Admendment_1-Questions_and_Answers.pdf

PDF 13 KB Posted

Attached to
MK 48 Heavyweight Torpedo IMA Services for Pearl Harbor and Yorktown
Solicitation number
N00024-16-R-6405
Issued by

About this file

"Bidders and Questions and Answers" to RFP N00024-16-R-6405

View the file

Other files

File Type Posted
Amendment_0003-Questions_and_Answers.pdf PDF
Amendment_0003_to_RFP_N00024-16-R-6405.pdf PDF
Amendment_0002-Questions_and_Answers.pdf PDF
Conformed_Copy__-_Amendment_0002.docx DOCX document
Amendment_0002_released_copy.docx DOCX document
Attachment_9B_Yorktown_Staffing_Plan_Template_(161004).xls XLS spreadsheet
Attachment_9A_PH_Staffing_Plan_Template_(170106).xls XLS spreadsheet
Attachment_9A_PH_Staffing_Plan_Template_(170106).xls XLS spreadsheet
Attachment_9B_Yorktown_Staffing_Plan_Template_(161004).xls XLS spreadsheet
Attachment_13A_Wage_Determination.pdf PDF
Attachment_11B_YKT_CDRLs.pdf PDF
Attachment_11A_PH_CDRLs.pdf PDF
Attachment_6A_PH_Cost_Summary_Format_(170106).xlsx XLSX spreadsheet
Attachment_6B_YKTN_Cost_Summary_Format_(170106).xlsx XLSX spreadsheet
Attachment_7A_PH_Supporting_Cost_&_Price_Data_(161219)_loc.xls XLS spreadsheet
Encl_(1)_to_Attachment_4A_-_Pearl_Harbor_Incentive_Value_Spreadsheet_(160927).xlsx XLSX spreadsheet
Encl_(1)_to_Attachment_4B_-_Yorktown_Incentive_Value_Spreadsheet_(161117).xlsx XLSX spreadsheet
Amendment_0001_to_N00024-16-R-6405.pdf PDF
Attachment_7B_YKTN_Supporting_Cost_and_Price_Data_(161219)_loc.xlsx XLSX spreadsheet
Attachment_13B_Wage_Determination.pdf PDF
Attachment_8B_Yorktown_IMA_CDRL_Addresses.pdf PDF
Attachment_9B_Yorktown_Staffing_Plan_Template.pdf PDF
Attachment_1B_YKTN_IMA__Notional_Annual_Workload_Projection.pdf PDF
Attachment_13A_Wage_Determination_for_Holonulu_HI.pdf PDF
Attachment_10B_YKTN_Monthly_Status_Report_Sample.pdf PDF
Attachment_11B_YKT_CDRLs.pdf PDF
Attachment_18_Acronym_Listing.pdf PDF
Attachment_2B_YKTN_Concept_of_Operations.pdf PDF
Attachment_8A_Pearl_Harbor_IMA_CDRL_Addresses.pdf PDF
Attachment_5A_PH_DD254.pdf PDF
Attachment_4B_YKTN_Incentive_Fee_Plan.pdf PDF
Attachment_1A_PH_IMA__Notional_Annual_Workload_Projection.pdf PDF
Attachment_9A_PH_Staffing_Plan_Template.pdf PDF
Attachment_3A_PH_Government_Furnished_Information.pdf PDF
Attachment_2A_PH_Concept_of_Operations.pdf PDF
Attachment_6B_YKTN_Cost_Summary_Format.pdf PDF
RFP_N00024-16-R-6405.pdf PDF
Attachment_12B_YKTN_Key_Personnel.pdf PDF
Attachment_15A_PH_Notional_Contractor_Furnished_Vehicles_Equipment.pdf PDF
Attachment_17_PDLR_Charter.pdf PDF
Attachment_14A_PH_Production_Plan.pdf PDF
Attachment_11A_PH_CDRLs.pdf PDF
Attachment_7B_YKTN_Supporting_Cost_and_Price_Data.pdf PDF
Attachment_4A_PH_Incentive_Fee_Plan.pdf PDF
Attachment_6A_PH_Cost_Summary_Format.pdf PDF
Attachment_10A_PH_Monthly_Status_Report_Sample.pdf PDF
Attachment_12A_PH_Key_Personnel.pdf PDF
Attachment_7A_PH_Supporting_Cost_&_Price_Data.pdf PDF
Attachment_13B_Wage_Determination_2015-4342_for_YKTN.pdf PDF
Attachment_3B_YKTN_Government_Furnished_Information.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP N00024-16-R-6405 -- BIDDERS QUESTIONS AND ANSWERS

Question 1: RFP N00024-26-R-6405, 24 Feb 2017, Page 118 of 152 - HQ L-2-0009 SMALL BUSINESS SUBCONTRACTING PLAN (NAVSEA) (JUN 1999) - Offeror shall submit as part of its proposal a written proposed subcontracting plan in accordance with the clause entitled "SMALL BUSINESS SUBCONTRACTING PLAN" (FAR 52.219-9). The plan shall include the congressionally mandated five percent (5%) goal for small disadvantaged business concerns or a detailed explanation as to why the goal cannot be included in the plan. In the previous RFP for this LOE the government indicated “There is no set aside at the task order level. At the MAC level, Seaport minimum limits apply.” Is this the case with this RFP?

