This solicitation is for a Construction Manager as Constructor (CMc) for fire life safety construction projects at the Milwaukee Federal Building and US Courthouse. The General Services Administration Public Buildings Service Region 5 is seeking a CMc to provide preconstruction and construction phase services. Key responsibilities for the CMc include cost estimating, scheduling, value engineering, and construction administration. The CMc will work under a guaranteed maximum price contract. The response due date for proposals was March 15, 2021, with a planned award date of April 15, 2021. The period of performance is 1,095 calendar days for construction following NTP. The solicitation includes relevant project background, scope of work details, proposal instructions, and evaluation criteria.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Milwaukee Federal Building and U.S.
Courthouse Fire Protection and Life Safety Upgrades
U.S. General Services Administration Great Lakes Region
DESIGN NARRATIVE
Design Development Submission
Project Number: 60630200
February 15, 2021
SENSITIVE BUT UNCLASSIFIED (SBU)
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice
Properly destroy or return documents when no longer needed
Milwaukee Fire and Life Safety Upgrades
FOR OFFICIAL USE ONLY
Do not remove this notice
Prepared for:
Attn: Tim Hansmann, AIA U.S. General Services Administration Design and Construction Division 517 East Wisconsin Ave., Suite 232 Milwaukee, WI 53202
Contract Number: GS-05P-15-FA-D-0005
Task Number: 47PF0020F0426
Project Location: Milwaukee Federal Courthouse 517 East Wisconsin Ave.
Milwaukee, WI 53202
Prepared by:
1300 East 9th Street Suite 500 Cleveland, OH 44114 www.aecom.com
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | iii
Table of Contents
1.0 Executive Summary
Building Information Scope of Work Project Schedule
2.0 Design Requirements
References Design Criteria Implementation Plan and Phasing Demolition Commissioning LEED Registration and Certification Quality Assurance and Quality Control Warranties Building Tenant Impact
3.0 Option #1: Fire Alarm System Replacement
General Requirements Fire Alarm Electrical Fire Command Center Historic Preservation Environmental Logistics Planning
4.0 Options #2 - #11: New Sprinklers in Non-Sprinkler-Protected Areas General Requirements Fire Protection Historic Preservation Environmental Logistics Planning
5.0 Option #12: Replace Sprinklers in the Historic Corridors
General Requirements Fire Protection Historic Preservation Environmental Logistics Planning
6.0 Cost Estimate
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | iv
APPENDICES
Appendix A - Project Team Contact List Appendix B - Historic Preservation Room Survey Appendix C - Meeting Minutes
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 5
1.0 Executive Summary
Building Information
The Federal Building and U.S. Courthouse in Milwaukee was originally constructed between 1892 and 1899 to house the U.S. Postal Service, Courts, and Customs Service. Major additions to the building transpired in both 1932 and 1940 resulting in the building that stands today.
An extensive restoration and renovation project was started in 1989 and completed in 1996, which restored much of the historic interior of the building to its original condition while incorporating contemporary office needs.
The Milwaukee Federal Courthouse is listed on the National Register of Historic Places.
Scope of Work
This project includes the design and construction of a complete fire alarm system replacement and to integrate other projects into this one to achieve a complete building protection system. The goal of this project is to improve life safety and reduce risk to the occupants, the building, and the environment at the Milwaukee Federal Building and U.S. Courthouse. The project will be delivered utilizing a Construction Manager as constructor (CMc). The scope of work includes the following:
Base Bid – Design Phase Services Option #1 – Fire Alarm Replacement and Abatement Option #2 – Add sprinklers to unprotected rooms in Sub-Basement Option #3 – Remove and replace Omega sprinklers in Basement Option #4 – Add sprinklers to unprotected rooms in Basement Option #5 – Add sprinklers to unprotected Mechanical and Storage Rooms (1st – 7th Floors) Option #6 – Add sprinklers to unprotected spaces & elevator lobbies on 1st Floor Option #7 – Add sprinklers to unprotected spaces & elevator lobbies on 2nd Floor Option #8 – Add sprinklers to unprotected spaces & elevator lobbies on 3rd Floor Option #9 – Add sprinklers to unprotected spaces & elevator lobbies on 4th Floor Option #10 – Add sprinklers to unprotected spaces & elevator lobbies on 5th Floor Option #11 – Add sprinklers to unprotected spaces & elevator lobbies on 7th Floor Option #12 – Remove and replace sidewall sprinkler heads in Historic Corridors
Base Bid: Design Phase Services
The Construction Manager as constructor will assist the team during the design phase of the project to coordinate the design approach, phasing, construction costs, and investigative demolition.
Option #1: Fire Alarm System Replacement Summary
The project scope of work includes the design and installation of a new fully addressable fire detection and voice evacuation fire alarm system. Because of the locations of the existing fire alarm and notification devices in the building (or lack thereof) and the age of the existing fire alarm system, the entire fire alarm and notification system in the building shall be replaced. The new fire alarm panel will be independent of
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 6 the existing fire alarm system and not monitored offsite until the new panel is fully accepted by the AHJ.
