Govt responses to bidders' questions, #2, DDG63

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: N00024‐19‐R‐4455 Phone TPPC USS STETHEM ‐ TPPC‐DDG63‐SWRMC19‐CN01 Billy.castleberry, Contract Specialist, billy.castleberry@navy.mil 202‐781‐1248

Sheila Utz, Contracting Officer, sheila.utz1@navy.mil 202‐781‐2486

Q # Work Item No. Document Number/Title Document

Type Question Government Response Solicitation ∆ 23 992-11-018, Messing and Berthing Barge Tow Service, Temporary Service, Equipment and Systems Test, Inspection and Repair in Contractor Plant; accomplish (OPTION ITEM)

Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Contractor notes that work items 992-11-004 and 992-11-018 specifications have the same scope of work identified and apear to duplicate each other.

*Contractor notes that work item 997-11-018 is an Option specification that apears to be for those Bidders outside the vessels home Port of San Diego CA.

Can the Customer confirm that that Option Work Item 992-11-018 is applicable only for those Bidders outside the vessels home Port of San Diego CA?

This option work item applies to out of homeport offerors only.

24 437-90-003 ShipAlt DDG51-77829K, Installation Radar and Time Domain Reflecto-Meter Tank Level Indicator for DFM, JP-5 and Potable Water; accomplish

Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.3 states "Accomplish the requirements of 009-26 of 2.1 to repair deck covering impacted by this ShipAlt"

*Contractor notes that paragraph 3.3 does not identify any reference documents (Drawings / Deck Schedule) for guidance or what Attachment(s) from NSI 009-26 are applicable to the deck covering repairs.

Please provide clarification as to the dispairity identified above in the specification as writtien?

The Ship Alt (SA) covers various location in order to accomplish the complete install and these locations may have various types of deck covering interfering with a portion of the SA (SI 009-23).

It is not the intent of 3.3 to replace the entire deck of each location interfering with completing the requirements of the SA. SI 009-26 is invoked to ensure that the correct and appropriate type of deck covering is installed and that all requirements associated with deck covering work is followed and adhered to.

25 450-90-002 ShipAlt DDG51-79322K, AEGIS Ballistic Missile Defense

(BMD)

4.1 Installation; accomplish (OPTION ITEM)

Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.4 states "Accomplish the requirements of 009-26 of 2.1 for each new and disturbed deck covering".

*Contractor notes that paragraph 3.4 does not identify any reference documents (Drawings / Deck Schedule) for guidance or what Attachment(s) from NSI 009-26 are applicable to the deck covering repairs.

Please provide clarification as to the dispairity identified above in the specification as writtien?

The Ship Alt (SA) covers various location in order to accomplish the complete install and these locations may have various types of deck covering interfering with a portion of the SA (SI 009-23).

It is not the intent of 3.4 to replace the entire deck of each location interfering with completing the requirements of the SA. SI 009-26 is invoked to ensure that the correct and appropriate type of deck covering is installed and that all requirements associated with deck covering work is followed and adhered to.

Pre‐Proposal Information (PPI) Question and Government Responses #1

NAVSEA POC

Name/Title/Email

To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, please contact Justin Lessel, justin.d.lessel@navy.mil, and Sheila Utz, sheila.utz1@navy.mil.

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

Q # Work Item No. Document Number/Title Document

Type Question Government Response Solicitation ∆ 26 438-90-001 ShipAlt DDG51-71726K, DDG Mod Full IBS Upgrade, Single

Bridge Watchstander; accomplish Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.5 states, "Accomplish the requirements of 009-26 of 2.1 including Attachment C for removal of existing deck and installation of new PRC deck covering in location listed in 1.2.2".

*Contractor notes that the vessel has been forward deployed and Homeported in Yokosuka, Japan for a number of years and may have recieved deck cover replacement and/or repairs that may contain a non-standard Rubber Based underlayment of verying thinkness that is not typical when accomplishing the requirements of NSI 009-26 Attachement "C" requirements.

