IDIQ Pricing-Std
| Attachment J-15 |
| RFP LBNF-355802-JD |
| IDIQ Fixed Rates for Order Pricing |
| Offeror: | | | | | | | |
| Date: | | | | | | | |
| Unit of Measure | Fixed Rates--Standard | | | | | |
| Labor | | CY 2025 | CY2026 | CY2027 | CY2028 | CY2029 | CY2030 |
| Technician (FRA Site) | Hour | | | | | | |
| Technician (Offeror's Site) | Hour | | | | | | |
| Weld Technician | Hour | | | | | | |
| ES&H Representative | Hour | | | | | | |
| QA Representative | Hour | | | | | | |
| Foreman/Supervisor | Hour | | | | | | |
| Project Manager | Hour | | | | | | |
| Materials/Equipment | |
| Welding equipment | Day |
| Vacuum Pump | Day |
| Mass Spectrometry | Day |
| Mobile shop | Day |
| Welding equipment | Week |
| Vacuum Pump | Week |
| Mass Spectrometry | Week |
| Mobile shop | Week |
| Welding equipment | Month |
| Vacuum Pump | Month |
| Mass Spectrometry | Month |
| Mobile shop | Month |
IDIQ Pricing-Overtime
| Attachment J-15 |
| RFP LBNF-355802-JD |
| IDIQ Fixed Rates for Order Pricing |
| Offeror: | | | | | | | |
| Date: | | | | | | | |
| Unit of Measure | Fixed Rates--Overtime | | | | | |
| Labor | | CY 2025 | CY2026 | CY2027 | CY2028 | CY2029 | CY2030 |
| Technician (FRA Site) | Hour | | | | | | |
| Technician (Offeror's Site) | Hour | | | | | | |
| Weld Technician | Hour | | | | | | |
| ES&H Representative | Hour | | | | | | |
| QA Representative | Hour | | | | | | |
| Foreman/Supervisor | Hour | | | | | | |
| Project Manager | Hour | | | | | | |
| Materials/Equipment | |
| Welding equipment | Day |
| Vacuum Pump | Day |
| Mass Spectrometry | Day |
| Mobile shop | Day |
| Welding equipment | Week |
| Vacuum Pump | Week |
| Mass Spectrometry | Week |
| Mobile shop | Week |
| Welding equipment | Month |
| Vacuum Pump | Month |
| Mass Spectrometry | Month |
| Mobile shop | Month |
IDIQ Pricing-Holiday & Wknd
| Attachment J-15 |
| RFP LBNF-355802-JD |
| IDIQ Fixed Rates for Order Pricing |
| Offeror: | | | | | | | |
| Date: | | | | | | | |
| Unit of Measure | Fixed Rates--Holiday or Weekend | | | | | |
| Labor | | CY 2025 | CY2026 | CY2027 | CY2028 | CY2029 | CY2030 |
| Technician (FRA Site) | Hour | | | | | | |
| Technician (Offeror's Site) | Hour | | | | | | |
| Weld Technician | Hour | | | | | | |
| ES&H Representative | Hour | | | | | | |
| QA Representative | Hour | | | | | | |
| Foreman/Supervisor | Hour | | | | | | |
| Project Manager | Hour | | | | | | |
| Materials/Equipment | |
| Welding equipment | Day |
| Vacuum Pump | Day |
| Mass Spectrometry | Day |
| Mobile shop | Day |
| Welding equipment | Week |
| Vacuum Pump | Week |
| Mass Spectrometry | Week |
| Mobile shop | Week |
| Welding equipment | Month |
| Vacuum Pump | Month |
| Mass Spectrometry | Month |
| Mobile shop | Month |
Delivery Order 1 Pricing
| Attachment J-15 |
| RFP LBNF-355802-JD |
| Firm Fixed Price Proposal for IDIQ Delivery Order 1 |
| Offeror: | | | |
| Date: | | | |
| Delivery Order #1: Argon Distribution VJ Pipes and Valves | | | |
| Subcontract Line Item (SLIN) | Description | Fixed Price | Completion* |
| 1 | Engineering Phase Deliverables per SOW Section 13 | | |
| 2 | Manufacturing of VJ Pipes and Valves #1 | | |
| 3 | Manufacturing of VJ Pipes and Valves #2 | | |
| 4 | Shipping of VJ Pipes and Valves #1 | | |
| 5 | Shipping of VJ Pipes and Valves #2 | | |
| 6 | Installation and testing of VJ Pipes and Valves #1 | | |
| 7 | Installation and testing of VJ Pipes and Valves #2 | | |
| Total: | | | |
| *Completion dates should be stated in number of weeks After Receipt of Order (ARO). | | | |
Delivery Order 2 Pricing
| Attachment J-15 |
| RFP LBNF-355802-JD |
| Firm Fixed Price Proposal for IDIQ Delivery Order 1 |
| Offeror: | | | |
| Date: | | | |
| Delivery Order #2: Argon Distribution Uninsulated Pipes and Valves | | | |
| Subcontract Line Item (SLIN) | Description | Fixed Price | Completion* |
| 1 | Engineering Phase Deliverables per SOW Section 13 | | |
| 2 | Manufacturing and shipping of Argon/Nitrogen Uninsulated Pipes and Valves #1 | | |
| 3 | Manufacturing and shipping of Argon/Nitrogen Uninsulated Pipes and Valves #2 | | |
| 4 | Installation and testing of Nitrogen Uninsulated Pipes and Valves | | |
| 5 | Installation and testing of Uninsulated Pipes and Valves #1 | | |
| 6 | Installation and testing of Uninsulated Pipes and Valves #2 | | |
| Total: | | | |
| *Completion dates should be stated in number of weeks After Receipt of Order (ARO). | | | |