at both ends of the system.

Existing piping shall be left in place, but marked "inoperable". Assume piping will not require slurry at this time.

317 Page 12, Part 3, Chapter 6, ESR G20 and G2030

This section seems to require site improvements with a design to “…containment, liner repair, fuel receipt and issue, parking and pedestrian circulation…”. Please provide details regarding what this work will include (complete dike replacement, crack repair, etc.)

No repairs to cracked, damaged, and deteriorated curbs, walls, and dikes are part of this project at this time.

318 Page 12, Part 3, Chapter 6,ESR G2010 and G2030

These sections seem to require repairs to “…cracked, damaged, and deteriorated curbs, walls, and dikes on Tanks 2, 3, 4, 5, and 6…”.

Please provide details regarding what this work will include (complete dike replacement, crack repair, etc.) for each tank area.

No repairs to cracked, damaged, and deteriorated curbs, walls, and dikes are part of this project at this time.

319 Page 6, Part 5, SECTION 33 56

13.13, 2.2.2.9

This Section requires two or more 3/16-inch diameter ground cables on the floating pan. Is a 1/8-inch cable permissible? A 1/8-inch diameter stainless steel cable that has a preset cast and helix. This causes the cable to spool on the top of the roof as it rises on the product. A larger diameter cable would cause a much larger spool to form on top of the roof. The larger spool increases the possibility that the cables can become tangled with the floating roof support legs and cause damage to the roof when the product level is lowered.

No, follow applicable specification.

320 Page 17, POL RFP SOW Part 3, Ch. 6, Scheduling

The tank SOW sequencing has changed from two bulk tanks & one ready tank; to one of each out of service at a time. Our initial assessment of the tasks & SOW indicates that completion of the project within 365 days from award of contract will be almost impossible to perform safely under the current working hours and tank availability. Can the working hours be adjusted to a six ten-hour day work week? Can more than one bulk tank be available at one time? Can the period of performance be extended to longer than 365 days to allow safe performance of the work?

See Part 2, Specification 01 14 00.05 20 1.4.4 Work Outside Regular Hours.

No more than one bulk tank can be out of service at any given time.

321 POL RFP SOW

Part 3, Ch. 6 Tank 1: 5)

The SOW requires an 8” stilling well to be installed in an 8” roof nozzle. The normal configuration for an 8” aluminum stilling well is to slide in a 10”carbon steel roof nozzle with a flange on the end of the stilling well that stacks on the nozzle flange with identical bolt holes. Because the stilling well is aluminum, it should not be welded directly to the roof nozzle, which is carbon steel. Should the proposal use an 8” aluminum stilling well and replace the existing 8” carbon steel roof nozzle with a new 10” roof nozzle, or should the proposal use a 6” aluminum stilling well to fit inside the existing 8” carbon steel roof nozzle?

Proposal shall included an 8" stilling well installed in a new 10" steel nozzle. Exact locations and other details will need to be figured during the tank inspections.

322 POL RFP SOW

Part 3, Ch. 6 Tank 2: 9)

The SOW calls for new “bearing plates” to be installed under the internal pipe supports in each tank. On a true “bearing plate”, the pipe supports would rest on top of the bearing plate, but not be welded to the bearing plate. Clips would have to be provided to hold the pipe supports in place. Is the intent of the SOW to provide reinforcing pads under the pipe supports?

Yes, reinforcing plates shall be installed as sited in RFP and should be completed seal welded and be in accordance to API 653.

323 POL RFP SOW

Part 3, Ch. 6 Tank 2: 14)

Per observations made during the site walk, it appears that the pilot to the control valve on each tank is attached to the shell of the tank with threaded fittings. Are those threaded fittings flush with the inner surface of the tank shell, or do they extend into the tank?

Unknown.

324 POL RFP SOW

Part 3, Ch. 6 Tank 2: 15)

Are the tanks internally coated all the way up the shell and extending to the underside of the cone roofs? What type of coating is in each tank? Are all of the tanks coated with lead free paint?

Yes.

Unknown.

Existing coatings are not known to contain hazardous materials.

325 Page 11, Global

Solicitation, II.

Submittal

Are the binder covers & tabs included in the page count? The following are excluded from the 200 page limitation: CCASS, JV's, teaming agreements, Past Performance Questionnaires, letter of commitments, cover letters, cover pages, tabs and table of contents.

326 POL RFP SOW There are various references throughout the POL RFP SOW about required meetings. The meeting location is defined to be per the (KO) Contracting Officers specified location. This can have significant cost, time and potential schedule impacts associated with with the specified meetings depending on who attends and the location of the meeting. Please define the location of each meeting and who is required to attend each meeting?