*Contractor notes that this non-standard Rubber Based underlayment has been encountered on other vessels that have been forward deployed to Yokosuka, Japan for example USS Cowpens (CG-

63) during its SSRA / MODPRD avails and requires signifcantly more effort during the removal and preperation process that increases the cost than that typicaly encountered to accomplish NSI 009- 26 Attachement "C" requirements.

*Contractor notes that the following listed (14) specification found in the J-11 Specification Package also have requirements to accomplish NSI 009-26 Attachement "C" and are affected by the response to this PPI, WI's 438-90-003, 472-90-002, 512-90-002, 634-11-001, 634-11-006, 634-11- 012, 634-11-019, 634-11-023, 634-11-024, 634-11-025, 634-11-035, 640-11-002, 641-11-003 and 643-11-002.

Can the Customer confirm by listing the affected specification and locations any decks that may have recieved this non-standard Rubber Based underlayment during the vessel forward deployed to Yokosuka, Japan?

Information noted; however, JRMC, Yokosuka homeports a number of US Forward Deployed Naval Forces (FDNF) ships; it is known, that they use the same standards used stateside to repair and maintain our FDNF ships, unless, a departure from those standards have been authorized by delegated technical authority.

In this case, we cannot confirm if there was a departure authorizing the install of the mentioned non-standard rubber base underlayment. The work item (WI) provides the scope of work and the requirements that need to be met, therefore, perspective bidders are to submit proposal in accordance with the requirements of the WI.

27 251-30-001 Paragraph 3.6 states, " Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 31 for each louver assembly removed in 3.4, including each associated access door."

Contractor Question: Are these louvers hot dipped galvanized under the paint? (This is a concern of the only known source ACL (Automatic Coating Limited) of Canada, which will accomplish the requirements of 3.6

Please advise

Currently it is not known if the louvers have been hot dipped galvanized under the paint.

28 167-11-006 HATCH REPAIR REPLACE; ACCOMPLISH Paragraph 3.13 of the spec requires contractor to accomplish powder coating applied by fluidized bed method.

The only known source ACL (Automatic Coating Limited) has responded saying "this is not something that we do," "doors and hatches you would need to contact SWRMC, as they are set up there for doors and hatch coating."

Contractor request qualified known source other than ACL or suggest issuing an Errata to revise the requirements for 009-32.

Please advise.

Paragraph 3.13 revised to reflect exterior and interior hatch preservation. Powder coating is not required.

Errata 2

29 168-11-002 CARGO DOOR; REPLACE Paragraph 3.5 of the spec requires contractor to accomplish powder coating applied by fluidized bed method.

The only known source ACL (Automatic Coating Limited) has responded saying "this is not something that we do," "doors and hatches you would need to contact SWRMC, as they are set up there for doors and hatch coating."

Contractor request qualified known source other than ACL or suggest issuing an Errata to revise the requirements for 009-32.

Please advise.

Paragraph 3.5 modified. Powder coating is not required. Errata 2

Type Question Government Response Solicitation ∆ 30 437-90-003 Paragraph 3.1 Accomplish the requirements of sheets 3 through 6 of 2.2 including all general notes and ripout.

Paragraph 4.1-4.6 States Government AIT will accomplish all electrical work.

Please clarify who will be accomplishing electrical work.

AIT will not conduct any work inside the DFM, JP-5 and/or Potable water tanks.

Therefore, paragraph 3.1, MSR shall accomplish the electrical work from the tanks as per sheets 3 through 6 of 2.2 including all general notes and ripout notes associated with these sheets.

31 980-90-003 paragraph 3.12 Provide heavy metal sampling in 350 location and 1000 square feet of abatement as designated by the supervisor.

To allow fair and compeditive pricing more details are needed as the number and size of continments are a driving factor in price.

For estimmating porpuses please provide quntity of locations (requiring containment) and how many square ft per location to abate.

Example (350 locations @ 2.85 SF per location for a total of 1000 SF).

