This document contains answers to questions from offerors on a federal solicitation for operations and maintenance services. The solicitation is for the Global Combat Support System - Marine Corps program to provide continued software development, operations, and maintenance support. Key details include:

  • The proposal due date was extended by one week to September 5, 2018 in response to an offeror question. The government intends for a fully functional solution development environment (SDE) to be established and maintained for five years under a separate contract line item if ordered. However, the period of performance for the SDE would not begin until completion of the transition-in period. Offerors are responsible for planning necessary work during transition to be ready to perform subsequent contract line items if ordered.

  • Clarification was provided that software licenses for a development instance of the system will be provided for use by the government during transition, but offerors are responsible for procuring their own licenses needed beyond that timeframe through separate ordering. The document provides answers to offeror questions on contract requirements and terms to inform their proposal submissions.

Q&A

View the file

Other files for this federal contract opportunity

Other files attached to Amendment 6, newest first.
File Type Posted
M6785418R7600-A0006_Amendment.pdf PDF
M6785418R7600-A0006_Conformed.pdf PDF
M67854-18-R-7600-A0005.pdf PDF
Question_Tracking_Matrix_A5.pdf PDF
Question_Tracking_Matrix_A4.pdf PDF
M67854-18-R-7600_Conformed_A0004.pdf PDF
M67854-18-R-7600-A0004.pdf PDF
H002.pdf PDF
M67854-18-R-7600_Conformed_A0003.pdf PDF
A001.pdf PDF
C001.pdf PDF
B003.PDF PDF
F001.pdf PDF
E002.pdf PDF
C003.PDF PDF
H001.pdf PDF
A002.PDF PDF
C004.pdf PDF
D002.pdf PDF
B001.pdf PDF
B002.pdf PDF
D003.pdf PDF
M67854-18-R-7600_A0003.pdf PDF
C002.pdf PDF
E001.PDF PDF
M67854-18-R-7600-A0002.pdf PDF
M67854-18-R-7600_-_Att_7_-_Perf_Incentive_Plan_A0002.pdf PDF
B001.pdf PDF
M67854-18-R-7600_Amend_0001.pdf PDF
M67854-18-R-7600_-_Attachment_8_-_QASP.pdf PDF
M67854-18-R-7600_-_Request_for_Proposal_(Base).pdf PDF
M67854-18-R-7600_-_Attachment_6_-_Case_Scenario.pptx PPTX presentation
M67854-18-R-7600_-_Attachment_3_-_Government_Furnished_Equipment.pdf PDF
M67854-18-R-7600_-_Exhibits.pdf PDF
M67854-18-R-7600_-_Attachment_1_-_List_of_Acronnyms.pdf PDF
M67854-18-R-7600_-_Attachment_9_-_PRS.xlsx XLSX spreadsheet
M67854-18-R-7600_-_Attachment_5_-_Past_Performance_Questionaire.docx DOCX document
M67854-18-R-7600_-_Attachment_7_-_Performance_Incentive_Plan.pdf PDF
M67854-18-R-7600_-_Attachment_4_-_GCSS-MC_PDSS_GFI_Request_and_NDA.DOC DOC document
M67854-18-R-7600_-_Attachment_2_-_GCSS-MC_PDSS_Tools.pdf PDF
M67854-18-R-7600_-_GCSS-MC_PDSS_-_2018-02-27.docx DOCX document
M67854-18-R-7600_-_Attachment_6_-_Scenario_1.pptx PPTX presentation
M67854-18-R-7600_-_Attachment_7_-_PDSS_CLIN_X001_Share_Lines.xlsx XLSX spreadsheet
M67854-18-R-7600_-_Attachment_8_-_MCSC_Vendor_Roster_for_LRC-template_FEB2018.xlsx XLSX spreadsheet
M67854-18-R-7600_-_Attachment_2_-_GCSS-MC_PDSS_Tools.docx DOCX document
M67854-18-R-7600_-_Attachment_9_-_MARCORSYSCOMO_5530.2_Badging_and_Building_Access_Order.pdf PDF
M67854-18-R-7600_-_Attachment_3_-_Government_Furnished_Equipment.docx DOCX document
M67854-18-R-7600_Attachment_5_Past_Performance_Questionnaire.docx DOCX document
M67854-18-R-7600_-_Attachment_4_-_GCSS-MC_PDSS_GFI_Request_and_NDA.DOC DOC document
M67854-18-R-7600_-_Attachment_1_-_List_of_Acronnyms.docx DOCX document
Show all 50

