Questions N00019-15-R-0106 UC-35 Contractor Logistics Support (CLS) RFP Questions and Answers
| # | Document | Question from Industry | Answers |
| 8 | FBO Amendment 0001 | Please advise when the Amendment 0001 will post to FebBizOps as stated in the questions posted on September 21, 2015? | RFP Amendment 0001 with the revised proposal due date of October 6, 2015, at 5:00 EST will be posted on FBO. |
| 10 | L-8 Price Matrix | L-8 Vol. 4 Price Matrix released in Amendment 001 dates for the Base Year does not match the Period of Performance stated in Section F. pg. 69 of the RFP. Please correct or clarify these dates. | The dates on the L-8 Vol. 4 Price Matrix (5/1/16 - 4/30/17) represents the PoP dates for all CLINs during the first year of contract performance, which includes: |
CLINs 0001-0006 (5/1/16-6/29/16) Transition Phase In CLINs 0007-0048 (6/30/16-4/30/17) Remaining CLINs
| 11 | Pratt & Whitney | Pratt & Whitney stated they do not provide Associate Contractor Agreements. Please advise. | Clause 5252.245-9520 will be removed in Amendment 2. Offerors are directed to PWS paragraph 3.3 |
| 12 | Pratt & Whitney | We need your assistance with the Associate Contractor Agreement as this is critical for our pricing. | Pricing is independent of the Associate Contractor Agreement. Pratt & Whitney has responded adequately to all offerors that have contacted them regarding price. Contact Pratt & Whitney again if you are having trouble. |
| 13 | Pratt & Whitney | We respectfully request an extension to accommodate the corrections and the Amendment impact to our proposal to 30 October 2015. | See Amendment 2. The deadline for proposals will be extended to 14 October 2015. |
| 14 | OEM Proposals | The OEM (Cessna and Pratt & Whitney) proposals have not been received. We respectfully request an extension to accommodate the corrections, the Amendment impact to our proposal, and the OEM pricing impact to our proposal, to 30 October 2015. | See Amendment 2. The deadline for proposals will be extended to 14 October 2015. |