About this file

The document is a 100% Engineers Estimate for the Eagle Springs Golf Course Maintenance Facility Live Oak Avenue Extension project in Walton County, Florida. The project involves constructing a maintenance building with a base bid and three alternates, including the main building construction, interior build-out, access and parking, and a sewer lift station. The contract duration is 120 days for substantial completion with an additional 30 days for punch list completion. The project requires a licensed General Contractor who must obtain a Walton County Building Permit.

The total estimated project cost is $3,283,497.67, broken down into base bid ($1,624,045.09), Alternate 1 interior build-out ($805,000.00), Alternate 2 access and parking ($682,853.32), and Alternate 3 sewer lift station ($171,599.26). The estimate includes a 15% contingency for each alternate and covers various construction elements such as site preparation, utility connections, building shell, foundation, interior systems, parking infrastructure, and sewer infrastructure. Optional pricing is also included for potential additional storage area improvements. The project requires the contractor to be insured and licensed in accordance with Walton County ordinances.

View the file

Other files

File Type Posted
ESGC_Phase_One_Maintenance_Building_(Addendum_#5_Revision).pdf PDF
ESGC_Phase_One_Maintenance_Building_(Addendum_#5_Revision).pdf PDF
P22-0080_Geotechnical_Report_-_Eagle_Springs_Additions.pdf PDF
P22-0080_Geotechnical_Report_-_Eagle_Springs_Additions.pdf PDF
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET_Updated.docx DOCX document
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET.pdf PDF
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET.pdf PDF
ITB_25_19_ESGC_PHASE_1_MAINT._BUILDING_ATTENDANCE_SHEET_Updated.docx DOCX document
EAGLE_SPRINGS_MAINTENANCE_BLDG_Arch_Plans.pdf PDF
EAGLE_SPRINGS_OWNER_REVIEW_05.17.23.pdf PDF
EAGLE_SPRINGS_MAINTENANCE_BLDG_Arch_Plans.pdf PDF
EAGLE_SPRINGS_OWNER_REVIEW_05.17.23.pdf PDF
ESGC_Phase_One_Maintenance_Building.pdf PDF
Contract_No._25-19.pdf PDF
Contract_No._25-19.pdf PDF
Contract_No._25-19.pdf PDF
100_percent_Engineers_Estimate.xls XLS spreadsheet
100_percent_Engineers_Estimate.xls XLS spreadsheet
2025.06.24_PLAN_SET.pdf PDF
2025.06.24_PLAN_SET.pdf PDF
2025.06.24_PLAN_SET.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_CIVIL_PLAN_SET_signed.pdf PDF
Eagle_Springs_DO.pdf PDF
Eagle_Springs_DO.pdf PDF
Eagle_Springs_DO.pdf PDF
Excerpt_from_11-13-23_BCC_Meeting_Minutes_(See_Item_#32).pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
Excerpt_from_11-13-23_BCC_Meeting_Minutes_(See_Item_#32).pdf PDF
ITB_25-08_Scope_of_Work_Summary.docx DOCX document
1_OVERALL_SITE_PLAN.pdf PDF
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
11_13_2023_agenda.pdf PDF
1_OVERALL_SITE_PLAN.pdf PDF
ITB_25-08_Bid_Schedule_Template.xlsx XLSX spreadsheet
1_OVERALL_SITE_PLAN.pdf PDF
11_13_2023_agenda.pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
23-1518_-_Pdf_agenda_item.pdf PDF
ITB_25-08_Scope_of_Work_Summary.docx DOCX document
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
ITB_25-19_ESGC_Maint_Bldg_Intake_Meeting_Form_.doc DOC document
ITB_25-08_Scope_of_Work_Summary.docx DOCX document
11_13_2023_agenda.pdf PDF
ITB_25-08_Bid_Schedule_Template.xlsx XLSX spreadsheet
EAGLE_SPRINGS_OWNER_REVIEW_05.17.23.pdf PDF
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

