J.2 Incentive Award Fee Plan JAN22.pdf

PDF 796 KB Posted

Attached to
EMERALD Follow-on: "CLOVER" Multiple-Award IDIQ Contract (Amendment 0005)
Solicitation number
HM0476-21-R-0023
Issued by

View the file

Other files

File Type Posted
Sol_HM047621R0023_Amd 0005_28MAR22.pdf PDF
J.17 Self-Scoring Sheet 18MAR22.xlsx XLSX spreadsheet
Sol_HM047621R0023_Amd 0005_28MAR22 Markup.pdf PDF
Sol_HM047621R0023_Amd 0004_08MAR22.pdf PDF
J.17 Self-Scoring Sheet 1MAR22.xlsx XLSX spreadsheet
J.19 Past Performance Questionnaire 08MAR22 Markup.docx DOCX document
J.19 Past Performance Questionnaire 08MAR22.docx DOCX document
Sol_HM047621R0023_Amd 0004_08MAR22 Markup.pdf PDF
J.17 Self-Scoring Sheet 1MAR22 Markup.xlsx XLSX spreadsheet
Sol_HM047621R0023_Amd 0003 Consolidated Markup_11FEB22.pdf PDF
Sol_HM047621R0023_Amd 0003 Consolidated_11FEB22.pdf PDF
J.18 Relevant Experience Project Template JAN22.docx DOCX document
Sol_HM047621R0023_Amd 0002 Consolidated_04FEB22.pdf PDF
J.19 Past Performance Questionnaire 03FEB22.docx DOCX document
J.17 Self-Scoring Sheet JAN22.xlsx XLSX spreadsheet
CLOVER QAs_Amd 0002_04FEB22.pdf PDF
J.7 NDA JAN22.pdf PDF
J.1 Multiple-Award IDIQ SOW 03FEB22.pdf PDF
HM047621R0023-0001 CLOVER RFP - Amendment 1.pdf PDF
J.5a Resume Template APR2021.docx DOCX document
J.10 Monthly Staff Report Template JUN2021.xlsx XLSX spreadsheet
J.15 Labor Rate Matrix - Task Order Template JUN2021.xlsx XLSX spreadsheet
J.9 Travel Template JUN2021.xlsx XLSX spreadsheet
J.7 NDA MAY2021.docx DOCX document
CLOVER RFP HM047621R0023 Question and Answer Template.xlsx XLSX spreadsheet
J.21 Telework Plan Template JUN2021.docx DOCX document
J.20 FCL Information Template MAY2021.docx DOCX document
J.19 Past Performance Questionnaire v3 9DEC2021.docx DOCX document
J.5b Resume Instructions APR2021.docx DOCX document
J.1 Multiple-Award IDIQ SOW v6_28SEP2021.pdf PDF
J.18 Relevant Experience Project Template JUN2021.docx DOCX document
J.23 FCL Application Supporting Documentation.docx DOCX document
J.4 Skill Definition MAY2021.docx DOCX document
CLOVER RFP HM047621R0023.pdf PDF
J.2 Incentive Award Fee Plan JUL2021_FDOsigned.pdf PDF
J.13 Monthly Activity Report Template APR2021.docx DOCX document
J.3 Labor Rate Matrix - IDIQ Template JUN2021.xlsx XLSX spreadsheet
J.14 Weekly Activity Report Template APR2021.docx DOCX document
J.8 DD254 DRAFT 11MAR2021 v1.pdf PDF
J.17 Self-Scoring Sheet v3 12JUN2021.xlsx XLSX spreadsheet
J.22 FCL_Orientation_Handbook_9_March_2021.pdf PDF
J.11 Monthly Financial Report CV Template JUN2021.xlsx XLSX spreadsheet
J.12 Monthly Financial Report Burn Rate Template JUN2021.xlsx XLSX spreadsheet
J.16 Position Matrix Template MAY2021.xlsx XLSX spreadsheet
J.6 OCI Disclosure and Analysis Form MAY2021.doc DOC document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

(U) HM0476-21-R-0023

(U) Section J Attachment 3

(U) National Geospatial-Intelligence Agency (NGA)

CLOVER

(EMERALD FOLLOW-ON)

(U) Solicitation HM0476-21-R-0023

(U) IDIQ Incentive Award Fee Plan

(U) Version: Amendment 0002

(U) January 2022

CLOVER HM0476-21-R-00023

Section J, Attachment 2 Incentive Award Fee Plan

Amendment 0002

1. NGA will provide an annual performance incentive award fee in addition to the FFP- LOE price of each task order. There will be two performance incentives eligible:

a. Staff Retention – 1% of the Awarded Value commencing at the start of each Period of

Performance (POP) and evaluated at the end of each OY POP.

b. Staff Vacancy – 1% of the Awarded Value commencing at the start of each POP and evaluated at the end of each POP.

