About this file

This document contains a preliminary project milestone schedule for the Milwaukee Federal Building and US Courthouse Fire Life Safety project. The schedule outlines key project tasks and milestones from project initiation in January 2015 through projected completion in March 2024. It includes phases for planning, design, construction management agent acquisition, construction manager at risk acquisition, design development through 100% construction documents, construction, substantial completion, and closeout. Major milestones include requirements finalization by December 2018, design proposal receipt by December 2019, construction notice to proceed by December 2021, substantial completion target of October 2023, and project complete by March 2024. The schedule provides task names, expected durations, start and finish dates, and dependencies to coordinate the various project phases over the multi-year timeline.

The related federal contract opportunity is a solicitation by the General Services Administration Public Buildings Service Region 5 for construction management services as the construction manager at risk for the Milwaukee Federal Building and US Courthouse Fire Life Safety project. Offerors should refer to the request for proposal attachments for additional requirement details. The solicitation provides information on the opportunity type, a brief project description, and the issuing federal agency.

View the file

Other files

Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Calendar

Days

Duration Start Finish Predecessors

1 Planning 1 1153 days Thu 1/1/15 Mon 6/3/19

2 Customer Request 1 1 day Thu 1/1/15 Thu 1/1/15

3 Project Initiated 1 1 day Thu 1/1/15 Thu 1/1/15

4 Initial Requirements 1 1 day Wed 8/15/18 Wed 8/15/18

5 Requirements Finalized 1 1 day Fri 12/14/18 Fri 12/14/18

6 Project Re-initiated 1 1 day Mon 6/3/19 Mon 6/3/19

7 Authority/Funding 0 559 days Wed 5/17/17 Mon 7/8/19

8 Prospectus Submitted 1 1 day Wed 5/17/17 Wed 5/17/17

9 Congressional Appropriation 1 1 day Mon 7/8/19 Mon 7/8/19

10 Pre-Design/AE Acquisition 0 401 days Thu 9/27/18 Thu 4/9/20

11 Acquisition Plan (Original D/B) 1 1 day Thu 9/27/18 Thu 9/27/18

12 A/E Scope of Work/IGCE 57 41 days Wed 6/19/19 Wed 8/14/19

13 Design RFP Sent 1 1 day Wed 10/2/19 Wed 10/2/19

14 Design Proposal Received 1 1 day Thu 12/5/19 Thu 12/5/19 13

15 Negotiation 99 71 days Fri 12/6/19 Fri 3/13/20 14

16 Design PR Submitted 1 1 day Fri 3/13/20 Fri 3/13/20 15

17 Contracting Accepts PR 1 1 day Mon 3/16/20 Mon 3/16/20 16

18 A/E Award/NTP 1 1 day Tue 3/24/20 Tue 3/24/20 17

19 Post Award/Kick-Off Meeting 1 1 day Thu 4/9/20 Thu 4/9/20 18

20 CMa Acquisition 0 156 days Tue 3/31/20 Tue 11/3/20

21 CMa Acquisition Plan 1 1 day Tue 3/31/20 Tue 3/31/20

22 CMa Scope of Work 1 1 day Thu 4/16/20 Thu 4/16/20

23 CMa RFP Sent 1 1 day Thu 4/30/20 Thu 4/30/20

24 CMa Proposals Received 1 1 day Mon 6/1/20 Mon 6/1/20

25 Review and Negotiation 132 94 days Thu 6/4/20 Tue 10/13/20

