About this file
This document contains questions and answers related to a solicitation for mail screening support services. The solicitation requires the contractor to support a federal agency's mission to ensure all mail and parcels are free of hazardous materials by screening all items within one day of receipt unless otherwise approved. The contractor must provide screening operation related customer service and support security and logistics partners. The questions and answers clarify aspects of the statement of work, pricing, and evaluation factors such as specifying labor categories and pricing for firm fixed price and labor hour contract line items. No changes will be made to escalation rates in option periods or the tasks included in various contract line items.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# RFP Document Section Subsection Page # Line # Impact Question Government's Response
Attachment 1 PWS
AND
Solicitation
7.3. Technical Exhibit III – Estimated Workload
Data
AND
Section SF 1449 - CONTINUATION SHEET
BASE PERIOD (12 MONTHS) –
(TIME & MATERIAL)
AND
ITEM NO 0003
AND
N/A
AND
N/A
Critical
In the PWS (Technical Exhibit III, pg. 24), CLIN X003 (Base Period (12 Months) – (Time and Material)) specifies 2 FTE (3,912 hours) for the Transportation Specialist Labor Category supporting the following PWS Tasks:
• PWS 5.2 – Transportation Services
• PWS 5.3.1 – Receiving/X-ray Phase Support
• PWS 5.5 – Continuity of Screening Operations However, pg. 4 of the Solicitation states that CLIN X003 provides reimbursement of travel costs IAW Section 1.6.14 of the PWS and notes a not-to-exceed amount of $21,500. Section 1.6.14 of the PWS specifies ODCs for supplies, consumables and contingency support services. Further, Attachment 4 (Pricing Matrix - Pricing Summary) provides for a Quantity of “1” and a U/I of “Lot” and does not allow for pricing Transportation Specialist labor hours. CLIN X003 (and the associated outyear CLINS) as structured in the PWS/Solicitation does not address labor requirements for the Transportation Specialists. It seems appropriate to include Transportation Specialists in CLIN X001 and CLIN 0005, given that they support daily mail screening operations. Will the government please clarify where Transportation Specialists be priced?
Revisions made to Attachment 4 Pricing Matrix via Amend 0004. Changes made highlighted in yellow.
Labor Category(ies) for Base Period for both FFP CLINs and T&M CLINs. The proposed labor rates for Time and Material (T&M) CLINs and Labor Hour (LH) are part of the total evaluated price.
DO NOT PROVIDE PRICNG FOR T&M and LH CLINS - just the Labor Rates.
Transportation Specialists and other tasks noted on Technical Exhibit III of the PWS for X003 will be priced under CLIN X003.
2 Attachment 1 PWS 7.3. Technical Exhibit III – Estimated Workload Data
BASE PERIOD (12 MONTHS) –
(TIME & MATERIAL) 24 N/A Critical
In the PWS (Technical Exhibit III, pg. 24), CLIN X003 (Base Period (12 Months) – (Time and Material)) specifies support of PWS Tasks 5.2, 5.3.1, and 5.5 – Continuity of Screening Operations.
Including PWS Task 5.5 – Continuity of Screening Operations in CLIN X003 does not allow for accurate pricing of non-COOP Transportation Support Services. Recommend Transportation Services (Labor and ODCs) supporting PWS Task 5.5 be removed from CLIN X003 and included in CLIN X004.
There will be no changes regarding these tasks.
Solicitation
AND
Attachment 1 PWS
Section SF 1449 - CONTINUATION SHEET
AND
7.3. Technical Exhibit III – Estimated Workload
Data
ITEM NO 0001
AND
BASE PERIOD (11 MONTHS) –
FIRM FIXED PRICE (FFP)
AND
N/A
AND
N/A
Substantive Pg.3 of the Solicitation states that CLIN 0001 is 12 months, however, pg. 24 of the PWS states that CLIN 0001 is 11 months. Please clarify the length of performance. Revisions made to Solicitation via Amend 0004. Changes made highlighted in green.
4 Attachment 4 Pricing Matrix Tab 1- Pricing Summary Base Period: 12 Months N/A N/A Substantive Can you clarify why is CLIN 0005 is Labor Hours and CLIN 0001 is FFP, seems both should be FFP? CLIN 0005 is a labor hour CLIN because the Government intends to only pay for actual hours worked by the Contractor during the Phase-in Period. There will be no change to the contract type for these CLINs.
