- USS STETHEM (DDG 63) and USS DECATUR (DDG 73) Extended Dry-Docking Selected Restricted Availability
- Solicitation number
- N00024-19-R-4455
About this file
Govt responses to bidders' questions BQ #4 USS STETHEM (DDG 63)
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: N00024‐19‐R‐4455 Phone TPPC USS STETHEM ‐ TPPC‐DDG63‐SWRMC19‐CN01 Billy.castleberry, Contract Specialist, billy.castleberry@navy.mil 202‐781‐1248
Sheila Utz, Contracting Officer, sheila.utz1@navy.mil 202‐781‐2486
Q # Work Item No. Document Number/Title Document Type Question Government Response
52 150-80-001 ShipAlt DDG-51-AER83007D Increase Deck Plate Thickness Modifications (Partial); accomplish
1) Paragraph 3.4 states, "Accomplish the requirements of 2.3 and 2.4 for each location listed in 1.2, using 2.5 through 2.10 for guidance".
*Contractor has identified a Quantity (6 EA) Decoy Launchers and Foundation at location 1.2.1 and at least a Quantity (2 EA) Antenna and Foundations at location 1.2.3 that are considered to be Alignment Critical and would require Alignment, In-place Machine & Flame spray activities if it is determined that they must be removed and replaced.
2) Reference 2.3 GN 49 added by reference 2.4 RLAR 83007/DDG51CL/1166156 states, If Deck Surveys determine a need for replacement of topside COMBAT/C41 Antennas, Domes or Other Critical Alignment Equipment the Installing (IA) is requested to contact the local DDG Planning Yard for support.
*Contractor notes that there is no paragraphs included in the Specification written between 3.3.1 and 3.4 that allows for accomplishment of a Structural Deck Survey and submission of the results so that it can be determined if the existing Critically Aligned equipment Foundations will need to be removed and replaced in conformance with GN 49.
3) Note 4.1 states, "This work item will clear DFS DDG-63-0003-2017 for the 02-Level amidships".
*Contractor notes that a copy of DFS DDG-63-0003-2017 was not provided to bidders.
Can the Customer provide clarifications regarding the disparities between the specification and references identified in 1) & 2)?
Can the Customer provide the DFS DDG-63-0003-2017 document to all bidders?
The Govt fiinds no discrepancy in the specification. The intent of the work item is to replace the entire deck area listed in 1.2 of the work item and no deck survey is required.
All requirements including alighnments and information are contained within the work item and the listed references, or shall be covered under the applicable CAT I and II standard items.
Note 4.1 is written for tracking and informational purposes only. Since, the intent of the work item is to replace the entire deck; by default the DFS will be corrected and the need for the DFS information resolves.
53 N/A RFP
On page 106 of 198 the RFP states, NOTE F: SPECIAL AGREEMENT FOR CHANGES WITH A PRICE OF $25,000 OR LESS
To make administration of small dollar value changes more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process.
Question:
In NOTE F, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"?
The example used was chosen to illustrate that a hypotthetical RCC may request that a drawing be corrected or updated; however the RCC is administrative in nature, no work from the contractor is provided, and therefore, no small dollar value growth chit is used.
Pre‐Proposal Information (PPI) Question and Government Responses #4
NAVSEA POC
Name/Title/Email
To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, please contact Billy Castleberry, billy.castleberry@navy.mil, and Sheila Utz, sheila.utz1@navy.mil.
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
Q # Work Item No. Document Number/Title Document Type Question Government Response
54 N/A N/A
Contractor acknowledges contents of Attach J-13 (Stethem) EDSRA Flex Milestones which contains the Execution milestones planned and HM&E (CS) Turnovers along with CS Space Release Schedule for the EDSRA.
*Contractor notes that the HM&E (CS) Turnovers is identified as being "USS DECATUR DDG73 FY19 EDSRA HM&E (CS) Turnovers".