In this work item (WI), it is accepted that location that contain heavy metals is "UNKNOWN." In this case, since the locations are unknown, the government is not in the position to provide the locations.

The intent of 3.12 of the WI is to take samples at various locations to determine if any of those locations, do in fact contain any heavy metals, and that appropriate safety precautions can be taken as required. Also, in 3.12, it provides an exceptable assumption of 1,000 SQFT of paint to abate.

32 980-90-004 Paragraph 3.17 Install and maintain a steel tube and clamp type staging in locations of 1.2.21, 1.2.22, 1.2.26, 1.2.27 and 1.2.30.

Paraagraph 1.2.30 is not on the spec, please clarify.

Paragraph 3.17 modifed to delete the reference to paragraph 1.2.26, 1.2.27 and 1.2.30.

Errata 3

33 980-90-004 Paragraph 3.13 Provide heavy metal sampling in 100 location and 500 square feet of abatement as designated by the supervisor.

To allow fair and compeditive pricing more details are needed as the number and size of continments are a driving factor in price.

For estimmating porpuses please provide quntity of locations (requiring containment) and how many square ft per location to abate.

Example (100 locations @ 5 SF per location for a total of 500 SF).

In this work item (WI), it is accepted that location that contain heavy metals is "UNKNOWN." In this case, since the locations are unknown, the government is not in the position to provide the locations.

The intent of 3.13 of the WI is to take samples at various locations to determine if any of those locations, do in fact contain any heavy metals and that appropriate safety precautions can be taken as required. Also, in 3.12, it provides an exceptable assumption of 1,000 SQFT of paint to abate.

34 077-11-002 Fire Drill Service; provide Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.1 states, “Accomplish a fire drill in accordance with 2.1 and Chapter 12 of 2.2.”

Paragraph 3.1.1 states, “Fire Drill must be in conjunction with Ships Force and the SUPERVISOR, with participation from the region/installation or municipal fire and emergency services and personnel aboard the vessel.”

Paragraph 3.1.2 states, “Schedule the drill within 30 days after start of the availability.”

Paragraph 3.1.3 states, “Accomplish planning, organizing, and implementing simulated fire drill response. Facilitate planning, hotwash meetings and coordinate with outside agencies in accordance with Chapter 12 of 2.2.”

Paragraph 3.1.4 states, “Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR.”

*Contractor has reviewed this specifications work scope and notes that in the port of San Diego, California the South West Regional Maintenance Center (SWRMC) has historically accomplished and coordinated all facets of this work requirement with the Contractor only receiving a courtesy notification of when the fire drill will be scheduled.

*Contractor believes that this specification’s work scope, which is coordinated by SWRMC in San Diego, should be reviewed by the Customer and potentially be changed to an (Option Item) with some type of notification in the specification that could state, “This work item is only to be accomplished if contract is not awarded within San Diego (Option Item). If awarded within San Diego, the Category I NAVSEA Standard Item 009-07 will apply without further reference.

Does the Customer concur and will an Amendment be issued to revise the J-14 Pricing Workbook and invoke an Errata to revise the specification?

While SWRMC will participate, this requirement will be the contractor's responsibility, pertains to all offerors, and is required in the base CLIN.

Type Question Government Response Solicitation ∆ 35 635-11-011 Sound Damping; replace (OPTION ITEM) Attachment J-

Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.1 state, "Accomplish the requirements of 009-90 of 2.1 for the services of a qualified technical representative to provide on-site technical assistance, guidance, oversight, drawings and prints to support with maintenance and repairs for each sound damping tile located in 1.2".

*Contractor notes that (3) different Manufactures listed for the products identified in 1.3.1 through 1.3.4

*Contractor notes there isn't a name or point of contact information within the work item.

Will the Government issue an errata for the work item and provide the name of the OEM including point of contact information?

The three manufactures listed in the work item are the OEM; however, these are not required sources. The contractor may choose an equivalent as stated in the work item.

