ITB_25-08_Scope_of_Work_Summary.docx

DOCX document 36 KB Posted

Attached to
ESGC Phase One Maintenance Building
Solicitation number
25-19
Issued by
Walton County, Florida

About this file

This is a Scope of Work Summary document for Invitation to Bid (ITB) #25-08 issued by Walton County, Florida for the ESGC Phase One Maintenance Building project located in DeFuniak Springs. The project involves constructing a pre-engineered metal building of approximately 9,600 square feet at the Eagle Springs Golf Course Complex. The base bid encompasses core building and site work including rough grading, site preparation, utility connections (water, sewer, and electrical stub-outs), foundation and slab installation, exterior shell and roof system with impact-rated doors and windows, and ADA-compliant entry features. Alternate 1 covers interior build-out with framing, finishes, bathrooms, break room, mechanical room, office partitions, and installation of HVAC, plumbing, and electrical systems. Alternate 2 addresses site access and parking with asphalt paving, grading, compaction, striping, ADA parking spaces, and stormwater management. The mandatory pre-bid meeting is scheduled for July 8, 2025, at 8:30 am, with bid responses due by July 30, 2025, at 3:00 pm. The contract duration is 120 days for substantial completion with an additional 30 days for punch list completion.

The total estimated project cost is $3,283,497.67, comprising a base bid of $1,624,045.09, Alternate 1 interior build-out of $805,000.00, Alternate 2 access and parking of $682,853.32, and Alternate 3 sewer lift station of $171,599.26. Bidders must submit a 5% bid security and required documentation including local preference applications, drug-free workplace certifications, and proof of licenses. The selected contractor must be a licensed General Contractor in accordance with Walton County Ordinance 2009-01 and must obtain a Walton County Building Permit. The project is funded through Walton County resources with a 15% contingency included for each alternate. The county will award the contract to the lowest, most responsible and responsive bidder meeting project specifications. A Development Order issued by the City of DeFuniak Springs, effective February 6, 2025, through February 6, 2026, authorizes project development with specific permitting and regulatory compliance conditions. No specific set-asides for disadvantaged enterprises are indicated, and no incumbent vendors are mentioned.

View the file

Other files

File Type Posted
ESGC_Phase_One_Maintenance_Building_(Addendum_#5_Revision).pdf PDF
ESGC_Phase_One_Maintenance_Building_(Addendum_#5_Revision).pdf PDF
P22-0080_Geotechnical_Report_-_Eagle_Springs_Additions.pdf PDF
P22-0080_Geotechnical_Report_-_Eagle_Springs_Additions.pdf PDF
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET_Updated.docx DOCX document
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET.pdf PDF
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET.pdf PDF
EAGLE_SPRINGS_MAINTENANCE_BLDG_Arch_Plans.pdf PDF
EAGLE_SPRINGS_OWNER_REVIEW_05.17.23.pdf PDF
EAGLE_SPRINGS_MAINTENANCE_BLDG_Arch_Plans.pdf PDF
ESGC_Phase_One_Maintenance_Building.pdf PDF
Contract_No._25-19.pdf PDF
Contract_No._25-19.pdf PDF
Contract_No._25-19.pdf PDF
100_percent_Engineers_Estimate.xls XLS spreadsheet
100_percent_Engineers_Estimate.xls XLS spreadsheet
100_percent_Engineers_Estimate.xls XLS spreadsheet
2025.06.24_PLAN_SET.pdf PDF
2025.06.24_PLAN_SET.pdf PDF
2025.06.24_PLAN_SET.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_DO.pdf PDF
Eagle_Springs_DO.pdf PDF
Eagle_Springs_DO.pdf PDF
11_13_2023_agenda.pdf PDF
ITB_25-08_Bid_Schedule_Template.xlsx XLSX spreadsheet
Excerpt_from_11-13-23_BCC_Meeting_Minutes_(See_Item_#32).pdf PDF
ITB_25-08_Bid_Schedule_Template.xlsx XLSX spreadsheet
Excerpt_from_11-13-23_BCC_Meeting_Minutes_(See_Item_#32).pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
Excerpt_from_11-13-23_BCC_Meeting_Minutes_(See_Item_#32).pdf PDF
ITB_25-08_Scope_of_Work_Summary.docx DOCX document
1_OVERALL_SITE_PLAN.pdf PDF
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
11_13_2023_agenda.pdf PDF
1_OVERALL_SITE_PLAN.pdf PDF
ITB_25-08_Bid_Schedule_Template.xlsx XLSX spreadsheet
1_OVERALL_SITE_PLAN.pdf PDF
11_13_2023_agenda.pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
ITB_25-08_Scope_of_Work_Summary.docx DOCX document
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
EAGLE_SPRINGS_OWNER_REVIEW_05.17.23.pdf PDF
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB 25-08 – Scope of Work Summary Base Bid – Core Building & Site Work

- Construction of a pre-engineered metal building (approx. 9,600 SF total)

- Rough grading and site prep per civil/structural plans

- Installation of utility connections (water, sewer, electrical stub-outs)

- Foundation and slab per structural drawings

- Exterior shell and roof system per architectural elevations (impact-rated doors and windows included)

- ADA-compliant entry features (excluding parking lot paving) Alternate 1 – Interior Build-Out

- All interior framing and finishes per floor plan A101 and sheets A104-A105

- Bathrooms, break room, mechanical room, and office partitions

- Installation of HVAC, plumbing, and electrical systems per M, P, and E sheets

- Ceilings, VCT flooring, cabinetry, and interior doors/hardware

- ADA fixtures, restroom accessories, and finishes per specifications Alternate 2 – Site Access & Parking

- Access driveway and parking lot paving (asphalt and/or base per site plan)

- Grading, compaction, striping, ADA parking spaces, and stormwater swales

- Coordination with Public Works for ROW if applicable

File details come from the government source that posted it. Updated .