5 Solicitation Section SF 1449 - CONTINUATION SHEET
ITEM NO 0002
ITEM NO 0003
ITEM NO 0004 3 and 4 N/A Substantive
The current Not-To-Exceed costs for CLIN X002, CLIN X003, CLIN X004 do not allow for annual cost escalations. To allow offerors to account for inflation, will the government consider allowing for escalation in each option period? Recommend considering using standard government escalation rates.
Not-to-exceed ceilings were revised via Amend 0003. There will be no changes to escalation rates in each period.
6 Attachment 1 PWS 7.3. Technical Exhibit III – Estimated Workload Data Technical Exhibit III 24 N/A General Regarding Part 7, Technical Exhibit III, on page 24 of the Draft PWS, what is the intended purpose of separating labor hours into
CLIN 0001 (FFP), CLIN 0004 (T&M), and CLIN 0005?
For CLIN 0005, please see response to Question #4. In regards to CLIN 0004, it is an optional CLIN and will only be exercised to provide continuity of service in the event of unforeseen contingencies (see PWS Section 5.5).
7 Solicitation 52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014) ADDENDUM c. FACTOR 3 -- PRICE 29 N/A Substantive
In Solicitation Evaluation Criteria, para 3.c., FACTOR 3 - PRICE (VOLUME V) – PRICING MATRIX (Attachment 4), “Labor Hour” states: “The Offeror is required to propose against for the LH CLINs.” The last para of this section states: “The Government will provide dollar amounts for the Labor Hour and Time-and-Material (T&M) contract line item numbers (CLINs). NOTE: DO NOT PROPOSE COSTS FOR THESE CLINS. PLEASE LEAVE THESE CLINS BLANK.” This direction appears inconsistent, please clarify.
Labor Category(ies) for Base Period for both FFP CLINs and T&M CLINs. The proposed labor rates for Time and Material (T&M) CLINs and Labor Hour (LH) are part of the total evaluated price.
DO NOT PROVIDE PRICNG FOR T&M and LH CLINS - just the Labor Rates.
8 Attachment 1 PWS 7.3. Technical Exhibit III – Estimated Workload Data Technical Exhibit III 24 N/A Substantive Regarding Part 7, Technical Exhibit III, on page 24 of the Draft PWS, is it the Government's intent that offerors staff 2
Transportation Specialists in CLIN 0003 for a NTE value of $21,500? This also applies to option year CLINs." See response to Question #5.
9 Solicitation 52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014) ADDENDUM c. FACTOR 3 -- PRICE 29 N/A General Regarding Draft RFP Section F, Section 3. EVALUATION FACTORS, subsection c. FACTOR 3 -- PRICE, how are offerors expected to provide an accurate pricing summary if offerors are prohibited from proposing labor costs for T&M CLINs? See response to Question #7.
10 Attachment 4 Pricing Matrix Tab 1- Pricing Summary Base Period: 12 Months N/A N/A General Regarding the Attachment 4 Pricing Matrix, Tab 1 - Pricing Summary, how are offerors supposed to provide an accurate contract price if offerors are directed to not price CLINs 0002 through 0005? This also applies to option year CLINs. See response to Question #7.
11 Attachment 4 Pricing Matrix Tab 2 - LCAT (Base) N/A N/A N/A General Regarding Attachment 4 Pricing Matrix, Tab 2 - LCAT (Base), how are offerors supposed to provide an accurate contract price if offerors are prohibited from pricing T&M CLINs? See response to Question #7.
12 Attachment 4 Pricing Matrix Tab 2 - LCAT (Phase-In LH) N/A N/A N/A General Regarding Attachment 4 Pricing Matrix, Tab 2 - LCAT (Phase-In LH), Is it your intent that we do not provide values in Column L? See response to Question #7.
13 Attachment 1 PWS 7.3. Technical Exhibit III – Estimated Workload Data CLIN Tables 24 N/A General
Regarding DRAFT PWS Template, Part 7, Technical Exhibit III, each labor category is based off 1,872 productive hours per year except for the Transportation Specialists, which are based off of 1,956. Should all positions be based off 1,872 productive hours per year?
All firm fixed price (FFP) tasks are based on 1872 hours. The Offeror is not required to base its proposal on the Government estimates. The Government is evaluating the Offerors' approach to meeting the technical requirements.
14 Draft RFP Section B Section SF 1449 - CONTINUATION SHEET
ITEM NO 0002
ITEM NO 0003
ITEM NO 0004
4 N/A General Regarding RFP Section B, Section SF 1449 - CONTINUATION SHEET, Page 4, we are provided NTE values for X002, X003, and X004 CLINs, why are offerors prohibited from pricing these CLINs? See response to Question #7.
File details come from the government source that posted it. Updated .