Follow RFP

327 Page 9, POL RFP SOW Part 1, The provided Davis Bacon Wage Determination - was for Construction Type Highway. Shouldn't this be based on the Davis Bacon Wage Determination - Construction Type Heavy Construction? ( If we use the different scale our price and cost structures will all be wrong. )

Davis Bacon Wage Determination Construction Type Heavy has been incorporated into Part 1 - Seed Project "Clean, Inspect and Repair Fuel Facility, Pesacola FL".

328 Global Solicitation /

POL RFP SOW

Part 2 Sect 01 32

17.05 20, 4.b / 1

The solicitation references the use of SURTRAK and Primavera P3 which are outdated software versions. Can current versions be used?

Refer to Part 2 01 32 17.05 20 1.4 Software.

329 During the site walk there were discussions and the contractors were told that the previous inspection reports would be provided. The information is needed to determine specific requirements to complete the repairs and have cost impacts.

When will we receive this information?

Past inspection reports will not be provided at this time, however they will be available to the winning contractor after project award.

330 There is an significant amount of information still needed to complete a proper and thorough proposal. We request a time extension of a minimum of two weeks after receiving all of the information needed to communicate with subcontractors and vendors to ensure compliance with the requirements?

The Proposal Due Date has been extended from 26 mar 2014 to 09 April 2013 no later than 2:00 PM PST.

331 Seed Project Please confirm that for the purposes of personnel that are required to be on “each project site” or to be on the “work site” at all times (e.g., SSHO and QC Manager), each tank is considered a different site?

Refer to Part 2 01 30 00.05 20 1.5 Supervision

Refer to Part 2 01 45 00.05 20 1.4 QC Organization

The term "work site" shall mean Bulk Storage or Ready Issue and includes associated piping, fire suppression system, and secondary containment.

There are two work sites. If work is occuring at both sites, it would be necesary to have two seperate SSHOs, one at each site.

332 Page 21, Sec

00210 IV.(4)

(i)(a)

Without as-built drawings and API Inspection reports, offerors will need to make several assumptions that impact pricing. How will the government evaluate differences in contractors’ pricing and technical approaches that result from different assumptions that may limit cost impacts at the proposal stage, but likely will result in change orders in the future?

See Drawings incorporated into the Solicitation via Amendment 0005.

333 Seed Project

RFP 00100, II.5

The Statement of Work for the seed project at NAS Pensacola indicates a Period of Performance of 365 days. Part 3 – Chapter 5 / ESR G30 – Page 17 - Scheduling indicates that “No more than one bulk storage tank shall be removed from service at any time (Tank 1, 2, 3, or 4).” Our analysis of the schedule indicates the project cannot be completed within the 365 calendar day POP requirement while meeting all other RFP requirements with regard to Government review times of documents, periods of expected inclement weather, 60 day notifications to the Navy prior to bringing a tank out-of-service, and limited number of work hours. Would the Navy consider extending the POP? If not, will proposers be disqualified from the procurement if one or more of the RFP requirements regarding the schedule issues identified above are not met? In addition to API Inspection Reports and as-builts, can the government please provide elevations of the alarm / HLSOV set points and maximum fill rates.

The Seed Project Period of Performance has been extended from (365 days) 12 months to 22 months.

334 Page 10, Seed Project Part 3 – Project Program, Chapter 6, D4090 – Other Fire Protection Systems

Please confirm contractor requirement to remove existing foam fire suppression system from applicable tanks?

The fire suppression system shall be capped at both ends of the system.

Existing piping shall be left in place, but marked "inoperable". Assume piping will not require slurry at this time.

335 Page 12-13, Seed Project Part 3 – Project Program, Chapter 6 G20 G2010 G2030

Please confirm contractor requirement to perform repairs. If required, please supply quantity of cracked, damaged and deteriorated curbs, walls and dikes needing repair.

No repairs to cracked, damaged, and deteriorated curbs, walls, and dikes are part of this project at this time.

336 00010, 00100, Price Schedule, D.2

Section 00100, Instructions to Offers, item D.2 – calls for completing attachment 7.1 NAVAFAC Form 4330-43. Volume 2 – Price Proposal, item III Price Evaluation Factor, (b) Basis of evaluation – last bullet states “Analysis of data other than certified cost or pricing data provided by the offeror”. If we provide sufficient detail that the government can clearly evaluate our pricing, can the requirement for the 4330-43 be removed? If not, will the government allow us to lump all of our subcontractors together on the 4330-43 and remove the requirement for a separate 4330-43 for each subcontractor?