Only at this time will the new fire alarm system be monitored by a central station alarm service. Upon acceptance of the new system, the existing fire alarm system shall be completely removed. Throughout the installation and removal process, abatement of Asbestos-Containing Materials (ACM) and Lead- Based Paint (LBP) impacted by the construction works shall be undertaken in the installation of the new system. Similar to the abatement of ACMs and LBP, the historic building elements that are directly impacted by the installation of the new detection and voice evacuation fire alarm system shall be preserved and restored.
Options #2-#11: New Sprinklers in Non-Sprinkler-Protected Areas Summary
The project scope of work also includes the design and installation of sprinklers in areas on various levels in the building, including the replacement of Omega Type, On-Off type sprinklers located in select mechanical spaces and correction of existing sprinkler spacing issues in the Basement and Sub- Basement levels. This includes removal, recalculating, re-engineering and installation of new sprinklers and sprinkler piping as needed to properly protect the mechanical and storage spaces per the requirements of PBS-P100 and NFPA 13. Sprinklers installed in elevator rooms, electrical switchgear room and transformer vaults will be provided with separate manual isolation valves and separate water flow switches located outside the room in an accessible location. Tamper switches will be provided on all such valves.
Similar to the fire alarm replacement work, abatement of ACM and LBP impacted by the construction works will be undertaken in the installation of the new sprinklers. Again, the historic building elements that are directly impacted by the installation of the sprinklers will be preserved and restored, paying special attention to ceiling conditions.
Option #12: Replace Sprinklers in Historic Corridors Summary
Lastly, the project scope of work includes the replacement of all existing sprinklers within Historic Corridors, and only the Historic Corridors, with quick response sprinklers. See the Construction Documents for the sprinkler locations. Similar to all other work, abatement of ACM and LBP impacted by the construction works will be undertaken in the installation of the new sprinklers. Again, the historic building elements that are directly impacted by the installation of the new sprinklers will be preserved and restored, paying special attention to ceiling conditions.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 7
Project Schedule
The project design is estimated to be completed by September 2021, and the project construction period is scheduled to occur between October 2021 and December 2023. The overall project schedule is provided below:
Project Award………………………………………..Mar. 26, 2020
15% Concept Design Submission..........…………Oct. 2, 2020
35% Design Development Submission………….. Feb. 15, 2021
50% CD Submission…......................................... May 14, 2021
90% CD Submission................................………..July 15, 2021
100% CD Submission…………............................ Sep. 3, 2021
NTP for Construction………………………………. Oct. 15, 2021
Substantial Completion……………………………. Dec. 15, 2023
Project Completion / Close-Out……………………Mar. 31, 2024
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 8
2.0 Design Requirements
References
All work under this contract will comply and/or reference the following standards, codes, and publications:
GSA PBS P100, Facilities Standards for the Public Buildings Service, dated 2018 – Mandatory Particular attention is directed to Chapter 7 Fire Protection and all applicable subsections.
https://www.gsa.gov/cdnstatic/2018%20P100%20Final%20Updated%207-26-18.pdfArchitectural Barriers Act Accessibility Standard (ABAAS). If local accessibility standards exist, the A/E OR must follow the most stringent requirements between the local standards and ABAAS.
International Fire Code, 2015 Edition National Fire Protection Association (NFPA) 101, Life Safety Code, 2018 Edition NFPA 13, Standard for the Installation of Sprinkler Systems, 2016 Edition NFPA 70, National Electrical Code, 2017 Edition NFPA 72, National Fire Alarm and Signaling Code, 2016 Edition NFPA 80, Standard for Fire Doors and Other Opening Protectives, 2016 Edition GSA/PBS P-120, Project Estimating Requirements for the Public Buildings Service, latest edition GSA Project Cost Estimating Tool (Uniformat), latest edition General Construction Cost Review Guide for Federal Office Buildings and Courthouses Cost
Benchmark Tool, latest edition Guiding Principles for Federal Leadership in High-Performance and Sustainable Buildings
(Federal Energy Management Program 2016), Shell/Tenant Improvement Definition from the GSA Pricing Desk Guide, latest edition Technology Policy for PBS-Owned Buildings Monitoring and Control Systems (March 31, 2011) Historic Structures Report prepared by the Durrant Group, Inc. for GSA (1981) Supplemental Report on Decorative Painting Analysis Investigation and Documentation prepared by Conrad Schmitt Studios, Inc. (1989) GSA Building Preservation Plan Update prepared by Beyer Blinder Belle Architects & Planners, LLP (2009)
Standards for Rehabilitation, Secretary of the Interior Building Design Standards, which was created through a partnership of GSA Great Lakes Region and Skidmore, Owings & Merrill, LLP (2015) The original construction drawings and select drawings from later work which are held in the basement of the Milwaukee Federal Building, Office of the Building Manager. A list of available drawings is noted in the 2009 Building Preservation Plan.