26 CMa PR Submitted 1 1 day Thu 10/15/20 Thu 10/15/20

27 Contracting Accepts PR 1 1 day Mon 10/19/20Mon 10/19/20

28 CMa Award/NTP 1 1 day Mon 10/26/20Mon 10/26/20

29 CMa Kick-Off Meeting 1 1 day Tue 11/3/20 Tue 11/3/20

30 CMc Acquisition 1 144 days Mon 9/28/20 Thu 4/15/21

31 CMc Acquisition Plan 1 1 day Mon 9/28/20 Mon 9/28/20

32 CMc Scope of Work/Package 1 1 day Fri 10/16/20 Fri 10/16/20

33 CMc Synopsis Issued 1 1 day Fri 11/20/20 Fri 11/20/20

34 CMc RFP Sent 1 1 day Mon 12/7/20 Mon 12/7/20

35 CMc Proposals Due 1 1 day Mon 1/18/21 Mon 1/18/21

36 SSEB 4 4 days Mon 1/25/21 Thu 1/28/21

37 Negotiation 43 31 days Mon 2/1/21 Mon 3/15/21

38 CMc PR Submitted 1 1 day Mon 3/22/21 Mon 3/22/21

39 Contracting Accepts PR 1 1 day Fri 3/26/21 Fri 3/26/21

40 CMc Base (Pre-Con) Award 1 1 day Fri 4/9/21 Fri 4/9/21

41 CMc Kick-Off Meeting 1 1 day Thu 4/15/21 Thu 4/15/21

42 Design 1 367 days Thu 4/9/20 Fri 9/3/21

43 Design Start 1 1 day Thu 4/9/20 Thu 4/9/20

44 Security Clearance 90 64 days Fri 4/10/20 Wed 7/8/20

45 Full Building Survey 4 4 days Mon 7/13/20 Thu 7/16/20

46 15% Concept Design Package 109 79 days Tue 6/16/20 Fri 10/2/20

47 GSA Review 21 15 days Tue 10/6/20 Mon 10/26/20

48 Commissioners's Presentation/DE Peer

Review

1 1 day Tue 10/27/20 Tue 10/27/20

49 Pre-Alteration Assessment 5 5 days Mon 11/2/20 Fri 11/6/20

50 35% Design Development Package 113 81 days Tue 10/27/20 Tue 2/16/21

51 GSA Review 21 15 days Wed 2/17/21 Tue 3/9/21

52 Value Management Session #1 1 1 day Wed 2/17/21 Wed 2/17/21

53 Art in Architecture Award 1 1 day Thu 4/1/21 Thu 4/1/21

54 50% CD Submission 44 32 days Thu 4/1/21 Fri 5/14/21

55 GSA Review 19 15 days Mon 5/17/21 Fri 6/4/21

56 Value Management Session #2 1 1 day Mon 5/17/21 Mon 5/17/21

57 90% CD Submission 43 31 days Fri 6/4/21 Fri 7/16/21

58 GSA Review 21 15 days Fri 7/16/21 Thu 8/5/21

59 Historic Submital to SHPO 1 1 day Thu 8/5/21 Thu 8/5/21

60 100% CD Submission 30 22 days Thu 8/5/21 Fri 9/3/21

61 Construction Documents Complete 0 0 days Fri 9/3/21 Fri 9/3/21

62 Construction 1 636 days Fri 10/15/21 Fri 3/22/24

63 Construction Option Award 0 0 days Fri 10/15/21 Fri 10/15/21

64 CMc Security Clearances 58 42 days Mon 10/18/21Tue 12/14/21

65 Construction NTP 1 1 day Tue 12/14/21 Tue 12/14/21

66 Construction Period 661 473 days Tue 12/14/21 Thu 10/5/23

67 Substantial Completion 0 0 days Thu 10/5/23 Thu 10/5/23

68 Project Closeout 170 122 days Thu 10/5/23 Fri 3/22/24

69 Project Complete 0 0 days Fri 3/22/24 Fri 3/22/24

9/3

10/15

10/5

3/22

Dec JanFebMarAprMayJun Jul AugSepOctNovDec Jan FebMarAprMayJun Jul AugSepOctNovDec JanFebMarAprMayJun Jul AugSep OctNovDec JanFebMarAprMayJun Jul AugSep OctNovDec JanFebMarAprMayJun Jul AugSepOctNovDec Jan FebMarAprMayJun Jul AugSepOctNovDec JanFebMarAprMayJun Jul AugSepOctNovDec JanFebMarAprMayJun Jul AugSep OctNovDec JanFebMarAprMayJun Jul AugSepOctNovDec Jan FebMarAprMayJun

4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter