23-1518_-_Pdf_agenda_item.pdf

PDF 92 KB Posted

Attached to
ESGC Phase One Maintenance Building
Solicitation number
25-19
Issued by
Walton County, Florida

About this file

This document is an Agenda Item Report for the Walton County Board of County Commissioners, submitted by the Parks and Recreation Department for a meeting on November 13, 2023. The report requests approval to advertise an Invitation to Bid (ITB) for the construction of a new Parks and Recreation Maintenance Building. The proposed project involves building a maintenance facility at the Eagle Springs Golf Course Complex, with the base bid covering building materials, construction, utility hookups, and site grading. Additional bid alternates include interior build-out and access/parking lot paving.

The project is located in DeFuniak Springs, Florida, with a contract duration of 120 days for substantial completion and an additional 30 days for punch list completion. The contractor must be an insured, licensed General Contractor in accordance with Walton County Ordinance 2009-01 and obtain a Walton County Building Permit as per Ordinance 2005-29. The financial sections indicate that the project has been reviewed by the finance department, is budgeted, and marked for approval on the consent agenda.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Walton County Board of County Commissioners

AGENDA ITEM REPORT 23-1518

Meeting: Board of County Commissioners - Nov 13 2023 Department: Parks and Recreation Submitted by: Shella Harman Staff Contact: Shane Supple, Recreation Manager

☒ Consent Agenda ☐ Regular Agenda ☐ Public Hearing

TITLE/REQUESTED ACTION:

Request approval to advertise an Invitation to Bid (ITB) for the construction of a new Parks and Recreation Maintenance Building

PURPOSE / SUMMARY EXPLANATION OR HISTORY:

Advertise for bids to begin construction of a new Maintenance Building.

FINANCIAL IMPACT:

DESCRIPTION:

REVIEWED BY FINANCE? Yes FUNDING TYPE:

TOTAL COST: BUDGETED? Yes