CCA Asbestos Site Survey Report (2005) Pre-Alteration Assessment Guidance, GSA Region 5, Facilities Management & Service Programs
Division, February 2017 revision GSA PBS P-120, Project Estimating Requirement for the Public Buildings Service, January 2007 Cost Estimating Workbook (CEW) Cost Benchmark Tool, latest edition GSA PBS 3490.2, Document Security for Sensitive but Unclassified Building Information, latest version
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 9
GSA Vendor Fitness Determination Training Manual PBS National Environmental Policy Act Desk Guide:
https://www.gsa.gov/real-estate/environmental-programs/gsa-nepa-implementation/pbs-nepa-deskguide
GSA standards and guidelines can be downloaded from the following web sites:
www.gsa.gov
Whole Building Design Guide’s website.
http://www.wbdg.org/ccb/browse_org.php?o=35
Design Criteria
Fire Alarm Design
Criteria for the new fire detection and voice evacuation fire alarm system require a system that is code-compliant and approved by the GSA Regional Fire Protection Engineer. See the Option #1 scope in Section 3 of this Narrative, Drawings, and the technical specifications for a fire detection and voice evacuation fire alarm system.
Fire Protection Design
Criteria for the potential fire sprinkler modifications require the installation of sprinklers to be code-compliant and approved by the GSA Regional Fire Protection Engineer. See the Options #2 to #12 scope in Sections 4 and 5 of this Narrative, Drawings, and the technical specifications for sprinkler system modifications.
Electrical Design
Criteria for the electrical scope associated with the new fire detection and voice evacuation fire alarm system will be complaint with PBS P-100. See the Option #1 scope in Section 3 of this Narrative and the technical specifications.
Fire Command Center
Criteria for the new fire command center will be complaint with PBS P-100 and Section 911 of the International Building Code. In addition, the location and accessibility of the new fire command center shall be approved by the GSA Regional Fire Protection Engineer. See the Option #1 scope in Section 3 of this Narrative and the technical specifications.
Historic Preservation and Restoration Design
The Milwaukee Federal Courthouse is listed on the National Register of Historic Places, and therefore must comply with Section 106 of the National Historic Preservation Act of 1966. A Historic Building Preservation Plan and a Historic Structures Report will be provided by GSA for review and use. All
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 10 guidance for renovations and modifications recommended will meet the requirements of Section 106 and comply with the Secretary of Interior Standards.
Environmental Hazard Abatement Design
After the Concept Design phase, the Project Team completed a Pre-Alteration Assessment of the building areas that will be impacted as identified in the conceptual design and is included as an Appendix in the Specifications. The assessment generally follows the Asbestos Pre-Alteration Assessment, GSA Region 5, Facilities Management & Services Programs Division guidance document. In addition, the Pre- Alteration Assessment includes a survey of painted surfaces to determine the extent of lead-based or lead-containing paint.
The Pre-Alteration Assessment incorporates information contained in historical environmental reports for the building, including:
Asbestos-Containing Material and Lead-Based Paint Survey Summary Report, Federal Courthouse Building, 517 East Wisconsin Avenue, Milwaukee, Wisconsin; Carnow, Conibear & Assoc., Ltd., December 2005
Asbestos and Lead Paint Inspection, Federal Building & Courthouse (WI0044), 517 East Wisconsin Ave., Milwaukee, WI 53202; TRC, September 17, 2019
Limited Asbestos Containing Materials and Lead Based Paint Survey, Downspouts located in the Basement, Milwaukee Federal Building, 517 East Wisconsin Ave, Milwaukee, WI; AECOM, Revised May 22, 2020
The Pre-Alteration Assessment included in this submission documents our findings and defines a strategy for reducing potential negative impacts associated with hazardous material treatment.
Implementation Plan and Phasing
After contract award, the Contractor shall provide GSA with an overall Construction Schedule updated from the RFP submittal, as noted in Section 1.4, and an Implementation Plan for the project. The Implementation Plan shall focus on mitigating the interruptions of Courthouse operations, phasing, and migration planning.
The Contractor shall develop an initial Implementation Plan within 3 weeks of contract award. This submission shall be linked to the Construction Schedule (refer to Section 1.4, Project Schedule), incorporate a 3-week look-ahead function, and schedule recovery planning.
Subsequent detailed updates to the Implementation Plan shall, at a minimum, follow the provided initial Implementation Plan, focusing on critical implementation activities and procedures, delivery sequences and dependencies, key milestones and deliverables, construction phasing, quality assurance tasks, design and budget trade-off considerations, security requirements, Fire Watch staffing, etc.
Upon acceptance of the initial Implementation Plan by GSA, a detailed Implementation Plan shall be submitted to the GSA for review and approval and, if needed, presentations and logistics plans are to be
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 11 provided to building tenants. The Contractor shall notify and coordinate O&M issues outside of the scope of the CMc contract with the GSA’ existing O&M contractor.
Tenant Notification
The Contractor shall coordinate with the GSA on-site manager and facility manager for tenant introductions and notifications. Notifications will need to be in compliance with the GSA’s Building Operation Requirements/Manual and must be administered 2 weeks prior to the date when access to a given space is required.
Material Storage / Delivery and Waste Removal
The Implementation Plan prepared by the Contractor shall also identify, at a minimum, material storage and staging areas and procedures, delivery procedures and dates of major or multiple deliveries, waste removal and recycling procedures, and day/night activity sequencing.
The following activities shall be coordinated with the GSA on-site manager and facility manager:
Locations for material storage, short-term and long-term Deliveries at street level or at the basement level or use of the parking garage spaces, with proposed time schedules Waste removal at the floor level and holding/release plans, including hazardous material procedures
Off-Hours Work
The GSA and tenants will occupy the building during the entire construction period. Work shall be conducted during off hours, and the GSA Property Management personnel are not on site during off hours. The Contractor shall plan on providing a foreman who debriefs the GSA Property Manager or his/her designee each morning on the progress from the night before and the schedule for the next evening’s work. The Contractor shall coordinate daily meetings with the GSA’s Property Manager, CMa as owner’s representative and the operations and maintenance contractor to advise of progress the prior night and to discuss and resolve any issues or concerns that may have arisen. The Contractor shall also be responsible for ensuring that appropriate clean-up has taken place in work areas before tenants arrive each morning and promptly address any areas of concern as needed.
Fire Watch Staffing
The Contractor shall indicate the timing and staffing for Fire Watch personnel, if required, on the project schedule and coordinate with the GSA Project Manager and building security officer.
Security Plan and Safety Plan
The Implementation Plan shall have a security plan prepared that will include, but not limited to, security clearances, secure areas in the building, visible document protection, use of cameras, and notifications for access to both public and secure building areas.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 12
The security plan shall detail the Contractor’s procedures for gaining security clearance for each staff member, dates for GSA security procedure training, daily procedures for workers attending the site, procedures for deliveries, and screening of material, etc. All practices are to be clearly detailed in the Implementation Plan for GSA review and approval.
The Contractor will have a proposed site and task-specific safety plan prepared that will include, but not limited to, safety notice postings, safety meeting, emergency contacts, and on-site health, job hazard analysis and safety support equipment. Based on the type of construction work taking place, a silica work exposure plan may be required. The Safety Plan shall be submitted to GSA for review and approval.
Artwork Protection
The Contractor shall submit a detailed plan indicating how the existing interior artwork will be protected during construction. Requirements for protection shall be coordinated with the GSA Property Manager and reviewed by GSA’s Historical Preservation for approval.
Turn-Over Strategy
The Contractor shall generate and submit to the GSA for acceptance a turn-over strategy as a part of the Implementation Plan that defines the turn-over process for the work as areas are completed. The strategy shall also define the ultimate turning over of the project upon completion
The Contractor shall assume sole and complete responsibility for the job site conditions during construction, including safety of all persons and property. The extents of the Contractor’s work area shall be limited to the work area associated with the current phase of the project under construction, the required staging areas, and the surrounding areas required to maintain a safe perimeter. The Contractor shall coordinate these boundaries with GSA Property Management.
Prior to the completion of a work area or project phase, the Contractor shall submit a turnover request and schedule to the GSA for approval. The approval for turn-over shall be contingent upon receipt of submittals, testing reports, punch lists, pay requests, etc.
Demolition
Significant but targeted demolition will be required during various phases of the work to complete the required Scope of Work. Detailed demolition requirements shall be indicated and completed in accordance with the "Selective Demolition" specification section 017320 in the Specifications.
Before beginning demolition work, the Contractor shall take pre-demolition photographs, in compliance with specification section 013220 – Photographic Documentation. Photographs shall document the pre-demolition conditions of finishes and surfaces both directly impacted by the demolition work and those adjacent. Additional photographic documentation may be requested by the GSA. The Contractor shall provide a photographic documentation plan for GSA review and approval. No demolition work shall commence without prior submission of photographic documentation of the respective room, space, or area, in compliance with the approved plan.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 13
Commissioning
The Contractor is required to complete commissioning for any systems affected by the construction works outside of the fire detection and voice evacuation fire alarm and fire sprinkler work. The fire detection and voice evacuation fire alarm and fire sprinkler will be commissioned by the GSA Regional Fire Protection Engineer. The GSA Regional Fire Protection Engineer will be the AHJ and is responsible for commissioning and testing for Fire Life Safety in the Design and Construction phases. The Contractor shall adjust/correct the work as required to comply with the GSA’s commissioning findings.
LEED Registration and Certification
This project will be considered exempt from the Capital Investment and Leasing Program Leadership in Energy and Environmental Design – New Construction (LEED-NC) requirement and will not be counted in the PBS performance measures for LEED-NC certification. All other energy efficiency and sustainable design requirements, including the Guiding Principles for Federal Leadership in High-Performance and Sustainable Buildings (Federal Energy Management Program 2016), must still be applied throughout design and construction to the greatest extent practicable.
Quality Assurance and Quality Control
After contract award, the Contractor shall submit a Quality Control Plan for approval by the GSA that shall include, at a minimum, the following:
The Contractor and all subcontractors shall be licensed, insured, bonded, and trained as required by all authorities having jurisdiction.
It shall be the responsibility of the Contractor to ensure that the construction means and methods do not compromise safety, construction materials, or the final as-built product.
The Quality Control Plan shall identify and recommend quality assurance practices such as the use of integrated design, design charrettes, design program review workshops, design excellence concept peer reviews, value engineering workshops, specialty design reviews, local government code reviews, construction excellence procurements, performance-based incentives, project delivery partnership concepts, effective turnover practices, and operations/maintenance service contracting.
As appropriate, graphics may be used to illustrate the technical narrative for locational purposes as a quality assurance measure.
Protocols for the internal review of design documents and design phase submissions.
Protocols for the internal review and approval of built works on site. The Contractor shall set up all elements to be mocked up for GSA review and approval before beginning major works such as historic preservation elements.