36 551-91-001 Self-Contained Breathing Apparatus (SCBA) Cylinder Inspect and Test; accomplish (OPTION ITEM)

Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.2 states "Accomplish the requirements of 009-90 of 2.1."

Paragraph 3.2.1 states "Provide the services of a Fire Protection Equipment Company technical representative for disassembly, inspection and testing of the equipment listed in 1.3, in accordance with Appendix D of 2.2, Chapter 4, Paragraph 4.5.4 of 2.3 and Chapter 77, Paragraph 3-81 of 2.4 for guidance, and Original Equipment Manufacturer's instructions for guidance."

*Contractor notes that in the Port of San Diego CA. for the Navy that these services are provided by a Scott Technologies approved Commercial Industrial Services (CIS) Service provider.

*Contractor notes that this is an Option specification that apears to be for those Bidders outside the vessels home Port of San Diego CA.

Can the Customer confirm that this Option Work Item is applicable only for those Bidders outside the vessels home Port of San Diego CA?

This option work item applies to all perspective bidders.

37 Various n/a The following work items call out a 4720 GFM ship alt kit. The revision or version of the 4720 is not clarified on the work item. the reference only states "4720-DDG63-FY19". Please clarify which revision of the 4720 the KTR should use to cross reference material to the drawings. 4720 references provided by the government are "4720-DDG63-FY19-A11" or "4720-DDG63-FY17-A2" 152-80-001 168-80-001 313-80-001 343-80-001 505-80-001 512-80-001 521-80-001 528-80-001 551-80-001

The 4720 GFM is a very fluid and dynamic document and is updated periodically by the planning yard (PY). The latest version is provided as it becomes available. This document is primarily designed to be for informational purposes. It identifies all the material that has been kitted by the PY for a specific SA that will be provided as

GFM.

The most current document is 4720-DDG63-FY19-A7 dated 12FEB19; will be provided.

Type Question Government Response Solicitation ∆ 38 Various n/a The following work items call out a 4720 GFM ship alt kit. The revision or version of the 4720 is not clarified on the work item. the reference only states "4720-DDG63-FY19". Please clarify which revision of the 4720 the KTR should use to cross reference material to the drawings. 4720 references provided by the government are "4720-DDG63-FY19-A11" or "4720-DDG63-FY17-A2" 436-90-001 437-90-002 512-90-001 516-90-001 542-90-001 651-90-001 262-90-001 437-90-003 438-90-001 438-90-002 438-90-003 439-90-001 439-90-002 441-90-001 541-90-001 472-90-002 450-90-001 450-90-002 462-90-001 468-90-001 472-90-001 482-90-001 512-90-002

The 4720 GFM is a very fluid and dynamic document and is updated periodically by the planning yard (PY). The latest version is provided as it becomes available. This document is primarily designed to be for informational purposes. It identifies all the material that has been kitted by the PY for a specific SA that will be provided as

GFM.

The most current document is 4720-DDG63-FY19-A7 dated 12FEB19; will be provided.

39 495-90-001 n/a The work item 495-90-001, calls out a 4720 that has not been provided, ref 2.10. KTR is looking for a copy of the following refernce, "4720-DDG63-FY20". Please provide

The most current document is 4720-DDG63-FY19-A7 dated 12FEB19; will be provided.

40 437-21-001 Lube Oil Storage and Settling Tank Level Indicating (TLI) System Cabling and Bushing; install

Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Paragraph 3.1 states, "Remove each existing cable and bushing listed in 1.3 at each location listed in 1.2".

*Contractor notes that Location 1.2.6 Lubricating Oil Storage Tank (3-291-2-F) is not listed within Reference 2.5, drawing 150890 Rev E, Tank Matrix, DDG-51 Class (DDG-56 THRU 78) and believes that it maybe incorrectly identified in the specification as written and should be identified as Lubricating Oil Storage Tank (3-290-2-F).

Please provide clarification for the above listed dispaity between Location 1.2.6 Lubricating Oil Storage Tank (3-291-2-F) of the Specification as written and Reference 2.5, drawing 150890 Rev E, Tank Matrix, DDG-51 Class (DDG-56 THRU 78)?

