This document contains a Justification and Approval (J&A) for using other than full and open competition to acquire door locksets from Corbin Russwin for the "Renovate Laboratory B310" project at the Dayton VA Medical Center. The J&A cites 41 USC 3304(a)(1) and FAR 6.302-1 as the authority for this limited competition, as Corbin Russwin locksets are used throughout the Medical Center campus requiring standardization. The facility has thousands of doors requiring a seven pin Corbin Russwin core for compatibility with the existing master key system. Market research found no other manufacturers able to meet this requirement. The anticipated cost to the government is deemed fair and reasonable based on commercial pricing and competition.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OFOC SOP Revision 09 Page 1 of 2 Original Date: 03/22/11 Revision 09 Date: 04/17/2020
DEPARTMENT OF VETERANS AFFAIRS
Justification and Approval (J&A) For
Other Than Full and Open Competition (>SAT)
Acquisition Plan Action ID: 36C250-20-AP-1390
1. Contracting Activity: Department of Veterans Affairs, NCO 10, Dayton VA Medical Center 2237: 552-20-2-6932-0006
2. Nature and/or Description of the Action Being Processed:
The requirement for the contractor to use Corbin Russwin for the “Renovate Laboratory B310”.
Project Number 552-18-101.
3. Description of Supplies/Services Required to Meet the Agency’s Needs:
As part of the project the Renovate Laboratory B310 project area will be receiving new door locksets. A master key system has been established at the Dayton VAMC. New lockset cylinders must be able to accommodate the existing master key system that used the seven pin Corbin Russwin core.
4. Statutory Authority Permitting Other than Full and Open Competition:
41 USC §3304(a)(1), as implemented by FAR 6.302-1.
( X ) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements per 41 USC §3304(a)(1) as implemented by FAR 6.302-1
5. Demonstration that the Contractor’s Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority):
Corbin Russwin locksets are used throughout the Medical Center to achieve integration across all the campus buildings.
6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable:
The facility has thousands of doors and each lockset must be able to accommodate a seven pin Corbin Russwin core for standardization purposes. This solicitation will be publicized via Contracting Opportunities on www.beta.sam.gov.
7. Determination by the CO that the Anticipated Cost to the Government will be Fair and Reasonable:
The best interests of the government are served through the use of this product. The pricing will be provided as part of equipment available in the commercial marketplace. The price will be determined to be fair and reasonable to the government based on competition.
8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons Market Research Was Not Conducted:
Multiple manufacturers produce can provide devices that are compatible with the Edwards/EST fire system, e.g., sirens and visual alarms, The exceptions associated with the J&A are the device’s that
OFOC SOP Revision 09 Page 2 of 2 Original Date: 03/22/11 Revision 09 Date: 04/17/2020 are addressable, e.g., smoke detectors, heat detectors, and pull stations, and these devices will need to be provided by the original equipment manufacturer.
9. Any Other Facts Supporting the Use of Other than Full and Open Competition:
N/A
10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition:
N/A
11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any Barriers to Competition before Making subsequent acquisitions for the supplies or services required:
No action can be taken in the circumstances due to the equipment being under warranty and the need to maintain this warranty. The VA will continue to review the martketplace during future construction initiatives to determine if products have become available which meet the needs of the
VA.
12. Requirements Certification: I certify that the requirement outlined in this justification is a Bona Fide Need of the Department of Veterans Affairs and that the supporting data under my cognizance, which are included in the justification, are accurate and complete to the best of my knowledge and belief.
Ravindra R. Wani Date Project Engineer/COR Dayton VAMC - Engineering
13. Approvals in accordance with the VHAPM Part 806.3 OFOC SOP:
a. Contracting Officer or Designee’s Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.
Diana J. Pittman Date Contracting Officer
NCO 10
Ravindra R.
Wani 344872
Digitally signed by Ravindra R. Wani 344872 Date: 2020.07 08 07:53:43 -04'00'
Diana J.
Pittman 251505
Digitally signed by Diana J.
Pittman 251505 Date: 2020 08.07 13 33:54 -04'00' 8/7/20