Protocols for the protection of existing and surrounding surfaces, workspaces, egress pathways, ventilations system, and the like.
Fire Alarm and Fire Sprinkler Installation Quality Control
The Contractor shall comply with the following:
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 14
Fire detection and voice evacuation fire alarm and fire protection routing shall be chosen to be efficient from a systems standpoint while minimizing impacts on historic and hazardous elements.
The Contractor shall engage the GSA’s Regional Fire Protection Engineer early and often during the design process to understand how the system(s) will operate and be installed.
The Contractor shall generate a construction review and approval plan, which will include mockups of key elements, to ensure that works are completed correctly the first time.
When penetrating existing surfaces, the Contractor shall complete a pilot hole prior to primary drilling or coring efforts to confirm the suitability of the location and existing conditions.
Existing life safety systems are to be maintained and protected during Contractor construction efforts. The existing system shall be maintained in working order until the new system is handed over to the GSA.
Maintain safe access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the GSA.
Historic Preservation Quality Control
The construction process for the fire detection and voice evacuation fire alarm system and fire sprinkler work shall take great care in the routing and selection of installation locations in order to protect the historic architectural character and materials in preservation Zone One and Zone Two spaces. These Zones have been identified in the Room Survey Matrix, the historic preservation zoning drawings, and the historic preservation survey sheets. The following quality control requirements, at a minimum, shall be implemented during the design and construction phases under the CMc contract:
Alterations shall follow the Secretary of the Interior’s Standards for Rehabilitation.
The Contractor shall initiate early design review with GSA Historic Preservation Staff (GSA HP
Staff). GSA HP Staff will review and approve all designs in Zones One and Two to mitigate potential adverse effects.
The Contractor shall submit all subcontractor qualifications, samples, historic preservation treatment procedures, and materials.
Mockups of historic restoration, as requested, shall be approved before starting work on site.
The Contractor shall provide thorough documentation of the historic spaces that will be affected by the work both as a record of their existing condition and to evaluate any alterations to the historic fabric as a result of the work.
The Contractor shall provide adequate protection of historic elements that may be impacted during the construction process.
The Contractor shall establish hold points for critical works to verify that the original intentions of the design are being accurately carried out.
All contributing elements that are to be temporarily removed shall be carefully documented and stored for later reinstallation.
The Contractor shall look for opportunities to gain access to wall and ceiling cavities from an adjacent and less historically significant space.
The Contractor shall avoid cutting and patching ornate architectural elements that would be difficult to replicate.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 15
Where cutting and patching of historic elements is necessary, the patches shall exactly replicate the material properties, sizes, profiles, and finishes of the elements before they were cut. They shall be pre-marked on site for GSA HP Staff and AHJ review and approval before actual cutting occurs.
If fire protection installations have to be located on an architecturally ornate wall and/or ceiling, the Contractor shall locate the devices/sprinklers so they do not conflict and detract from the composition.
Where code compliance is not achievable due to detrimental historic preservation impacts, the Contractor shall notify the GSA for coordination of a solution acceptable to the GSA.
Environmental Quality Control
Quality control for environmental remediation services during implementation will follow the technical specifications:
GSA Specification 028200 Asbestos Abatement GSA Specification 028300 Lead-Based Paint Mitigation
Within the State of Wisconsin, as regulated by the U.S. Environmental Protection Agency (EPA), asbestos abatement is governed by National Emission Standards for Hazardous Air Pollutants (NESHAP) regulations, the Wisconsin Department of Natural Resources (WDNR) under Chapter NR 447 of the Wisconsin Administrative Code, and the Wisconsin Department of Health Services (WDHS). Additionally, the Occupational Safety and Health Administration (OSHA) regulates employee exposure to asbestos under Title 29 of the Code of Federal Regulations (CFR) 1926.1101.
The functional requirements of these governing agencies include certification of abatement companies and workers, notification with fees to regulatory agencies, preparation of an Asbestos Occupant Protection Plan, construction monitoring along with regulatory inspections, and final clearance inspections.
Within the City of Milwaukee, the WDNR’s inspection services can be delegated to the City of Milwaukee Department of Neighborhood Services.
Warranties
The Contractor shall warrant for one year that the improvements constructed are reasonably free of defects and that the work conforms to the requirements of the contract documents, drawings, plans, and specifications. If any defects are found, the Contractor shall promptly repair or replace any of the defective work at its cost. The warranty shall become effective upon the GSA’s substantial completion of the work and the completed turn-over of the facility.
Additional terms and conditions of the limited 1-year warranty shall be submitted with the bid for consideration by the GSA. The limited warranty shall be part of the Options.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 16
Building Tenant Impact
The Milwaukee Federal Building and U.S. Courthouse is expected to be fully occupied during construction. Some areas in the building are accessible by the general public and some have high security functions as part of Court and other governmental operations. There are 24-hour tenant operations in this building which must not be interrupted except for minimal pre-scheduled impacts.
The Contractor must protect all government property in immediate work areas by installing protective equipment, materials, coverings, and all measures for limiting disruption. The Contractor shall return all work areas to the condition that existed prior to any work being undertaken. The expectation is that there will be minimal disruption to agency workspaces or missions. Work needs to be coordinated to determine if some work can be accomplished during normal working hours.
