26 08 00 Commissioning of Electrical Systems.pdf

PDF 107 KB Posted

Attached to
Y1DA--648-349 Construct Space for the Surgical Service Minor Construction - Portland, OR VAMC
Solicitation number
IFB-36C77625B0017
Issued by

About this file

This specification document (Section 26 08 00) details the commissioning requirements for electrical systems in the VA Portland Healthcare System's Surgical Service Space Construction project. The document outlines the comprehensive commissioning process for electrical systems, which includes construction inspections, pre-functional checklists, contractor tests, systems functional performance testing, and training of VA personnel. Key requirements include coordination with a Commissioning Agent appointed by the VA, completion of detailed pre-functional checklists, conducting systems tests under various operating conditions, and providing training to VA operation and maintenance staff on the installed electrical systems. The commissioning process is intended to ensure thorough verification of system installation, performance, and operational readiness prior to final acceptance.

View the file

Other files

File Type Posted
Amendment 6 - 36C77625B0017 0006 8-12-2025.pdf PDF
20250811 - RFI TRACKING SHEET - SOLICITATION 36C77625B0017 - Project 648-349.pdf PDF
Amendment 5 - 36C77625B0017 0005 8-11-2025.pdf PDF
Wage rates Multnomah 8-8-2025.pdf PDF
20250807_RFI TRACKING SHEET - SOLICITATION 36C77625B0017 - Project 648-349.pdf PDF
Online Bid Opening Meeting Info.docx DOCX document
Amendment 4 - 36C77625B0017 0004 8-7-2025.pdf PDF
00 01 10 - Table of Contents.pdf PDF
Amendment 3 - 36C77625B0017 0003 7-30-25.pdf PDF
20250729_PVAMC Surgical Suite Expansion_Add001.pdf PDF
Wage rates Multnomah 7-25-2025.pdf PDF
As-Built Plan Roof Details.pdf PDF
RFI TRACKING SHEET - SOLICITATION 36C77625B0017 - Project 648-349.pdf PDF
100-SF-33 fan data.pdf PDF
Addendum 001 - MA Architects.pdf PDF
AHU 33 Terminal unit report.pdf PDF
Wage rates Multnomah 7-11-2025.pdf PDF
Amendment 2 - 36C77625B0017 0002 7-21-25.pdf PDF
Amendment 1 - 36C77625B0017 0001 7-10-25.pdf PDF
Wage rates Multnomah 7-4-2025.pdf PDF
Contractor sign in.pdf PDF
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 4 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 3.pdf PDF
Attachment 1 - 648-349 VAPHCS Specs 100Pct BID Set REV 3.pdf PDF
Attachment 7 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 6.pdf PDF
Attachment 10 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 9.pdf PDF
Attachment 2 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 1.pdf PDF
Attachment 14 - Infection Control Risk Assessement - ICRA 648-349.pdf PDF
Attachment 11 - Brand Name Justification - Portland_Redacted.pdf PDF
Attachment 8 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 7.pdf PDF
Attachment 17 - RFI TRACKING SHEET - SOLICITATION 36C77625B0017 - Project 648-349.xlsx XLSX spreadsheet
Attachment 12 - Wage rates Multnomah 5-30-2025.pdf PDF
Attachment 5 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 4.pdf PDF
IFB 36C77625B0017.pdf PDF
Attachment 13 - PreConstruction Risk Assessment - PCRA 648-349.pdf PDF
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 15 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 9 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 8.pdf PDF
Attachment 3 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 2.pdf PDF
Attachment 6 - 648-349 VAPHCS - Space for Surgical Service Plans BID Set Part 5.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERAN AFFAIRS

VA PORTLAND HEALTHCARE SYSTEM

PROJECT No.: 648-349

CONSTRUCT SPACE FOR SURGICAL SERVICE

100% Construction Documents

26 08 00 - 1

COMMISSIONING OF ELECTRICAL SYSTEMS 100%CD

SECTION 26 08 00

COMMISSIONING OF ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 26.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissioning the Facility electrical systems, related subsystems and related equipment. This

Section supplements the general requirements specified in Section 01 91

00 General Commissioning Requirements.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 26 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 26, is required in cooperation with the VA and the

Commissioning Agent.

PROJECT No.: 648-349

26 08 00 - 2

B. The Facility electrical systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements:

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of Electrical systems will require inspection of individual elements of the electrical systems construction throughout the construction period. The Contractor shall coordinate with the

Commissioning Agent in accordance with Section 01 91 00 and the

Commissioning plan to schedule electrical systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the

Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning

PROJECT No.: 648-349

26 08 00 - 3

Agent will select a broader sample of checklists for review. If the

Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 26 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected

Contractor tests at the sole discretion of the Commissioning Agent.

Contractor tests shall be completed prior to scheduling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS, for additional details.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent.

Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor

PROJECT No.: 648-349

26 08 00 - 4 shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00. The instruction shall be scheduled in coordination with the VA Resident Engineer after submission and approval of formal training plans. Refer to Section 01

91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 26 Sections for additional Contractor training requirements.

----- END -----