This is an Intake Meeting Form for a construction contract prepared by Walton County, Florida, documenting the administrative details and planning requirements for Invitation to Bid (ITB) #25-19 for the ESGC Phase One Maintenance Building project located in DeFuniak Springs. The project involves constructing a maintenance facility at the Eagle Springs Golf Course Complex with a base bid scope of approximately 9,600 square feet including building materials, construction, utility hookups, and site grading, along with two alternate bid options for interior build-out and access/parking lot paving. A mandatory pre-bid meeting is scheduled for May 30, 2025, at 9:00 am at the CPD Conference Bridge. Questions and clarification requests from bidders must be submitted to the Purchasing Department by June 12, 2025, with bid responses due by June 24, 2025, at 3:00 pm. The contract requires 120 days for substantial completion and an additional 30 days for punch list completion, with work commencing within 10 days of Notice to Proceed. The Board of County Commissioners approved the project at their November 13, 2023, meeting with an approximate budget of $1.4 million.
The project utilizes a unit price payment structure with progress payments structured as a monthly lump sum. The estimated contract value requiring liquidated damages calculation must be determined by the Design/Engineering professional. Walton County has specified local vendor preference as applicable and does not involve federal funding or Davis-Bacon Act requirements. The project is not using grant funds. The selected contractor must be a licensed General Contractor in compliance with Walton County Ordinance 2009-01 and must obtain a county building permit per Ordinance 2005-29. The bid form requires a 30-day bid acceptance period, with the contractor having 10 days after Notice of Award to return the signed contract. Chance or David is designated as the project manager, Jason Cutshaw serves as the Purchasing contact, and Shane has authority to issue change orders. Advertisement of the project is scheduled to begin on May 23, 2025, and the Board of County Commissioners award date is to be determined.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Updated 4/23/2025
SEQ CHAPTER \h \r 1
INTAKE MEETING FORM
CONSTRUCTION CONTRACT
| Name of Project: |
| ITB 25-19 ESGC Phase one maintenance building |
Date Rec’d in Purchasing:
Bid Number: ITB 25-19
| Intake Meeting Attendees: |
| Jason, Shane, Matt T, Brad, Scott, Buddy, Dave, David |
| Has this project been budgeted? Aprox 1.4 mil |
| Account #: |
| NEED |
| Has BCC approved to go forward with this project? |
| Yes No |
| @ Which BCC Meeting? |
| 11/13/2023 |
| Are all rights of way, permits, etc., in hand so that contract can be awarded immediately after award by BCC? |
| Project Manager Chance/ Engineer DRMP Randall Jernigan |
| Cost of permits to be borne by contractor (per §218.80, F.S. must be disclosed in bid docs or contractor cannot be charged.) |
| Project Manager / Engineer DRMP |
INVITATION TO BID
| Drawings/Specs prepared by: |
| Russell Johnson |
| Brief description of project: |
| Project Manager Chance, Shane |
| Will Purchasing office be closed any days (besides Fridays) prior to the bid close date? |
| TBD |
| Cost to obtain copies of bid docs: |
| N/A (electronic) |
| If this is a road construction contract, who is responsible for traffic control/signage? WHERE IS THIS SPELLED OUT IN THE DRAWINGS/SPECS/SCOPE OF WORK? |
| Project Manager (Chance or David) |
| License Required: |
| Project Manger |
Are Contract Special Conditions (i.e. Pre-Cast Construction, Hot Mix Asphalt, MOT, etc.)
Anything else we need to know?
Project Manager
Instructions to Bidders
| How long is bid to remain open and subject to acceptance? |
| 30 days |
Bid Form
| Name & address of County contact person: |
| Jason Cutshaw |
| Phone & FAX numbers of County contact person: |
| 850-892-8176 |
Ext. 1229
| How many days after Notice of Award must signed contract be returned by contractor? |
| Typically (10) |
| How many days after Notice to Proceed must work begin? |
| 10 |
| How many days to completion? |
| SUBSTANTIAL:120 |
FINAL: 30 (60 for Alt)
Will a Limited Notice to Proceed be necessary for any long lead time materials? TBD PM
Contract
| Hours of Work |
| Daylight – Dark |
M-S Other:
| Payment options Default payment is UNIT PRICE(req bid sched) |
| Unit Price Not-To-Exceed |
| __X_ Lump Sum Proposal |
| ___Lump Sum @ Completion |
| ____ Progress Payments |
| If progress payments are to be made, provide details concerning schedule: |
| Lump sum per month |
| Estimated value of contract (in order to calculate liquidated damages): |
| DRMP NEED! |
| Who has authority to issue change orders? |
| Shane |
| Who is designated project manager? |
| Chance or David |
| Who is the Purchasing contact? |
| Jason Cutshaw |
| Are grant funds being used for this project? If so, please provide copy of grant contract. When does grant K expire? |
| No |
| Local Vendor Preference: |
Yes: X No:
| Are federal funds being used to fund this project? (Does Davis-Bacon Act apply?) |
| No |
| Local Vendor Preference: |
Yes: No:
Are there any special warranty or guarantee conditions (i.e., for live plants)?
| THINGS TO SAY OUT LOUD AT THE PREBID MEETING: |
| PM, ENG, Legal, |
Insurance, Lead time on materials, Sewer plan,
| Legal to complete front end documents by: |
| CR |
§255.0525, F.S.
Projects in excess of $200K – must advertise at least once in newspaper 21 days prior to bid opening and 5 days prior to any scheduled pre-bid meeting
Projects in excess of $500K – must be advertised at least once in a newspaper 30 days prior to bid opening and 5 days prior to any scheduled pre-bid meeting
Pre-Bid Meeting
Date: 5/30 Time: 9 Mandatory?
YES
LOCATION: CPD
Conference Bridge: 850-635-0655, 261217
Questions/requests for clarification must be submitted to Purchasing by: 6/12
Close Bidding
Date:
6/24/25
Time: 3:00 pm
Open Bids
Immediately Following
Begin Advertisement: TBD 5/23
BCC Award Date:TBD
NOTE: IF THERE ARE ALTERNATES TO THE BID, BE SURE BID SCHEDULE CONTAINS A LINE ITEM FOR COST OF BOND FOR THE ALTERNATE.
W:\Board of County Commissioners\Central Purchasing\PURCHASING\Solicitation ITB\ITB 2025\ITB 25-10 11 Maint Building Eagle Springs\ITB 25-08 ESGC Maint Bldg Intake Meeting Form .doc 7/2/2012 W:\Board of County Commissioners\Central Purchasing\PURCHASING\Solicitation ITB\ITB 2025\ITB 25-10 11 Maint Building Eagle Springs\ITB 25-08 ESGC Maint Bldg Intake Meeting Form .doc
File details come from the government source that posted it. Updated .