*Contractor notes that the J-13 does not currently include the Planning Events Readiness List (PERL) that provided to show each work item’s Milestone assignment for Work Certification.
This information is pertinent to ensuring that work item assignments are appropriately assigned and correlate to Government expectations.
Can the Customer provide a corrected HM&E (CS) Turnovers to hull DDG63?
Can the Government provide the PERL for the USS Stethem EDSRA?
A revised J-13 with PERL are provided via amendment 0004.
55 992-11-010 Temporary Service; provide
Paragraph 3.19 states, "Provide (31 EA) CONEX Boxes, size 8 feet wide x 20 feet long x 8 feet tall and deliver to the ship 15 days prior to the start of availability".
*Contractor notes the Attachment J-13 Flex Milestones does not include the "15 days prior to the start of availability" timeframe listed within the funded Period of Performance. The Government has the J-13 "Avail Start at KTR Facility" as September 16, 2019.
Will the Government revise the current Attachment J-13 to include the additional 15 days (At the NAVSTA?) or revise the delivery of Conex Boxes to the Start of Avail?
J-13 will not be revised to add 15 days. Delivery of CONNEX Boxes can be coordinated with the maintenace team upon contract award.
57 423-11-001 (E1) AN/WSC-9(V)2 Antenna Foundation; replace
Errata_0001, paragraph 3.3 was revised to state, "Remove the existing and install new foundation listed in 1.3 and located in 1.2.1, using 2.2 through
2.4 for guidance".
*Contractor as of the time of this writing has not received a copy of references 2.3 drawing 180- 6765056 Rev A, AN/USC-38(V) 2 EHF SATCOM Instl FDN Mod & ML and 2.3 drawing 180- 7517650 Rev A, EHF FOT AN/USQ-38(V) 9 STRL FDN Mods & ML.
Will the Government provided missing references 2.2 & 2.3?
Drawings 180-6765056 and 180-7517650 are provided via RFP FBO update.
59 123-15-002 Lube Oil Tank; repair
Paragraph 3.3.1.5 states, "Repair the known defect located at the bottom of tank listed in 1.2.3 using Detail 3A-1-5B of 2.6 for guidance".
*Contractor notes the (known defect) is unknown as there are no sub paragraphs of Paragraph
3.3.1.5 describing or defining the (known defect).
*Contractor notes paragraph 3.3.1.5 appears to be out of alignment and / or does not contain scope of repairs intended by the Customer to accomplish.
Can the Customer provided clarification as to the intended repairs of known defects to be accomplished by paragraph 3.3.1.5 located at the bottom of tank listed in 1.2.3 using Detail 3A-1- 5B of 2.6 for guidance?
Will the Customer provide an Errata revised specification incorporating change to all bidders?
Paragraph 3.3.1.5 is within the scope of weld build up in 3.3.1. It is specifically called out in the work item to ensure a known condition noted on a previous assesment is appropriately addressed and repaired.
No ERRATA shall be issued.
60 123-19-002 Waste Water Tank; repair
Paragraph 3.2.1 states, "Vee-out and weld a total of 3 linear feet of deteriorated and damaged welds. Area of repairs shall include deck, bulkhead, shell plating and overhead of each tank listed in 1.2 for a total of one square foot per tank".
*Contractor notes that Vee-out and weld a total of 3 linear feet is greater than a total of one square foot per tank when only 2 Tanks are identified in 1.2.
Paragraph 3.2.2 states, "Base metal weld buildup of 108 square inches of plating defects for tanks listed in 1.2 for a total of 36 square inches per tank.
*Contractor notes that weld buildup of 108 square inches of plating is greater than a total of 36 square inches per tank when only 2 Tanks are identified in 1.2.
Paragraph 3.2.3 states, "Remove existing and install new a total of 2 square feet of deteriorated plating for each tank listed in 1.2 for a total of 6 square feet".
