LHD8 Execution USS Makin Island (LHD8)
FY17 DSRA
| EXECUTION MILESTONES / KEY EVENTS | |||||||
| Key Event/Milestone | Current - In Plant | Current - NAVSTA | Revised | Notes | |||
| A+ | Date | A+ | Date | A+ | Date | ||
| Start of Availability | 0 | 17-Jul-17 | 0 | 17-Jul-17 | |||
| Dock | 0 | 17-Jul-17 | - Offeror to Propose Dock & Undock Dates IAW Specification 997-11-002 |
- Offeror using San Diego Naval Station pier shall enter dock at "Start of Availability"
| Availability 20% Open and Inspect Reports Due | 84 | 09-Oct-17 | 84 | 09-Oct-17 | |
| Dry Dock Reports Due | - Offeror to Propose-Schedule Report Due Date no later than the first 20 percent of the scheduled docking period (IAW 009-01). | ||||
| Undock | - Offeror to Propose Dock & Undock Dates IAW Specification 997-11-002 |
- Offeror using San Diego Naval Station pier shall enter dock at "Start of Availability"
| 25% Conference | 107 | 01-Nov-17 | 107 | 01-Nov-17 | |
| 50% Conference | 212 | 14-Feb-18 | 212 | 14-Feb-18 | |
| 75% Conference | 317 | 30-May-18 | 317 | 30-May-18 | |
| Habitability Complete | 329 | 11-Jun-18 | 329 | 11-Jun-18 | |
| Engineering Production Complete Date (PCD) | - Offeror to Propose-Shall be scheduled after undock and before CSLO. PCD shall be scheduled at least 14 days prior to LOA IAW NSSI/JFMM and Work specification 982-11-001. | ||||
| Combat Systems Light Off (CSLO) | - Offeror to Propose-Schedule No later than A+333 (15-Jun-18) to support testing/SOVT. Major Alterations that will be tied to CSLO JSF Alts 1743/82876/82035 and 83220 | ||||
| Complete LOA | 371 | 23-Jul-18 | 371 | 23-Jul-18 | |
| Fast Cruise Start | 403 | 24-Aug-18 | 403 | 24-Aug-18 | |
| Dock Trials Start | 403 | 24-Aug-18 | 403 | 24-Aug-18 | |
| SOVT Complete | 403 | 24-Aug-18 | 403 | 24-Aug-18 | |
| Sea Trials Start | 406 | 27-Aug-18 | 406 | 27-Aug-18 | |
| Sea Trials Complete | 411 | 01-Sep-18 | 411 | 01-Sep-18 | |
| Sea Trials Correction Period Start | 411 | 01-Sep-18 | 411 | 01-Sep-18 | |
| Avail Complete | 419 | 09-Sep-18 | 419 | 09-Sep-18 |