Upon contract award, the Contractor shall conduct an initial planning meeting with GSA Property Manager and the facility manager. The Contractor shall have its Implementation Plan (Section 2.6) prepared for referencing against the building tenant housing plan. The Contractor shall maintain detailed tenant impact documentation as part of the Implementation Plan based on dates of construction work impact, floor level, and tenant impact. Tenant areas under construction which may require guard service at night during unoccupied hours shall be identified during the design phase, so that appropriate RWA may be obtained.
Additional items for coordination are the Contractor’s security plan, safety plan, and work hour scheduling.
In public areas, the construction work shall be conducted after hours unless approved by the GSA and GSA Property Manager. Design and management site visit inspections may occur during the day. As part of the Contractor’s Implementation Plan, the Contractor shall provide a design visit schedule for GSA review, as well as any proposed testing or sampling. Any light construction activities or construction in non-occupied areas of the building proposed by the Contractor for normal work hours will require approval by the GSA and the facility manager.
A building housing plan for tenant location and floor plans are provided as reference documents. These documents indicate where a Federal agency is located, the limits of its occupancy, the rooms, and room numbers for the rooms. The room numbers on the CAD floor plans are from a design document room tag numbering system, and the actual room number signage in the building is a different room signage numbering system. The Contractor in indicating work areas should provide dual designations for work areas – CAD floor plan designation and room number signage.
Below is a summary listing of the tenants by floor level in the building; recent relocations, if any, need to be confirmed on site. Refer to the Drawings for existing tenant information on floor plans.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 17
Level Tenant
Sub-Basement Probation
Sub-Basement Building Common
Sub-Basement Core and Support
Sub-Basement Core and Support
Basement Fire Protection Riser Room
Basement Justice Department US Marshal
Basement Justice Department US Attorney (Fitness)
Basement PBS - Field Office (Fitness)
Basement PBS - MCO (Marshall Space)
Basement Probation (Fitness)
Basement District Clerk (Fitness)
Basement Bankruptcy (Fitness)
Basement Building Joint Use
Basement Parking
Basement Building Common
Basement Core and Support
Basement Building Common
Basement Core and Support
First Floor Bankruptcy Judicial Courtrooms
First Floor Bankruptcy Clerk
First Floor DHS NA Pro and Pro Dir
First Floor Judicial Com Def
First Floor Building Common
First Floor Core and Support
First Floor Building Common
First Floor Core and Support
First Floor Building Joint Use
First Floor Vacant
Second Floor District Judicial Courtrooms - Clevert
Second Floor District Judicial - Nancy Joseph
Second Floor District Judicial Courtrooms - Unassigned
Second Floor District Judicial Courtrooms - Not Named
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 18
Second Floor District Judicial Courtrooms - Not Named
Second Floor Mag Judicial Chambers - Goodstein
Second Floor Mag Judicial Chambers - Gorence
Second Floor District Clerk
Second Floor District Clerk
Second Floor PBS - Field Office (GSA)
Second Floor Building Common
Second Floor Core and Support
Second Floor Building Common
Second Floor Core and Support
Third Floor District Judicial Courtrooms - Adelman
Third Floor District Judicial Courtrooms - Randa
Third Floor District Judicial Courtrooms - Unassigned
Third Floor Justice Department US Marshal
Third Floor Judicial District Courts, US
Third Floor District Clerk
Third Floor District Clerk
Third Floor Building Common
Third Floor Core and Support
Third Floor Building Common
Third Floor Core and Support
Fourth Floor Senate
Fourth Floor Court of Appeals Courtrooms - small office
Fourth Floor District Judicial Courtrooms
Fourth Floor District Clerk
Fourth Floor Probation
Fourth Floor Justice Department US Marshal
Fourth Floor Justice Department US Attnys
Fourth Floor Justice Department Trustees
Fourth Floor Tax Court, US
Fourth Floor SSA (Social Security)
Fourth Floor FAS - Office
Fourth Floor Com Nat and Com Serv
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 19
Fourth Floor Bankruptcy Clerk and Bankruptcy Hearing
Fourth Floor HHS DM (IG)
Fourth Floor Building Joint Use
Fourth Floor Building Common
Fourth Floor Core and Support
Fourth Floor Building Common
Fourth Floor Core and Support
Fifth Floor Senate
Fifth Floor Cir Libraries
Fifth Floor District Judicial Courtrooms
Fifth Floor Justice Department US Attorneys
Fifth Floor GSA PBS Other
Fifth Floor PBS File Office
Fifth Floor DHS USSS (Secret Service)
Fifth Floor Vacant
Fifth Floor Building Common
Fifth Floor Core and Support
Fifth Floor Building Common
Fifth Floor Core and Support
Sixth Floor Court of Appeals Courtrooms
Sixth Floor Justice Department US Attorneys
Sixth Floor Building Common
Sixth Floor Core and Support
Sixth Floor Building Common
Sixth Floor Core and Support
Seventh Floor Court of Appeals Courtrooms - Sykes
Seventh Floor Court of Appeals Courtrooms - Evans
Seventh Floor District Clerk Storage
Seventh Floor Justice Department US Marshal
Seventh Floor Justice Department US Attorney
Seventh Floor Vacant
Seventh Floor Building Common
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 20
Seventh Floor Core and Support
Seventh Floor Attic of North Building
Eighth Floor (Penthouse P1)
Building Common
Eighth Floor (Penthouse P1)
Core and Support
Eighth Floor (Penthouse P1)
Roof
Tower Floors 9, 10, 11, and 12
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 21
3.0 Option #1: Fire Alarm System Replacement
General Requirements
The project includes the design and installation of a new fire detection and voice evacuation fire alarm system while at the same time mitigating any hazardous materials affected by the work and preserving the historic nature of the building. Because of the locations of the existing fire alarm and notification appliances in the building (or lack thereof) and the age of the existing fire alarm system, the entire fire alarm and notification system in the building will be replaced. Upon acceptance of the new system, the existing fire alarm system will be completely removed.