Refer to revised NAVFAC FORM 4330-43, Direct Subcontractor Totals (L64) changed FROM "The Subcontractor Items of Work schedule, above, should be completed for each separate subcontractor and included in the offeror's price proposal" TO "The final awardee will be requred to complete and submit the Subcontractor schedule, above, for each separate subcontractor included in the awardee's price proposal".

337 Seed Project Part 3 – Project Program, Chapter 6, Para 4

External coating repairs include removal of existing coating and recoat of entire exterior to include tank shell, roof, appurtenances and stairways. Observation: Existing stairways have galvanized stair treads and hardware that appear in good condition. Given this, removal of the galvanized surface in lieu of the specified coating may diminish corrosion protection over the existing galvanized application (when applied to stair tread grating with extensive corner and edge area). Question: Is the contractor to sandblast remove existing galvanized surfaces, to include tread grating, and recoat per the specification?

Galvanized, alumium, and stainless steel surfaces shall NOT be blasted and/or coated.

338 Seed Project Part 3 – Project Program, Chapter 6, Para

Newly applied internal coatings will require uninterrupted dehumidification 24 hours a day for four (4) days as part of the curing process. Since site access work hours are 0600-1430, will contractor personnel be allowed 24 hour site access to provide oversight and equipment monitoring / refueling during the dehumidification and curing process? Is the contractor required to be on site to monitor generators /DH equipment during non-working hours? Or will facility personnel monitor equipment overnight/non-working hours?

See Part 2 Specification 01 14 00.05 20 1.4.4 Work Outside Regular Hours.

Government will not monitor Contractor equipment.

339 Seed Project, General Question

Is it a contract requirement to have a full time SSHO/Safety Officer at both tank sites (bulk and ready ) locations during all construction activities, (total of two SSHO)?

Refer to Part 2 01 30 00.05 20 1.5 Supervision

Refer to Part 2 01 45 00.05 20 1.4 QC Organization

The term "work site" shall mean Bulk Storage or Ready Issue and includes associated piping, fire suppression system, and secondary containment.

There are two work sites. If work is occuring at both sites, it would be necesary to have two seperate SSHOs, one at each site.

340 Page 5, Sec 00100, Para. II-5

Completion date is shown at maximum of 365 calendar days.

Initial scheduling appears that the 365 day duration may not be achievable with current schedule restrictions. Will a POP extension be granted or can additional tankage be out of service concurrently?

The Seed Project Period of Performance has been extended from (365 days) 12 months to 22 months.

341 Page 5, Sec 01 14 00.05 20

Are the onsite work hours flexible, or are we limited to 7 am to 3:30 as specified. Pre Bid Meeting notes indicated available on site hours of 0630-1500. What if a specific work item may run late on a single day?

Refer to Part 2, 01 14 00.05 20 1.4.4 Work Outside Regular Hours.

342 Page 7, Part 3- Chapter 3, Table 3.2

Indicates government will not provide power – however if power is available and metered will the government provide this service?

Power for an office trailer only is available in the grass area located at the North side of the fence in front of Building 3882 near the bulk storage facility. The contractor will coordinate hookups, provide meter and pay for electricity.

343 Page 10, Part 3 Chapter 6?ESR D20, D4090 Other Fire Protection Systems

May we submit more than one resume per position as long as we remain within the page limitation?

Multiple resumes are allowed, evaluation will be in accordance with the Key Personnel Qualification Resumes in accordance with the factor basis of evaluation (see page 20-21 of the Solicitation). Page limitation remains 200 pages.

344 Page 22, Part 3 Chapter 6 ESR G30 and Part 3 Chapter 6 ESR G30 Page 19.

G306003 Tank Condition Assessment and Tank 1 Repairs

Tank 1 -4 condition assessment indicates 10,000 gallons for transfer back into fuel storage tank. Tank 1 Repair scope indicates Tank 1 is scheduled for OOS inspection, interior floor coating, center column bearing plate and interior piping repairs in 2014. a) Will this repair work be done by others prior to this Seed Project award? b) Will Tank 1 be placed back into service and required to be cleaned to perform the Repairs; or will the Tank be cleaned and left open for additional Program repairs noted.

a) Tank 1 repairs (apart from seed task scope item) will perfomred by others before award of seed project.

b) Assume Tank 1 will be inservice and will require removal from service and will require cleaning.

345 Sec 1.0, Page 3.

Sec 2.3 Page 4.

Sec 6.0 Page 14.

Part 3 RFP, docs on Part 2-6.