Contractor notes a total of 2 square feet of deteriorated plating for each tank listed in 1.2 is less than for a total of 6 square feet when only 2 Tanks are identified in 1.2.
Can the Customer provided clarification as to the disparities identified above for paragraph 3.2.1,
3.2.2 and 3.2.3 of the specification as written?
Will the Customer provide an Errata revised specification incorporating change to all bidders?
ERRATA 5 corrects the below listed paragraphs:
3.2.1 change to 1.5 linear foot.
3.2.2 change 36 square inches to 54 square inches.
3.2.3 change 2 square feet to 3 square feet.
61 562-80-001 ShipAlt DDG51-64269D, Port and Starboard Rudder Weld Modifications; accomplish
Paragraph 3.1 states, "Accomplish the requirements of 2.2 through 2.4, using 2.5 for guidance".
Contractor notes as of the time of this writing reference 2.4 RLAR 64269/DDG59/1139592, Additional Hulls Added to Dwg Chg to Callout Stbd Rudder has not been provided.
Will the Government provided Para 2.4 (RLAR 64269/DDG59/1139592)?
RLAR 64269/DDG59/1139592 is provided.
62 262-90-001 (E2) ShipAlt DDG51-76253K, Install Lube Oil Coalescing Filter;
accomplish
Paragraph 3.9 states, "Accomplish the requirements of 009-13 of 2.1 for each differential pressure gage, pressure gage and temperature gage on each instrument panel assembly, using
2.9 for guidance".
*Contractor notes at the time of this writing reference 2.9 S9262-AQ-MMA-010 Rev-3 has not been provided.
Will the Government provided Para 2.9, S9262-AQ-MMA-010 Rev-3?
S9262-AQ-MMA-010 Rev-3 is provided via RFP FBO update.
63 571-31-001 (E2) Sliding Padeye, Tilting; overhaul and preserve
Paragraph 3.1 states, "Accomplish the requirements of 009-78 of 2.1 for removal and installation of Passive Countermeasure System (PCMS) for the equipment listed in 1.3 and located in 1.2, using 2.2 and 2.3 for guidance and the material listed in 5.1".
*Contractor notes at the time of this writing reference 2.3 472-6764961 Rev-A has not been provided.
Will the Government provided Para 2.3,v472-6764961 Rev-A?
v472-6764961 Rev-A is provided via RFP FBO update.
64 992-11-004 Temporary Service, Equipment and Systems Test, Inspection and Repair in Contractor Plant, Barge and Tow Barge; accomplish
Paragraph 3.1 states, "Pick-up and deliver the barge listed in 1.3 to and from the Contractor's facility plant 14 Days prior to Availability Start Date, using 2.4 for guidance.".
*Contractor notes the specification as written does not provide the Size of Personnel Berthing Barge expected to be provide in the Port of San Diego CA..
Can the Customer provide the Size / Dimentions Contractor can expect to be provided in the in the Port of San Diego CA?
Currently no specific barge has been assigned; for planning puposes estimated that barge is approximatel 261 feet long, 50 feet wide with a draft of 7 feet;
displacement is approximateky 40 to 50 tons.
65 251-31-003 Ship Service Gas Turbine Generator (SSGTG) Intake Number One; repair and preserve
Paragraph 3.4 states, "Remove existing CRES perforated shething for upper level of No. One SSGTG cleanside intake located in 1.2 as designated by the Supervisor, using 2.6 for guidance".
*Contractor notes the specification as written does not provide the cleanside location (i.e. space #) nor identifies which loction in Para 1.2 is Number One SSGTG .
Can the Customer provide the clean side location and drawings of areas of perforated sheathing to be removed?
The intent of work item is to repair and preserve the dirty side of Number One SSGTG Intake. Per drawing, the clean and the dirty side share the same compartment numbers listed 1.2.1.
3.4 was included in the work item to ensure and alert repair activity; if any structural repairs are accomplished, they would have to remove perferated sheathing on the opposite of ajoining cleanside bulkheads.