The existing fire alarm system will continue to operate in parallel to the installation of the new fire detection and voice evacuation fire alarm system until the new system is tested, commissioned, and put into service. At that time, the existing system can be decommissioned and demolished, and surface restoration can be completed, if and as needed.
Fire Alarm
The Scope as identified below is to be provided by the Contractor as a part of the Option #1 scope of work.
New Fully Addressable Fire Detection and Voice Evacuation Fire Alarm System New fully addressable fire detection and voice evacuation fire alarm system Scope of Work basis:
A new fully addressable fire detection and voice evacuation fire alarm Control Panel (FACP) with one- and two-way voice system. New fire alarm control panel shall be located in the fire command center.
Provide a fire alarm annunciator located in plain view within 25 feet of the primary fire department entrance to the building.
Provide redundant fire detection and voice evacuation system controls in the U.S. Marshal Service Command and Control Center.
Provide interconnected network supply and return vertical risers of a two-hour rated cable or cable system located in the existing non-fire rated electrical rooms adjacent to the common corridors at the southeast and southwest of the “South” building. The risers will be interconnected via a two-hour rated cable or cable system on the seventh floor and basement level.
Protect all circuits necessary for the operation of the notification appliances until they enter the evacuation signaling zone (floor) with a two-hour rated cable or cable system.
Provide a minimum of two (2) distinct fire alarm audible notification appliance circuits on each floor.
Provide a minimum of two (2) distinct fire alarm visible notification appliance circuits on each floor.
Notification appliance circuits will be Class B circuits.
Provide a minimum of two (2) Class B signaling line circuits (SLC) per floor with a maximum coverage area per SLC of 26,000 square feet.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 22
Design, procure, install, test, commission with GSA fire life safety oversight, and add components in rooms/spaces as required.
Provide new or additional addressable initiating devices as required.
Automatic operation of shunt trip circuit breakers to shunt power to elevators.
New audible and visible notification appliances including a speaker in every office/office area to provide audibility throughout the building.
U.L. listed Central Station Alarm monitoring service of all fire detection and voice evacuation system trouble, supervisory and alarm signals via two different communication paths.
Door hold-open devices.
New duct detection for any air handling unit (AHU) requiring duct detectors with the detector programmed as a supervisory signal.
New addressable control relays for all AHUs requiring duct detectors and locating these relays within 3 feet of duct detectors for AHU shutdown.
AHU shutdown due to duct detector shall not occur through building automation system. AHU shall have a hardwired connection from fire alarm panel that will shut down unit upon signal from duct detector. Fire alarm signal shall override building automation system control.
Multi-criteria detection where required.
Identify any fire alarm or fire protection subsystems located anywhere in the complex and provide monitoring of such systems.
Historic atrium beam style detection system. Beam detectors will be tied into the atrium’s smoke evacuation system and shall activate the system when the detector goes into alarm.
Heat detection for all attic spaces.
All fire alarm wiring is to be solid copper wiring.
All fire alarm wiring is to be installed in minimum ¾-inch rigid metal or EMT conduit using compression type fittings and couplings.
Circuit-integrity (CI) cable is to be installed in EMT only.
New Electrical System New electrical system Scope of Work basis:
Provide U.L. listed power conditioners with built-in overload protection.
New power supplies and amplifiers for the total load of the new fire detection and voice evacuation fire alarm system plus required spare power capacity.
There are existing shunt trip circuit breakers on all of the existing (hydraulic or geared traction) elevators where required by code to have sprinklers in elevator shafts and elevator machine rooms. These existing shunt trip circuit breakers shall be connected to the new Fire Alarm System.
Existing System Description The fire alarm system documentation drawings identify locations of the main Fire Alarm panel and remote annunciator panels, locations of fire alarm risers, and other key areas such as the Historic Corridors, atrium, lobbies, and courtrooms where there may be challenging work conditions for installation of new fire detection and voice evacuation fire alarm devices and notification appliances.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 23
Phasing It is recommended that the Contractor consider the installation of work on a floor-by-floor and/or zone-by-zone basis to allow facilities to maintain operations and to comply with scheduling requirements.
Scheduling for implementation is to be flexible with alternates. The implementation plan shall contain and address contingent areas if scheduled work areas are unavailable.
The GSA and tenants will occupy the building during the entire construction period. Work will be conducted during off-hours when GSA Property Management is not on site.
Refer to NFPA 72, National Fire Alarm and Signaling Code and GSA PBS-P100, Facilities Standards for the Public Buildings Service (P100) for requirements and specifications.