Sections 1.0 – Project Description; 2.3

– Project Specific Priorities; 6.0 – Engineering Systems Requirements, G30 Site Civil / Mechanical, General System Requirements, Piping Inspection and R i

Part 3 (6.G30) indicates Piping Inspection and Repair is “Not Used.” However, two other sections (1.0 and 2.3) reference API 570 pipeline integrity and pipeline penetration. For example: Section 1.0 states “Work to be performed includes an inspection of portions of the POL facility located at NAS Pensacola to include condition assessment, inspection, and repair in accordance with American Petroleum Institute (API) Standards 570…” Section 2.3 states “Priorities of the project are to collect a valid set of inspection data, use the data to assess pipeline and tank integrity, repair deficient conditions, and extend the life of the POL facilities.” Please confirm there is no work to be performed in accordance with API Standard 570.

No API 570 work required.

346 Part 2, Section 01 10 00.05 20 – pg 2 and 3, Part 3, Chapter 6, pag

17. Parts 2 and 3 of RFP document Parts 2-

6. Part 2 - Section 01 10

00.05 20, Paragraphs 1.3

(a) and (f). Part 3, Chapter 6, ESR G30, Page 17 Scheduling

Part 2, Section 01 14 00.05 20, Paragraphs 1.3 (a) and (f) indicate that no more than two fuel tanks shall be removed from service at the same time. Of those two, no more than one of the ready fuel tanks can be out of service at the same time. Part 3, Chapter 6, ESR G30, Page 17, Scheduling Paragraph indicates no more than one bulk storage tank shall be removed from service at any time. Please confirm it is the government’s intent that the bulk fuel tanks be performed one at a time, in series (per Part 3 reference), rather than allowing the last two bulk tanks to be performed simultaneously (per Part 2 reference).

No more than one bulk tank can be out of service at any given time.

347 Page 1-17, 01 14

00.05 20 & Part 3 1.3 & Scheduling

There appears to be a phasing discrepency for the number of bulk tanks that can be brought out of service at any given time.

Section 01 14 00.05 20 implies that only the ready fuel tanks have a restriction that only one can be out of service at any given time, and that up to two bulk fuel tanks can be out of service at any given time. However, Part 3 Page 17 explicitly states that only one bulk tank can be out of service at a time.

Please clarify.

No more than one bulk tank can be out of service at any given time.

348 Section 1.0 – pg 3; Section 2.3 – pg 4; Section 6.0

– pg 14. Part 3 of RFP document Parts 2-6.

Sections 1.0 – Project Description; 2.3

– Project Specific Priorities; 6.0 – Engineering Systems Requirements, G30 Site Civil / Mechanical, General System Requirements, Piping Inspection and Repair

Part 3 (6.G30) indicates Piping Inspection and Repair is “Not Used.” However, two other sections (1.0 and 2.3) reference API 570 pipeline integrity and pipeline penetration. For example: Section 1.0 states “Work to be performed includes an inspection of portions of the POL facility located at NAS Pensacola to include condition assessment, inspection, and repair in accordance with American Petroleum Institute (API) Standards 570…” Section 2.3 states “Priorities of the project are to collect a valid set of inspection data, use the data to assess pipeline and tank integrity, repair deficient conditions, and extend the life of the POL facilities.” Please confirm there is no work to be performed in accordance with API Standard 570.

No API 570 work required.

349 Part 2, Section 01 10 00.05 20 – pg 2 and 3 Part 3, Chapter 6, pg 17 Parts 2 and 3 of RFP document Parts 2-

6. Part 2 - Section 01 10

00.05 20, Paragraphs 1.3

(a) and (f). Part 3, Chapter 6, ESR G30, Page 17, Scheduling

Part 2, Section 01 14 00.05 20, Paragraphs 1.3 (a) and (f) indicate that no more than two fuel tanks shall be removed from service at the same time. Of those two, no more than one of the ready fuel tanks can be out of service at the same time. Part 3, Chapter 6, ESR G30, Page 17, Scheduling Paragraph indicates no more than one bulk storage tank shall be removed from service at any time. Please confirm it is the government’s intent that the bulk fuel tanks be performed one at a time, in series (per Part 3 reference), rather than allowing the last two bulk tanks to be performed simultaneously (per Part 2 reference).

No more than one bulk tank can be out of service at any given time.

350 Part 2, Section 01 10 00.05 20 – pg 2 and 3 Part 3, Chapter 6, pg 17 Parts 2 and 3 of RFP document Parts 2-

6. Part 2 - Section 01 10

00.05 20, Paragraphs 1.3

(a) and (f). Part 3, Chapter 6, ESR G30, Page 17, Scheduling

Based on our understanding of the schedule constraints for the sample project (i.e., four bulk tanks taken out of service one at a time), our Seed Project schedule will extend more than 365 days. Will the government consider extending the POP for the Seed Project?