66 N/A RFP Page 17 of 23
Solicitation states, "Execution Scenario 2: Both the USS DECATUR (DDG 73) and USS STETHEM (DDG 63) availabilities together, utilizing concurrent “double” docking, if supported by the offerors’ available pier & dock facilities..."
*Contractor assumes that under Scenario 2, that a single Berthing Barge will be utilized to accommodate both crews for the duration of the avails in the Port of San Diego CA.
Question: Can the Customer confirm that in the Port of San Diego CA. a single Berthing Barge of adequate size and configuration to accommodate both vessels Ships Force duty sections will be provided for execution of Scenario 2?
Plan for separate barges provided.
67 N/A Attachment J-3 & J-13 Execution Milestones and Key Event Dates
IAW Section C - Descriptions and Specifications, SCOPE OF WORK, 2. LOCATION: which states, "Government facilities are not available for this requirement. All work shall be completed at the contractor’s facilities." Additionally, attachments J-3 and J-13 Execution Milestones and Key Event Date documents also identify the first milestone as, "Avail Start at KTR Facility."
These appear to be generalized statements prepared for a coastwide bid for out of homeport (San Diego) bidders.
The contractor has reviewed previously awarded contracts, both Coastwide and SDMAC, and notes that availablities accomplished in the Port of San Diego start pierside at NAVSTA 32nd Street for the first 14 Calendar days. This allows the customer and ship's force time to prepare the ship to enter contractors facility. Activities listed are not all inclusive: Ship's Force movement to Berthing Barge and Ship's Force off-load of stores, material, and portable equipment. This also allows the contractor an opprotunity to set-up temporary services; installation of staging, drain, disposal, and dewatering of specific water systems; installation of the AN/SPY-1D Antenna Protective Covers and installation of deck protection prior to arrival in the contractors facility.
Question: Can bidder's assume that if the contract is awarded to a bidder for accomplishment in the Port of San Diego, than the first 14 Calendar days will be accomplished pierside at NAVSTA 32nd Street prior to movement of the ship and berthing barge to the contractors facility?
Yes, the first 14 calendar days will be accomplished pierside at NAVSTA 32nd St.
prior to the ship's and barge's movement to the contractor facility.
68 992-11-019 Habitability Facility; provide (OPTION ITEM)
Location of Work 1.2.1 states, Pierside, Adjacent to the Ship
*Contractor notes that this is an Option specification that apears to be for those Bidders outside the vessels home Port of San Diego CA.
Can the Customer confirm that this Option Work Item is applicable only for those Bidders outside the vessels home Port of San Diego CA?
Yes, this only applies to out of homeport bidders.
69 N/A RFP - Proposal Scenarios
Contractor acknowledges that we are to provide multiple proposals to comply with the three scenarios in the RFP. The Contractor believes that proposals should be provided in the following manner:
Scenario 1 - Decatur Proposal (award Dectur not Stethem) Scenario 1 - Sthethem Proposal (award Stethem not Decatur) Scenario 2 - Decatur/Stethem Tandem Proposal (single award both ships) Scenario 3 - Decatur/Stethem Seperate Docks Proposal (single award both ships)
Question:
Does the Government concur that bidders are to provide a total of four seperate proposals for the three scenarios? Please advise soonest.
The Government clarifies that since each scenario results in separate contracts for each ship, up to six proposals should be submitted depending on an offeror's facilities:
Scenario 1 - Decatur Proposal (award Dectur not Stethem) Scenario 1 - Sthethem Proposal (award Stethem not Decatur)
Scenario 2 - Decatur/Stethem Tandem Proposal (award Decatur) Scenario 2 - Stethem/Decatur Tandem Proposal (award Stethem)
Scenario 3 - Decatur/Stethem Seperate Docks Proposal (award Decatur) Scenario 3 - Decatur/Stethem Seperate Docks Proposal (award Stethem)