Review of all approved available NAVSEA drawings for the USS STETHEM indicate that the tank number listed on 1.2.6 (3-291-2-F) of the WI is correct. 2.5 is an OEM drawing and should be used as a reference for guidance.

41 VARIOUS Solicitation No.

N00024-19-R-

1) Since the ship was last painted in a US Shipyard, has there been any paint applied outside of the United States?

2) If so, verify that all paint applied outside of the United States met NAVSEA Standard Item FY19 Change 3, 009-32, table 1 thru 8 requirements?

1) The ship is currently homeported at Yokosuka, Japan; therefore, paint has been applied outside of the United States.

2) 009-32 3.1 General Preservation Requirements:

3.1.1 Consider marine coatings, and abrasive blasting media to contain heavy metals (e.g., beryllium, cadmium, chromium, or lead), hexavalent chromium, crystalline silica and/or other toxic or hazardous substances. 3.1.2 Accomplish safety precautions as specified in 2.2, 2.3, and the Work Item or task order during surface preparation and the application or removal of marine coatings. 2.3 29 CFR 1915, Occupational Safety and Health Standards for Shipyard Employment, Subparts C and Z.

Contractor is required to follow all requirements of the safety precautions listed in 009- 32.

Type Question Government Response Solicitation ∆

42 DDG 73 & DDG 63, 997-

11-001 Drydocking and Undocking; accomplish Attachment J-1

Specification Package No.

TPPC-DDG73-

SWRMC19-

CN01 and Attachment J- Specification Package No.

TPPC-DDG63-

SWRMC19-

CN01

Work Item 997-11-001, Drydocking and Undocking; accomplish

DDG-63 (USS STETHEM), Paragraph 3.1.7 states, "Drydocking period shall not exceed 180 days unless directed otherwise by the SUPERVISOR at the Docking Conference".

DDG-73 (USS DECATUR), Paragraph 3.1.7 states, "Drydocking period shall not exceed 280 days unless directed otherwise by the SUPERVISOR at the Docking Conference".

Contractor notes that the Maximum docking durations for USS STETHEM and USS DECATUR are 180 days and 280 days respectively.

In accordance with RFP Execution Scenario 2 (USS STETHEM and USS DECATUR utilizing concurrent “double” docking), bidder requests that the Maximum docking durations for both USS STETHEM and USS DECATUR be changed to “Drydocking period shall not exceed 280 days” (Same Duration). RFP Execution Scenario 2 requires the Docking and Undocking dates to be the same for both USS STETHEM and USS DECATUR.

In addition, the RFP provides the following Availability Start Dates:

USS STETHEM: 16 September 2019 USS DECATUR: 03 September 2019

In accordance with RFP Execution Scenario 2 (USS STETHEM and USS DECATUR utilizing concurrent “double” docking), bidder requests that the USS STETHEM and USS DECATUR Availability start dates be changed to 03 September 2019 (Same Date). RFP Execution Scenario 2 requires the Availability start dates to be the same to facilitate Docking both vessels at the same time.

The Navy’s responses to these bidder’s questions are required as soon as possible to facilitate required proposal preparation/estimating efforts, subcontractor/vendor solicitations and facility planning efforts.

Please advise soonest!

DECATUR docking work item was corrected to not exceed 180 days. 280 days does not support the availabity schedule.

Due to ship schedules, the start of availabity dates cannot be adjusted.

43 997-11-001 n/a Work Item 997-11-001, paragraph 3.7 requires that the vessel be drydocked within the first 10% of the contractual period. This unusually early constraint minimizes contractor scheduling flexibility and could result in limiting competition for the Government due to other dockings that may encroach on this time fence. Recommend that the language in paragraph 3.7 be removed to allow maximum flexibility for Offerors and increase the probability of the Government receiving multiple competitive bids.

Work Item is revised to reflect a dry-docking date within the first 25% of the availability.