100%_2025

Eagle Springs Golf Course Maintenance Facility Live Oak Avenue Extension
Walton County, Florida
Opinion of Probable Construction Cost
ITEMDESCRIPTIONUNIT OF MEASUREQTYUNIT PRICETOTAL
BASE BID ITEMS
1Mobilization (5% of site work)LS1$ 61,001.64$ 61,001.64
2Maintenance of TrafficLS1$ 10,000.00$ 10,000.00
3Site Grading and Preparation (including stormwater pond)LS1$ 25,000.00$ 25,000.00
4Site Demolition, Clearing and Grubbing, and CleanupLS1$ 35,000.00$ 35,000.00
5Site Erosion ControlLS1$ 15,000.00$ 15,000.00
6Utility Connections (Water/Sewer/Electric)LS1$ 110,000.00$ 110,000.00
7Building Foundation and SlabLS1$ 250,000.00$ 250,000.00
8Pre-Engineered Metal Building Shell ErectionLS1$ 500,000.00$ 500,000.00
9Impact-Rated Doors and WindowsLS1$ 100,000.00$ 100,000.00
10Insulation and Vapor BarrierLS1$ 100,000.00$ 100,000.00
11Exterior Trim and FinishesLS1$ 75,000.00$ 75,000.00
12*Regular ExcavationCY3958$ 15.86$ 62,773.88
13*Regular Embankment (Fill)CY4040$ 16.94$ 68,437.60
SUB-TOTAL$ 1,412,213.12
CONTINGENCY (15%)$ 211,831.97
TOTAL$ 1,624,045.09
ALTERNATE 1 – INTERIOR BUILD-OUT
14Interior Framing and DrywallLS1$ 160,000.00$ 160,000.00
15Interior Doors, Hardware, and TrimLS1$ 70,000.00$ 70,000.00
16Bathroom Fixtures and AccessoriesLS1$ 65,000.00$ 65,000.00
17Break Room Casework, Hardware and FixturesLS1$ 25,000.00$ 25,000.00
18Flooring (VCT) and Base TrimLS1$ 60,000.00$ 60,000.00
19CeilingsLS1$ 25,000.00$ 25,000.00
20Interior PaintingLS1$ 35,000.00$ 35,000.00
21HVAC System InstallationLS1$ 125,000.00$ 125,000.00
22Plumbing System InstallationLS1$ 50,000.00$ 50,000.00
23Electrical System InstallationLS1$ 85,000.00$ 85,000.00
SUB-TOTAL$ 700,000.00
CONTINGENCY (15%)$ 105,000.00
TOTAL$ 805,000.00
ALTERNATE 2 – ACCESS & PARKING
246" concrete (sidewalk)SY124$ 132.22$ 16,395.28
25Concrete Wheel StopEA25$ 150.00$ 3,750.00
266" white solid striping (thermoplastic)GM0.08$ 6,416.99$ 513.36
276" blue solid striping (thermoplastic)LF94$ 7.30$ 686.20
2824" Stop BarLF34$ 10.34$ 351.56
29Handicap symbolEA1$ 300.00$ 300.00
30Preformed White Directional ArrowsEA10$ 148.80$ 1,488.00
31Site Single Post Sign w/Panel Less Than 12 sf (excludes ADA signage)EA5$ 557.45$ 2,787.25
32ADA Single Post Sign w/Panel Less Than 12 sfEA1$ 557.45$ 557.45
331.5" Asphalt SP 12.5 (roadway and cart path)TN492$ 360.00$ 177,120.00
346" Limerock Base (OBG 4)SY6022$ 22.00$ 132,484.00
3512" Type B StabilizationSY122$ 14.96$ 1,825.12
36RiprapTN19$ 217.24$ 4,127.56
37Type F DBIEA8$ 5,600.00$ 44,800.00
3818" Mitered End Section (1:4 slope)EA2$ 3,300.00$ 6,600.00
3930" Double Mitered End Section (one MES @1:2 slope, One MES @1:4 slope)EA2$ 5,000.00$ 10,000.00
4018" RCP Storm PipeLF617$ 161.00$ 99,337.00
4130" RCP Storm PipeLF92$ 329.16$ 30,282.72
42Performance turf - SodSY7000$ 4.34$ 30,380.00
43Landscaping and IrrigationLS1$ 30,000.00$ 30,000.00
SUB-TOTAL$ 593,785.50
CONTINGENCY (15%)$ 89,067.82
TOTAL$ 682,853.32
ALTERNATE 3 – SEWER LIFT STATION AND FORCEMAIN
44Mobilization (5% of utility work)LS1$ 3,386.75$ 3,386.75
454" PVC (SDR35)(Sanitary Sewer, included cleanouts and connections)LF81$ 140.00$ 11,340.00
468" PVC (SDR35)(Sanitary Sewer)LF5180$ 900.008" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)8" PVC (SDR35)(Sanitary Sewer)
472" Forcemain (SDR21) (Sanitary Sewer, includes all bends, fittings, and connections)LF1400$ 30.00$ 42,000.00
482" Water service (HDPE, DR9 AWWA C906)LF708$ 30.00$ 21,240.00
492" gate valve w/ valve boxEA2$ 500.00$ 1,000.00
50Directional DrillLF30$ 55.00$ 1,650.00
51ManholeEA1$ 10,500.00$ 10,500.00
522" backflow (RPZ)LS1$ 2,000.00$ 2,000.00
532" water meterEA1$ 2,000.00$ 2,000.00
548"X8"x2" tapping sleeve and valveEA1$ 2,000.00$ 2,000.00
55Grinder Lift Station with AppurtenancesLS1$ 35,000.00$ 35,000.00
56BollardsEA4$ 300.00$ 1,200.00
57Site ElectricalLS1$ 15,000.00$ 15,000.00
SUB-TOTAL$ 149,216.75
CONTINGENCY (15%)$ 22,382.51
TOTAL$ 171,599.26
OPTIONAL PRICING (IF REQUESTED)
OPTION: Storage Area – 8 ft Interior Metal PanelsLS1
OPTION: Storage Area Floor Finish (Sealed Concrete)LS1
OPTION: Storage Area Floor Finish (Tnemec System)LS1
OPTION: Non-Impact Rated Doors/WindowsLS1
TOTAL BASE BID$ 1,624,045.09
TOTAL ALTERNATE 1$ 805,000.00
TOTAL ALTERNATE 2$ 682,853.32
TOTAL ALTERNATE 3$ 171,599.26$ 3,283,497.67