Electrical
The new electrical scope of work will consist of the following:
The 6th floor Fire Alarm Voice Communication System Remote Transponder will be located in electrical room “645E”, this room is down the corridor from room “650”. Room “650” has an emergency power panel “6EMP/B” which has space for additional circuit breakers.
The 4th floor Fire Alarm Voice Communication System Remote Transponder will be located in electrical room “457E”, this room is down the corridor from room “469E”. Room “469E” has an emergency power panel “4EMP/B” which has space for additional circuit breakers.
The 2nd floor Fire Alarm Voice Communication System Remote Transponder will be located in electrical room “257E”, this room is down the corridor from room “267E”. Room “267E” has an emergency power panel “2EMP/B” which has space for additional circuit breakers.
There will be the new FACP located in the new Fire Command Center on the first floor, emergency power for this panel will come from first floor emergency panel “1EMP/B”, located in Electrical Room 119B, adjacent to the new Fire Command Center room, and which has space for additional circuit breakers.
All the existing elevators main power disconnects have shunt trip circuit breakers controlled by the existing fire alarm system. The existing shunt trip circuit breakers shall be wired to the new Fire Alarm system.
Fire Command Center
The new fire command center shall be designed and installed in accordance with the requirements of PBS-P100 and Section 911 of the International Building Code. The scope of work will consist of the following:
The fire command center shall be separated from the remainder of the building by 1-hour fire rated construction.
The fire command center shall be not less than 200 square feet with a minimum dimension of 10 feet.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 24
Storage unrelated to the operation of the fire command center shall be prohibited.
New lighting shall be provided and shall be connect to the existing Life Safety Distribution. The new luminaires shall have integral battery packs.
Life Safety power shall be provided to accommodate the new panels and Video Display Unit.
A new fire rated door, that can be locked closed, shall be provided for the space.
A new 1-hour rated ceiling will be added in order to separate the new space from the existing ductwork which passes through the room alleviating the need to utilize fire and smoke dampers
The new fire command center shall comply with NFPA 72 and shall contain all of the following:
Fire alarm control panel.
Elevator status panel, including recall switch.
Generator Annunciator panel, including manual start and stop.
Bi-Direction amplification system for communication between the command center, fire pump room and elevator pump house.
Bi-Directional amplifier for fire department radio communications.
Hard wired telephone allowing a technician or firefighter to communicate outside of building for testing or emergency response situations.
Touch screen Video Display Unit. Screen shall be flat with a minimal display of 19 inches diagonally.
Table, desk or stand for Video Display Unit
Historic Preservation
General Requirements and Guidelines The following section provides general requirements and guidelines for minimizing the impact on the historic fabric of the Milwaukee Federal Building and U.S. Courthouse where the fire protection system will be upgraded or replaced.
In Zone One and Zone Two rooms, the devices and electric conduit routing will impact the historic materials and appearance of the space. The proposed fire detection and voice evacuation fire alarm design will comply with the applicable requirements and guidelines listed below. Specific Federal guidelines for adding new fire detection and voice evacuation fire alarm systems to historic buildings are published in the document Fire Safety Retrofitting in Historic Building and the 2018 version of the PBS- P100. Where guidelines do not reference a specific Federal document, they are based on historic preservation “best practices”; these guidelines are summarized below.
Coordinate the location of all fire detection and voice evacuation fire alarm devices with both the GSA’s Fire Life Safety and Historic Preservation Staff.
FOR OFFICIAL USE ONLY
Do not remove this notice
Page | 25
Install smoke detectors, heat detectors, fire alarms and required electrical conduits so that they are not unusually prominent or do not affect the significant historic fabric of a building (Fire Safety Retrofitting in Historic Building, pg. 20).
Select the style of alarm devices so that its appearance is in harmony with other architectural elements of the historic building (Fire Safety Retrofitting in Historic Building, pg. 20).
It is not recommended to install smoke and heat detectors in historic plaster relief or cornices (Fire Safety Retrofitting in Historic Building, pg. 20).
In compliance with all code requirements, where possible, smoke detectors will be placed to minimize destruction of ornamental surfaces. Where ceilings are elaborately embellished, explore alternative detection products and approaches such as air sampling detection, projected beams, low-profile spot detectors, recessed installation, or custom-coating detector housings to blend with ornamental finishes. Application of special finish treatments outside of the standard factory process will be coordinated with, and approved in writing by, the manufacturer to ensure that UL labels and detector performance are not compromised. Smoke detector housings will be removed before application of special finishes (PBS-P100, pg. 222). It is not recommended to install smoke and heat detectors on the surface of ceilings that are historically significant (Fire Safety Retrofitting in Historic Building, pg. 20).
It is not recommended to install fire alarm pull stations in such a manner that they detract from or permanently change the appearance of the historic building or area (Fire Safety Retrofitting in Historic Building, pg. 15).
All electrical conduit routing will be carefully planned to minimize cutting and patching of historic material. This may include installation from a non-, or less, historically significant space where feasible (e.g., installation of conduit for a highly historic space from the backside of a wall in an office space). The Contractor shall create as many inspection openings as necessary to determine adequate routing.
All electrical conduit in Zones One and Two is to be concealed.
Project Team Coordination Guidelines Close coordination within the project team is essential in ensuring that…