2. Staff Retention – Staff Retention provides an important factor in successful performance. In order to highlight the importance of retaining staff throughout the life of the program. The government will provide an incentive to vendors to retain staff throughout the life of the program and the specific requirement. This award will be granted based upon the retention rate of staff on an annual basis.

GOAL: The vendor will retain at least 90% of the staff assigned to a task order from day one of the period of performance to the last day of the period of performance, in the position they are initially assigned to.

Methodology of Calculations:

Base Year – percentage will be calculated from the date of onboarding to NGA to the last day of the period of performance.

Option Year – percentage will be calculated annually from the first to the last day of the period of performance.

Award amount calculation:

1. Staff retention will be calculated by dividing the number of active staff at the end of each POP from the total number of staff assigned on the first day of the Period of Performance, that are still assigned to their original positions. 1% of the Awarded Value on day one of the Period of Performance for those positions will be the total incentive amount and will be listed under a separate CLIN.

2. Any position up-scope added after day one of the Period of Performance will not be counted in that year but will be added to subsequent option years.

3. Any position that is de-scoped after day one of the period of performance will count towards the award, as it has already been calculated into the total amount allowable.

Schedule:

1. No less than 20 calendar days before the end of a period of performance the vendor shall notify the Government if it believes it is qualifies for the award.

Section J, Attachment 2

2. No more than 10 calendar days after the end of a period of performance the vender shall submit a report that demonstrates the staff, by position, on day one of the period of performance and the staff on the last day of the period of performance. This report shall be included in a separate invoice for the award.

3. The COR will validate the report and if approved will certify the award invoice no more than 30 calendar days after submission.

3. Staff Vacancy –

Vacant positions cause an unnecessary burden for the government and is not inclusive of a positive and productive use of resources. In order to limit staff vacancies the government will provide an incentive to vendors to limit the vacancy rates of the assigned positions on each task order. This award will be granted, based upon the vacancy rate of the total positions on a bi-annual basis.

GOAL: The vendor will have staffed at least 90% of all billets assigned to a task order.

Methodology of Calculations:

Base Year – percentage will be calculated from +20 days from the date of task order award to the last day of the period of performance.

Option Year – percentage will be calculated annually from the first to the last day of the period of performance. .

Award amount calculation:

1. Staff vacancy will be determined from the total number of staff assigned on the first day of the Period of Performance. 1% of the Awarded Value on day one of the Period of Performance for those positions will be the total incentive amount and will be listed under a separate CLIN.

2. Any position up-scope added after day one of the Period of Performance will be counted in that year and will be added to subsequent option years.

a. An adjustment will be added to the incentive CLIN when the position is up-scoped.

b. The initial date of 20 days after award of the position will be utilized to calculate the vacancy rate.

3. Any position that is de-scoped after day one of the period of performance will be counted towards the award, as both a positive and negative towards the final calculation, for the days that it was an active position on the task order.

Section J, Attachment 2

4. For the purposes of this award, any vacant position shall be considered filled once an official eNom has been submitted and accepted by the government.

5. If a vendor has been requested to keep a position vacant by the contracting officer at any time during the life of this contract, this vacancy will not be counted as a negative in the formulation of the vacancy percentage rate.

a. This shall be documented by the vendor and provided as supporting documentation in an end of option year report to the government.

Schedule:

1. No less than 20 calendar days before the end of a period of performance the vendor shall notify the Government if it believes it qualifies for the award.

2. No more than 10 calendar days after the end of a period of performance the vender shall submit a report that demonstrates the vacancy rate of all positions along with any supporting documentation to support the claim of an 90% staffing rate or higher.

This report shall be included in a separate invoice for the award.

3. The COR will validate the report and if approved will certify the award invoice no more than 30 days after submission.

X___________________________ M. Brian Mosteller Fee Determining Official

//Original Signed//