The Seed Project Period of Performance has been extended from (365 days) 12 months to 22 months.

351 Page 11, Sec 00210, Sub Requirements Non Price Vol 1

The format requirements state “Each 11x17 page submitted will count as one (1) page.” Is this correct or should this actually state each 11x17 page shall count as two (2) pages?

Pages 11x17 single side will count as one page, double side will count as two pages.

352 Page 11, Sec 00210, Sub Requirements Non Price Vol 1

Can we assume drop-ins such as letters from teaming partners, CCASS ratings, ISRs be in the forms/letters native font style and/or size.

Tables and charts can be landscape format and can be font size 10.

353 Page 22, Sec 00210, Factor 5 Safety EMR DART Rate

The RFP requests EMR and DART data for complete calendar years (2010, 2011, 2012). Considering this data is available for calendar year 2013, will the government change the requirement to reflect calendar years 2011, 2013, and 2013?

EMR and DART Rates should be submitted for the previous completed calendar years of 2010, 2011, 2012.

354 Page 17, Sec 00210, Factor 4, Key Personnel, Submittal Requirements

The RFP states “Resume shall include professional licenses and certifications, number of years of experience, firms they worked for, a list of relevant POL projects (in accordance with the definition of relevant projects provided above that they have completed, and their role on these projects. Does the reference to “definition of relevant projects provided above…” refer to the definition of Relevant on page 14 under Factor 1, Corporate Experience?

Correct, definition of Relevant Project provided on page 14 of the Solicitation.

355 Page 17, Sec 00210, Factor 4, Key Personnel, Submittal Requirements

The requirements makes reference to the definition of relevant under Factor 1, which states projects must have been completed within the last five (5) years of the date of the issuance of this RFP. Since multiple Key Personnel requirements state experience more than 5 years is required such as: 10 years in POL Experience (Program Manager); 7 years of experience in POL facilities (Project Engineer); or 10 years of combined experience (QC Manager) will the government allow key personnel resumes to include project experience that dates beyond the 5 year limit imposed under Factor 1, Corporate Experience so that Offerors can fully document a candidates experience?

Resumes should be submitted in accordance with the definition of Relevant Projects however, relevant experience is allowed for experience dated beyond the 5 year limitation.

356 Page 17, Sec 00210, Factor 4, Key Personnel, Submittal Requirements

This section makes reference to the definition of “Relevant” used for Corporate Experience which states projects must be completed. Can an Offeror include projects on a resume that are substantially completed and that they will be weighted the same as a completed project?

Resumes should be submitted in accordance with the definition of Relevant Projects however, relevant experience is allowed for experience dated beyond the 5 year limitation.

357 Factor 3, Key Personnel, Basis for Evaluation

The Basis for Evaluation makes reference to functional areas specified in the PWS. Is this referring to the SOW_Combined_Part 2_thru_6.pdf? If so, this document does not reference functional areas of key personnel. Please clarify what the intention of functional areas relates to for this Factor.

Refer to GPOL SOW Combined Parts 2-6.

358 Part 4, Section G.1040 Hazardous Waste RemediationG10 40 1.5, Disposal, states that all waste materials will become the property of the Contractor

1) Does this statement mean that the Government expects that the Contractor take ownership of waste materials that the Contractor brings onto the site? 2) Does the term “waste materials” as used in this statement include hazardous material? 3) Does the term “waste materials” as used in this statement include hazardous waste? 4) Does this statement mean that the Government expects that the Contractor take ownership of the hazardous waste that was not previously identified as being on the site and may be found during work performed at the site? 5) If hazardous waste that was not previously identified is found during work performed at the site, will the Contractor be considered the owner of such waste because the Contractor has the responsibility for the proper transportation and disposal of the hazardous material, although the Government will be listed as the generator on the hazardous waste manifests?

Only RFP Part 4 requirements which apply to the project and further define RFP Part 3 project specific requirements are required. Part 3 G10 Site Preparation is not used.

359 MACC SOW, 01

57 19.00 20, 3.12.2 Hazardous Waste/Debris Management

Hazardous Waste/Debris Management states that the Government’s Station Environmental Office must sign all hazardous waste manifests prior to any hazardous waste being removed from Government property. Is the Government signing the manifest as the generator of the hazardous waste? The tank cleaning process will generate a substantial volume of contaminated liquid. Will the Government sign the manifest as the Generator of this waste?

Refer to Part 2 01 57 19.00 20 3.12 in its entirety. Identify all construction activities which will generate hazardous waste/debris. Provide a documented waste determination for all resultant waste streams.