This is Amendment 04 to solicitation RFP LBNF-355802-JD for the Long-Baseline Neutrino Facility Argon Distribution IDIQ contract, issued on January 10, 2025. The amendment primarily notifies potential offerors of an administrative change regarding Fermilab's management transition from Fermi Research Alliance LLC to Fermi Forward Discovery Group LLC (FFDG) effective January 1, 2025, under DOE prime contract 89243024CSC000002.

The amendment replaces two key attachments: J-1 (General Terms and Conditions) and J-2 (Insurance Requirements), updating them to reflect the new management organization and including streamlined indemnity clauses and updated FAR/DEAR flow-downs. The proposal due date remains unchanged at January 17, 2025, 5:00 PM CST. The underlying project involves equipment for transferring gaseous and liquid argon throughout underground facilities at the Sanford Underground Research Facility (SURF), located 4,850 feet below surface level, in support of the Deep Underground Neutrino Experiment (DUNE) which requires approximately 70,000 tons of liquid argon across four cryostats.

View the file

Other files

File Type Posted
Amendment 06--RFP LBNF-355802-JD.pdf PDF
Amendment 05--RFP LBNF-355802-JD.pdf PDF
J-1 FFDG General Terms and Conditions for Subcontracts Combining Supplies and Services Performed at SURF (01.2025).pdf PDF
J-2 2025 INSURANCE REQUIREMENTS FOR FFDG SUBCONTRACTED WORK AT SURF Risk category 4 (Rev 01.pdf PDF
Amendment 03--RFP LBNF-355802-JD_Final.pdf PDF
Amendment 02--RFP LBNF-355802-JD 11-26-2024.pdf PDF
Amendment 01--RFP LBNF-355802-JD 10-05-2024.pdf PDF
J-4 - SOW Appendix B - Instructions for Downloading.docx DOCX document
J-1 General Terms and Conditions - Supplies and Services at SURF 10-23.pdf PDF
J-4 - Delivery Order 2 - Argon Distribution Uninsulated Pipes Valves SOW (1).pdf PDF
J-4 - IDIQ Task Order 1 and 2 - Appendix A - FORM_2_Rev_B.3_load_envelopes.pdf PDF
J-4 - SOW Appendice C - Instructions for Downloading.docx DOCX document
J-7 - Section 013300 Submittals_02-14-2024.pdf PDF
J-8 - Section 014100 Cryo Quality Requirements_2-16-2024.pdf PDF
Mandatory Site Visit Registration Questionnaire Sept 2024.docx DOCX document
J-13 - Section 01320 Project Schedule_Final 02-14-2024.pdf PDF
J-14 Wage Determination 2015-5377 Rev 26 07-22-2024.pdf PDF
J-3 SDSTA Risk Transfer Protocols with Exhibits Final.pdf PDF
J-4 - IDIQ - Argon Distribution Equipment SOW.pdf PDF
J-6 Section 010010 General Requirements Installation_Feb 2024.pdf PDF
J-15 Fixed Prices for Orders-04-25-2024 (1).xlsx XLSX spreadsheet
SMALL BUSINESS SUBCONTRACTING PLAN template Far 52.219-9.docx DOCX document
RFP LBNF-355802-JD Final 09-27-2024.pdf PDF
J-2 INSURANCE REQUIREMENTS FOR FRA SUBCONTRACTED WORK AT SURF Risk category 4 (Rev 2-2018)A.pdf PDF
J-4 - Delivery Order 1 - Argon Distribution VJ Pipes Valves SOW (2) (1).pdf PDF
J-5-Exhibit A.pdf PDF
FRA Safety Questionnaire (Rev. 08-17).pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT TO SOLICITATION

AMENDMENT NO.

DATE OF AMENDMENT:

January 10, 2025

SOLICITATION NO.

RFP LBNF-355802-JD

DATE ISSUED:

September 28, 2024

PROJECT NO.

N/A

PROPOSAL DUE DATE:

January 17, 2025

TITLE OF PROJECT:

LONG-BASELINE NEUTRINO FACILITY ARGON DISTRIBUTION IDIQ

Offerors must acknowledge this Addendum prior to the hour and date set forth in the solicitation by one of the following methods:

1. By completing the Subcontractor Annual Representations and Certifications (SARC), or

2. By separate fax, letter, or email.

If by virtue of this Addendum you desire to change a proposal already submitted, such change may be made by email, provided such email clearly references the Solicitation number and this Amendment number and is received prior to the proposal due date.

Amendment No. 4 is issued to:

1) Notify potential offerors of the following administrative change: As of 1 January 2025, day to day operation and management of Fermilab has transitioned from Fermi Research Alliance LLC to Fermi Forward Discovery Group LLC. Fermi Forward is the successor contractor for operation and management of the Fermi National Accelerator Laboratory (Fermilab) under prime contract number 89243024CSC000002 with the United States Department of Energy.

All references to Fermi Research Alliance or FRA within the RFP are hereby replaced with Fermi Forward Discovery Group or FFDG. Any award resulting from RFP LBNF-355802-JD will be issued by FFDG.

2) RFP Attachment J-1 [FRA General Terms and Conditions For Combining Supplies and Services Performed at SURF (03/2024)] is deleted and replaced with Attachment J-1 [FFDG General Terms and Conditions For Combining Supplies and Services Performed at SURF 01.2025]

A copy of the updated J-1 is provided with this Amendment. The key updates in these terms include:

• Entity name change to reflect the new M&O for Fermilab, Fermi Forward Discovery Group, LLC.

• A streamlined indemnity clause for clarity.

• The inclusion of new and updated FAR and DEAR flow downs.

3. RFP Attachment J-2 [Insurance Requirements for FRA Subcontracted Work at SURF—Risk Category 4 (08/2024)] is replaced with Attachment J-2 [Insurance Requirements for FFDG Subcontracted Work at SURF— Risk Category 4 (01.2025)] A copy of the updated J-2 is attached.

THE OFFER CLOSING DATE IS UNCHANGED AND REMAINS JANUARY 17, 2025 AT 5:00 P.M.

CENTRAL STANDARD TIME (CST-CHICAGO).

All other provisions remain unchanged.

Fermi Forward Discovery Group, LLC P.O. Box 500 Batavia, IL 60510 M.S 123

Jeremy Duncan LBNF Procurement Specialist

(865) 300-0443