N00024-17-R-4312_SSQ_Response_2-5.docx
DOCX document 29 KB Posted
- Attached to
- LCS Execution Planning Federal contract opportunity
- Solicitation number
- N00024-17-R-4312
About this file
Response to Contractor Questions 2-5
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESPONSE TO SOURCES SOUGHT QUESTION
DATE OF REQUEST: 5/12/2016 SOLICITATION NO: N00024-17-R-4312
QUESTION NO: 2-5
CONTRACTOR QUESTION:
Question 2: What type of maintenance activities are typically included in the sustainment availabilities?
Question 3: Will the planning services provided under this contract cover all maintenance activities, including Preventive Maintenance, performed on the LCS ship class?
Question 4: Once the LCS Execution Planning Support contract is awarded, will any 4E work specifications be written under the LCS Planning Yard and Sustainment contracts?
Question 5: Does the Government anticipate conducting an industry day in conjunction with this potential acquisition?
DO NOT WRITE BELOW THIS LINE
(FOR GOVERNMENT USE ONLY)
RESPONSE TO CONTRACTOR:
Response 2: Sustainment type of availabilities would be Chief of Naval Operations (CNO) Scheduled Availabilities, Continuous Maintenance Availabilities (CMAVs), Window of Opportunities (WOOs), and Planned Maintenance Availabilities (PMAVs). Work is also scheduled and accomplished by Alteration Installation Teams (AITs).
Response 3: No. This contract will not require any 4e Work Spec creation nor planning services for Preventive Maintenance/Facility Maintenance.
Response 4: Yes. Currently, Planning Yard Contract N00024-14-C-4313 allows the contractor to create 4e Work Specs for Ship Change Documents (SCDs) /Ship Installation Drawings (SIDs) they are tasked to work under modernization tasks. Work is also scheduled and accomplished by Alteration Installation Teams (AITs).
Response 5: The Government will evaluate the need for Industry Day after receipt of Sources Sought responses.
TECHNICAL
REVIEW:
DATE:
TECHNICAL SUPERVISOR
REVIEW:
DATE: