This is Standard Form 1408 (Rev. 1/2014), "Preaward Survey of Prospective Contractor (Accounting System)" form used to evaluate a potential contractor's accounting system prior to contract award.

The form contains two main sections: Section I for the overall recommendation and Section II with a detailed evaluation checklist. The checklist evaluates whether the accounting system follows generally accepted accounting principles and includes specific criteria like proper segregation of direct/indirect costs, timekeeping systems, labor distribution, cost accumulation under general ledger control, and compliance with FAR cost principles. The form requires evaluators to indicate if the system is acceptable for award through three options: "Yes," "Yes with recommendation for follow-on review," or "No." The form must be completed by a surveyor and reviewing official, with space provided for signatures, contact information and dates. This document appears to be a blank template form with an OMB control number 9000-0011 and expiration date of 10/31/2026.

View the file

Other files for this federal contract opportunity

Other files attached to Human Health and Performance Contract 2 (HHPC2), newest first.
File Type Posted
HHPC2 RFP 80JSC025R7001 Amendment 3.pdf PDF
80JSC025R7001 Amendment 3 SF30 01.22.25.pdf PDF
J-2 Contract Data Requirements List A3.pdf PDF
HHPC2 RFP 80JSC025R7001 Amendment 2.pdf PDF
J-2 Contract Data Requirements List A2.pdf PDF
HHPC2 RFP Questions and Answers 2.pdf PDF
L-2 Government Pricing Model (GPM) A2.xlsx XLSX spreadsheet
L-10 Pre-award Survey of Prospective Contractor Acct System Checklist A2.pdf PDF
80JSC025R7001 Amendment 2 SF30 01.16.25.pdf PDF
L-2 Government Pricing Model (GPM) A1.xlsx XLSX spreadsheet
HHPC2 RFP Questions and Answers A1.pdf PDF
J-2 Contract Data Requirements List A1.pdf PDF
80JSC025R7001 Amendment 1 SF30 12.20.24.pdf PDF
L-9 Prime_Subcontractor Identification and SOW Division of Work Listing Worksheet A1.xlsx XLSX spreadsheet
L-6 Past Performance Matrix A1.xlsx XLSX spreadsheet
J-16 Standard Labor Categories (SLCs) A1.pdf PDF
HHPC2 RFP 80JSC025R7001 Amendment 1.pdf PDF
L-10 Pre-award Survey of Prospective Contractor Accounting System Checklist.pdf PDF
HHPC2_Pre-Proposal_Conf_12-12-24.pdf PDF
Template for Submission of Comments.xlsx XLSX spreadsheet
L-5 Past Performance Consent Letters.pdf PDF
L-9 Prime_Subcontractor Identification and SOW Division of Work Listing Worksheet.xlsx XLSX spreadsheet
J-10 HHPC2 Performance Evaluation Plan.pdf PDF
J-2 Contract Data Requirements List.pdf PDF
L-1 Technical Approach - TA1_TA2_and TA3.pdf PDF
L-3 Small Business Subcontracting Tables.pdf PDF
J-16 Standard Labor Categories (SLCs).pdf PDF
J-49 CITAR Report Template.xlsx XLSX spreadsheet
HHPC2 RFP 80JSC025R7001.pdf PDF
L-2 Government Pricing Model (GPM).xlsx XLSX spreadsheet
L-4 Past Performance Questionnaire.pdf PDF
L-7 Key Personnel Resume.pdf PDF
J-3 Installation Accountable Government Property.pdf PDF
J-50 CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
J-1 Applicable Documents.pdf PDF
J-14 DD254.pdf PDF
J-11 Wage Determination WD 15-5233 and WD 15-5447.pdf PDF
L-6 Past Performance Matrix.xlsx XLSX spreadsheet
J-4 Government Furnished Property.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION I - RECOMMENDATION

YES

YES, WITH A RECOMMENDATION THAT A FOLLOW ON ACCOUNTING SYSTEM REVIEW BE PERFORMED AFTER CONTRACT AWARD (Explain in 2. NARRATIVE)

NO (Explain in 2. NARRATIVE)

PREAWARD SURVEY OF

PROSPECTIVE CONTRACTOR

(ACCOUNTING SYSTEM)

SERIAL NUMBER (For surveying activity use)

PROSPECTIVE CONTRACTOR

OMB Control Number: 9000-0011 Expiration Date: 10/31/2026

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0011. We estimate that it will take 24 hours to read the instructions, gather the facts, and answer the questions.

Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S.

General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

1. PROSPECTIVE CONTRACTOR'S ACCOUNTING SYSTEM IS ACCEPTABLE FOR AWARD OF PROSPECTIVE CONTRACT

2. NARRATIVE (Clarification of deficiencies and other pertinent comments. If additional space is required, continue on plain sheets of paper.)

IF CONTINUATION SHEETS

ATTACHED - MARK HERE

b. TELEPHONE NUMBER (include area code)

b. TELEPHONE NUMBER (include area code)

c. DATE SIGNED

c. DATE REVIEWED

3. SURVEY

MADE BY

4. SURVEY

REVIEWING

OFFICIAL

a. SIGNATURE AND OFFICE (Include typed or printed name)

a. SIGNATURE AND OFFICE (Include typed or printed name)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is NOT usable

STANDARD FORM 1408 (REV. 1/2014)

Prescribed by GSA - FAR (48 CFR) 53.209 -1(f)

SECTION II - EVALUATION CHECKLIST

MARK "X" IN THE APPROPRIATE COLUMN (Explain any deficiencies in SECTION I NARRATIVE) YES NO

NOT

APPLI-

CABLE

1. EXCEPT AS STATED IN SECTION I NARRATIVE, IS THE ACCOUNTING SYSTEM IN ACCORD WITH

GENERALLY ACCEPTED ACCOUNTING PRINCIPLES APPLICABLE IN THE CIRCUMSTANCES?

2. ACCOUNTING SYSTEM PROVIDES FOR:

a. Proper segregation of direct costs from indirect costs.

b. Identification and accumulation of direct costs by contract.

c. A logical and consistent method for the allocation of indirect costs to intermediate and final cost objectives. (A contract is final cost objective.)

d. Accumulation of costs under general ledger control.

e. A timekeeping system that identifies employees' labor by intermediate or final cost objectives.

f. A labor distribution system that charges direct and indirect labor to the appropriate cost objectives.

g. Interim (at least monthly) determination of costs charged to a contract through routine posting of books of account.

h. Exclusion from costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions.

i. Identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract.

j. Segregation of preproduction costs from production costs.

3. ACCOUNTING SYSTEM PROVIDES FINANCIAL INFORMATION:

a. Required by contract clauses concerning limitation of cost (FAR 52.232-20 and 21) or limitation on payments

(FAR 52.216-16).

b. Required to support requests for progress payments.

4. IS THE ACCOUNTING SYSTEM DESIGNED, AND ARE THE RECORDS MAINTAINED IN SUCH A MANNER THAT ADEQUATE, RELIABLE DATA ARE DEVELOPED FOR USE IN PRICING FOLLOW-ON ACQUISITIONS?

5. IS THE ACCOUNTING SYSTEM CURRENTLY IN FULL OPERATION?

(If not, describe in Section I Narrative which portions are

(1) in operation, (2) set up, but not yet in operation,

(3) anticipated, or (4) nonexistent.)

STANDARD FORM 1408 (REV. 1/2014) BACK

SECTION I - RECOMMENDATION

YES

YES, WITH A RECOMMENDATION THAT A FOLLOW ON ACCOUNTING SYSTEM REVIEW BE PERFORMED AFTER CONTRACT AWARD (Explain in 2. NARRATIVE) NO (Explain in 2. NARRATIVE)

PREAWARD SURVEY OF

PROSPECTIVE CONTRACTOR

(ACCOUNTING SYSTEM)

SERIAL NUMBER (For surveying activity use)

PROSPECTIVE CONTRACTOR

OMB Control Number: 9000-0011 Expiration Date: 10/31/2026 Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0011. We estimate that it will take 24 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

1. PROSPECTIVE CONTRACTOR'S ACCOUNTING SYSTEM IS ACCEPTABLE FOR AWARD OF PROSPECTIVE CONTRACT

2. NARRATIVE (Clarification of deficiencies and other pertinent comments. If additional space is required, continue on plain sheets of paper.)

IF CONTINUATION SHEETS

ATTACHED - MARK HERE

b. TELEPHONE NUMBER (include area code)

b. TELEPHONE NUMBER (include area code)

c. DATE SIGNED

c. DATE REVIEWED

3. SURVEY MADE BY

4. SURVEY REVIEWING OFFICIAL

a. SIGNATURE AND OFFICE (Include typed or printed name)

a. SIGNATURE AND OFFICE (Include typed or printed name)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is NOT usable

STANDARD FORM 1408 (REV. 1/2014)

Prescribed by GSA - FAR (48 CFR) 53.209 -1(f)

SECTION II - EVALUATION CHECKLIST

MARK "X" IN THE APPROPRIATE COLUMN (Explain any deficiencies in SECTION I NARRATIVE)

YES

NO

NOT APPLI-CABLE

1. EXCEPT AS STATED IN SECTION I NARRATIVE, IS THE ACCOUNTING SYSTEM IN ACCORD WITH GENERALLY ACCEPTED ACCOUNTING PRINCIPLES APPLICABLE IN THE CIRCUMSTANCES?

2. ACCOUNTING SYSTEM PROVIDES FOR:

a. Proper segregation of direct costs from indirect costs.

b. Identification and accumulation of direct costs by contract.

c. A logical and consistent method for the allocation of indirect costs to intermediate and final cost objectives. (A contract is final cost objective.)

d. Accumulation of costs under general ledger control.

e. A timekeeping system that identifies employees' labor by intermediate or final cost objectives.

f. A labor distribution system that charges direct and indirect labor to the appropriate cost objectives.

g. Interim (at least monthly) determination of costs charged to a contract through routine posting of books of account.

h. Exclusion from costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions.

i. Identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract.

j. Segregation of preproduction costs from production costs.

3. ACCOUNTING SYSTEM PROVIDES FINANCIAL INFORMATION:

a. Required by contract clauses concerning limitation of cost (FAR 52.232-20 and 21) or limitation on payments (FAR 52.216-16).

b. Required to support requests for progress payments.

4. IS THE ACCOUNTING SYSTEM DESIGNED, AND ARE THE RECORDS MAINTAINED IN SUCH A MANNER THAT ADEQUATE, RELIABLE DATA ARE DEVELOPED FOR USE IN PRICING FOLLOW-ON ACQUISITIONS?

5. IS THE ACCOUNTING SYSTEM CURRENTLY IN FULL OPERATION?(If not, describe in Section I Narrative which portions are

(1) in operation, (2) set up, but not yet in operation,

(3) anticipated, or (4) nonexistent.)

STANDARD FORM 1408 (REV. 1/2014) BACK

8.2.1.3144.1.471865.466429 Standard Form 1408 - Pre-Award Survey of Prospective Contractor (Accounting System)

PROSPECTIVE CONTRACTOR:
IF CONTINUATION SHEETS ATTACHED - MARK HERE: 0
1. PROSPECTIVE CONTRACTOR'S ACCOUNTING SYSTEM IS ACCEPTABLE FOR AWARD OF PROSPECTIVE CONTRACT. YES: 0
1. PROSPECTIVE CONTRACTOR'S ACCOUNTING SYSTEM IS ACCEPTABLE FOR AWARD OF PROSPECTIVE CONTRACT. YES, WITH A RECOMMENDATION THAT A FOLLOW ON ACCOUNTING SYSTEM REVIEW BE PERFORMED AFTER CONTRACT AWARD (Explain in 2. NARRATIVE): 0
1. PROSPECTIVE CONTRACTOR'S ACCOUNTING SYSTEM IS ACCEPTABLE FOR AWARD OF PROSPECTIVE CONTRACT. NO (Explain in 2. NARRATIVE): 0
SERIAL NUMBER (For surveying activity use):
2. NARRATIVE (Clarification of deficiencies, and other pertinent comments,. If additional space is required, continue on plain sheets of paper.):
4. SURVEY REVIEWING OFFICIAL. a. SIGNATURE AND OFFICE (include, typed or printed name) (Typed name):
3. SURVEY MADE BY. a. SIGNATURE AND OFFICE (include, typed or printed name) (Typed name):
c. DATE REVIEWED. Enter 2 digit month, 2 digit day and 4 digit year.:
c. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:
b. TELEPHONE NUMBER (include area code):
b. TELEPHONE NUMBER (include area code):
4. Survey Reviewing Official. (a) Signature and Office. Sign here if you are the Survey Reviewing Official.:
1. EXCEPT AS STATED IN SECTION I NARRATIVE, IS THE ACCOUNTING SYSTEM IN ACCORD WITH GENERALLY ACCEPTED ACCOUNTING PRINCIPLES APPLICABLE IN THE CIRCUMSTANCES? YES.: 0
a. Proper segregation of direct costs from indirect costs. YES.: 0
b. Identification and accumulation of direct costs by contract. YES.: 0
c. A logical and consistent method for the allocation of indirect costs to intermediate and final cost objectives. (A contract is final cost objective.) YES.: 0
1. EXCEPT AS STATED IN SECTION I NARRATIVE, IS THE ACCOUNTING SYSTEM IN ACCORD WITH GENERALLY ACCEPTED ACCOUNTING PRINCIPLES APPLICABLE IN THE CIRCUMSTANCES? NO.: 0
a. Proper segregation of direct costs from indirect costs. NO.: 0
b. Identification and accumulation of direct costs by contract. NO.: 0
c. A logical and consistent method for the allocation of indirect costs to intermediate and final cost objectives. (A contract is final cost objective.) NO.: 0
1. EXCEPT AS STATED IN SECTION I NARRATIVE, IS THE ACCOUNTING SYSTEM IN ACCORD WITH GENERALLY ACCEPTED ACCOUNTING PRINCIPLES APPLICABLE IN THE CIRCUMSTANCES? NOT APPLICABLE.: 0
a. Proper segregation of direct costs from indirect costs. NOT APPLICABLE.: 0
b. Identification and accumulation of direct costs by contract. NOT APPLICABLE. : 0
c. A logical and consistent method for the allocation of indirect costs to intermediate and final cost objectives. (A contract is final cost objective.) NOT APPLICABLE. : 0
d. Accumulation of costs under general ledger control. YES.: 0
e. A timekeeping system that identifies employees' labor by intermediate or final cost objectives. NOT APPLICABLE.: 0
f. A labor distribution system that charges direct and indirect labor to the appropriate cost objectives. YES.: 0
g. Interim (at least monthly) determination of cost charged to a contract through routine posting of books of account. NOT APPLICABLE.: 0
h. Exclusion from costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions. YES.: 0
i. Identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract. NOT APPLICABLE.: 0
j. Segregation of preproduction costs from production costs. YES.: 0
a. Required by contract clauses concerning limitation of cost (FAR 52.232-20 and 21) or limitation on payments (FAR 52.216-16). NOT APPLICABLE.: 0
b. Required to support request for progress payments. YES : 0
4. IS THE ACCOUNTING SYSTEM DESIGNED, AND ARE THE RECORDS MAINTAINED IN SUCH A MANNER THAT ADEQUATE, RELIABLE DATA ARE DEVELOPED FOR USE IN PRICING FOLLOW-ON ACQUISITIONS? NOT APPLICABLE.:
5. IS THE ACCOUNTING SYSTEM CURRENTLY IN FULL OPERATION? YES

(If not, describe in Section I Narrative which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) nonexistent.): 0

5. IS THE ACCOUNTING SYSTEM CURRENTLY IN FULL OPERATION? NO

(If not, describe in Section I Narrative which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) nonexistent.) : 0

5. IS THE ACCOUNTING SYSTEM CURRENTLY IN FULL OPERATION? NOT APPLICABLE

(If not, describe in Section I Narrative which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) nonexistent.) : 0

4. IS THE ACCOUNTING SYSTEM DESIGNED, AND ARE THE RECORDS MAINTAINED IN SUCH A MANNER THAT ADEQUATE, RELIABLE DATA ARE DEVELOPED FOR USE IN PRICING FOLLOW-ON ACQUISITIONS? NO.: 0
4. IS THE ACCOUNTING SYSTEM DESIGNED, AND ARE THE RECORDS MAINTAINED IN SUCH A MANNER THAT ADEQUATE, RELIABLE DATA ARE DEVELOPED FOR USE IN PRICING FOLLOW-ON ACQUISITIONS? YES: 0
b. Required to support request for progress payments. NO.: 0
b. Required to support request for progress payments. NOT APPLICABLE.: 0
a. Required by contract clauses concerning limitation of cost (FAR 52.232-20 and 21) or limitation on payments (FAR 52.216-16). NO.: 0
a. Required by contract clauses concerning limitation of cost (FAR 52.232-20 and 21) or limitation on payments (FAR 52.216-16). YES.: 0
j. Segregation of preproduction costs from production costs. NO.: 0
j. Segregation of preproduction costs from production costs. NOT APPLICABLE.: 0
i. Identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract. NO.: 0
i. Identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract. YES.: 0
h. Exclusion from costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions. NO.: 0
h. Exclusion from costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions. NOT APPLICABLE.: 0
g. Interim (at least monthly) determination of cost charged to a contract through routine posting of books of account. NO. : 0
g. Interim (at least monthly) determination of cost charged to a contract through routine posting of books of account. YES.: 0
f. A labor distribution system that charges direct and indirect labor to the appropriate cost objectives. NO.: 0
f. A labor distribution system that charges direct and indirect labor to the appropriate cost objectives. NOT APPLICABLE.: 0
e. A timekeeping system that identifies employees' labor by intermediate or final cost objectives. NO.: 0
e. A timekeeping system that identifies employees' labor by intermediate or final cost objectives. YES.: 0
d. Accumulation of costs under general ledger control. NO.: 0
d. Accumulation of costs under general ledger control. NOT APPLICABLE. : 0