A00F_DID OT-11-20017_C-9 Phase Out Transition Plan.doc
DOC document 48 KB Posted
- Attached to
- C-9B Contractor Logistics Support Federal contract opportunity
- Solicitation number
- N00019-10-R-0039
About this file
A00F_DID OT-11-20017_C-9 Phase Out Transition Plan
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title:
Phase-Out Transition Plan Number:
OT-11-20017
Approval Date:
20110707 AMSC Number:
N/A Limitation:
NA
DTIC Applicable:
N/A GIDEP Applicable:
N/A Office of Primary Responsibility:
PMA 207
Applicable Forms:
N/A
Use/relationship:
Phase-Out Transition Plan provides a detailed description of the transfer of full assumption of duties at each site, Airframe and Engine Depot to the follow-on contractor.
This Data Item Description (DID) contains format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract and described in the Performance Work Statement (PWS). It should be tailored to the minimum data requirements of the applicable contract or purchase order. This DID is for One-Time use for solicitation N00019-10-R-0039.
Requirements:
1. Format. Contractor format is acceptable.
2.
Content. The Phase-Out Transition Plan content shall include:
a. A written comprehensive plan explaining actions required to complete the total transition effort within a sixty (60) calendar day transition period.
b. Details of accounts and subscription services to be terminated or transferred.
c. Process to conduct a full joint inventory and transference of all Government Furnished Material inventory including all records.
d. Status of all items in inventory as well as the items that have been inducted into repair facilities, being modified or are being purchased.
e. Details for the removal of all contractor owned items.
f. Critical path schedule for risk mitigation of the transition period.
3. End of OT-11-20017