Amendment 6 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M67854‐18‐R‐7600 Questions and Answers Amendment 0003

Question Number Document/Section Paragraph/Reference Question/Issue/Concern Government Answer Amendment #

226 Solicitation Section L Paragraph L-6 Please increase the page count from 40 pages to 50 pages for Sec L-8.4 Vol III Factor 1 – Technical Approach to Service Operations, to accommodate responses required due to the the addition of PWS Paragraph 3.3

The page count will not be changed. 0003

227 Solicitation Section L Paragraph L-8.2A Reference to CLIN 4004

Please confirm Offerors are not to price CLIN 4004 and remove the reference to CLIN 4004 in the Continuation of Services description in Section L on pg 78 based on the following:Sec L-8.2A pg 78 (Continuation of Services Under FAR 52.217-8) –states, “The proposed values for the CLINs 4001, 4003, and 4004 will be used to calculate a total evaluated price for evaluation.” However, Section L-8.2 A on page 77 states, “CLINs 0004/1004/2004/3004/4004 Reserved, do not price.”

The reference to CLIN 4004 is removed from the Continuation of Services Under FAR 52.217-8 section. 0003

228 Solicitatoin Section L Paragraphs L8.4

Relative to questions 169 and 171 referenced below, please confirm that Offeror proposal response to the requirements of L.8.4 Volume III Factor 1 and L.8.5 Volume III Factors 2 and 3 will be compliant if we ONLY addresses the PWS items called out in section L.8.4 and L.8.5 (specifically PWS 3.2, 3.3, 3.8.2.1, 3.12, and 3.10) AND we include the statement as stated in Section L-8.1 A6• Ques #169 states:

Are offerors expected to respond to PWS items that are not evaluated?

Govt Answer: Offerors are required to submit their proposals in accordance with Section L of the RFP.

• Ques #171 states: The Government has included a number of PWS items that are not evaluated as part of the technical factors. Would it be sufficient for offerors to simply indicate the relevant capability in a checklist or chart in Volume III?

Govt Answer: See Section L-8.1 A6.

The awardee will be required to perform the entire requirements of the solicitation whether or not a specific requirement is evaluated during source selection. For proposal and evaluation purposes offerors are required to respond to the content requirements of Section L.

229 Amendment 0002 Question Clarification

1. Request the Government clarify the answers it provided to questions 49, 110, 153, and 197, summarized below, as they appear to contradict each other:

Question #49 - Will software licenses used for development purposes be provided as GFE. The response was no. Questi0n #110 - All available agreements can be provided contact Government contracting Question #153 - Will the Oracel Technology and Oracle Applicatoins agreements be included with the SDE? Response refers back to Question #110 Question #197 - Will sofware license include Oracle and non-Oracle cover the SDE build and on-going maintenance support. Respone refers back to Question #110.

Will all of the items liste din the "GCSS-MC_Provided_Software_SDE" be provided to the contracctor at the start of transition-in; or, will the contract be required to re-purchase and re-establish these items?

The items provided in "GCSS-MC_Provided_Software_SDE" referenced in Question #110 are for development capability directed by the Government in a "Support Instance" within the contractor provided SDE. These items will be provided at the start of the transition, if they are still required. If they are required beyond the transition, they will be negotiated with an additional task order.

230 Solicitation General Will the Government extend the proposal due date by one week? Yes. The proposal due date is changed to 5 September 2018. 0003

231 Section B Ordering Procedures

Please confirm CLIN 0003, the Solution Development Environment, will be awarded and funded with CLIN 0002, the Transition-In CLIN. Funding of CLIN 0003 at the beginning of the contract, will allow procurement of all required material associated with CLIN 0003, which is essential and must be stood up prior to the of the end of the transition period. Should the SDE CLIN be funded at a later date, it will result is substantial risk and schedule slips. Material would need to be procured in advance of authorization, resulting in pre contract costs

The Government's intention is for a 5 year period of performance for a fully functional SDE under CLIN 0003. If CLIN 0003 is ordered, the period of performance will not begin until the completion and exit of a successful "transition-in" period. It is the offeror's own business decision on how to account for any work that may be needed during the transition period to be ready to work on CLINS X001 and X003, if ordered.

File details come from the government source that posted it. Updated .