ANSWER: This RFP was not issued via SEAPORT and, as such, the SEAPORT minimum limitations do not apply. Offerors are advised to follow the instructions indicated in RFP N00024-16-R-6405.

Question 2: RFP N00024-26-R-6405, 24 Feb 2017, Attachment 13B indicates to use Service Contract Act Wage Determination # 2015-2342 Rev.1 dated 11/25/2015 for Yorktown. After answering the prompts as directed at http://www.wdol.gov/, the website provides # WD 2015- 2342 (Rev. 3) dated 12/30/2016. Is # WD 2015-2342 (Rev. 1) the correct WD to use?

ANSWER: RFP N00024-16-R-6405 has been amended via Amendment 1 to provide an updated Attachment 13B – Wage Determination and has been posted via FEDBIZOPS. In addition, an updated Attachment 13A – Wage Determination has also been posted via FEDBIZOPS.

Question 3: RFP N00024-26-R-6405, 24 Feb 2017, Page 131 of 152 - Para 4.2.3.2 Staffing Plan (Attachment 9A or 9B) advocates submission of a Staffing Plan (Attachment 9A or 9B – PDF File) - Using MS Excel. Does the government intend to provide Attachment 9A/9B in an Excel format?

ANSWER: RFP N00024-16-R-6405 has been amended via Amendment 1 to provide Attachments 9A and 9B Staffing Plans in excel formats and has been posted via FEDBIZOPS.

Question 4: RFP N00024-26-R-6405, 24 Feb 2017, Page 135 of 152 - Para 4.4.2 COST SUMMARY FORMAT (ATTACHMENT 6A or 6B – PDF File) advocates submission of Cost Summary Format (ATTACHMENT 6A or 6B) in Microsoft Excel spreadsheet format. Does the government intend to provide Attachment 6A/6B in an Excel format?

ANSWER: RFP N00024-16-R-6405 has been amended via Amendment 1 to provide Attachments 6A and 6B Cost Summary Format in excel formats and has been posted via

FEDBIZOPS.

Question 5: RFP N00024-26-R-6405, 24 Feb 2017, Attachment 11B, CDRL A001 (Work Management Plan), Block 12 of DD Form 1423 indicates that the first submission is to occur 7DAC. This is defined in DOD 5010-12-M as “If the, contract start date is not known, indicate the number of calendar days after contract (DAC) start that the data is due (e.g., "90 DAC")." In the Yorktown Statement of Work, Page 48 of 152, Paragraph B.3.1 Transition Planning and Execution – CLIN 5001, the third paragraph states "Prior to the start of the transition the contractor shall obtain Government approval of the Transition Plan CDRL A001." Does the

RFP N00024-16-R-6405 -- BIDDERS QUESTIONS AND ANSWERS

government require the Transition Plan CDRL A001 to be submitted with the Proposal Response contrary to CDRL A001 Block 12 and will the government review occur within 5 days of receipt and the contractor required to respond 10 days after review completion as indicated in Block 13 of CDRL A001?

ANSWER: RFP N00024-16-6405 has been amended via Amendment 1 to correct Section C, paragraphs A.3.1 and B.3.1 to delete the requirement to obtain GOV approval of the Transition Plan (CDRL A001) prior to commencing the Transition Period. The Transition Period will commence upon award and, the awardee can commence initial actions as outlined in paragraphs A.3.1 or B.3.1. The timeline for the final approval of CDRL A001 will be as outlined in the CDRL form (DD1423).

Question 6: RFP N00024-16-R-6405, 24 Feb 2017, Attachment 11B, the cover "Yorktown IMA Contract Data Requirements (CDRL) List” indicates that there are two CDRLs A001 and A002.

The particulars for CDRL A002 are not identified in Attachment 11B. Will the government provide DD Form 1423 for CDRL A002?

ANSWER: RFP N00024-16-6405 has been amended via Amendment 1 to correct Attachment 11B CDRLs and has been posted via FEDBIZOPS. In addition, Attachment 11A CDRLs has been corrected and has also been posted via FEDBIZOPS.

File details come from the government source that posted it. Updated .